| Owner | Filings | Most Recent |
|---|---|---|
| ATTARI REALTY | 3 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| PARKER AND WEST ENGINEERING, PLLC | 1 | 12/11/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| SUNRUN | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SUNRUN INSTALLATION SVC | General Contractor | 2 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PARKER AND WEST ENGINEERI | 5272 | 1 | 12/11/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | SUNRUN INSTALLATION SVC | 12/18/2024 |
| BIS | PL | ISSUED | CITY TESTING & PLUMBING I | 02/15/2007 |
| BIS | EQ | ISSUED | STATE BUILDERS CORP. | 02/09/2004 |
| BIS | — | ISSUED | STATE BUILDERS CORP. | 02/09/2004 |
| BIS | PL | ISSUED | WAGNER ZIV PLUMBING & HEATING CO | 10/23/2003 |
| BIS | — | ISSUED | STATE BUILDERS CORP. | 07/11/2003 |
| BIS | EQ | ISSUED | STATE BUILDERS CORP. | 07/11/2003 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/06/2024 | Complete | SUNRUN SOLAR ELECTL CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/11/2024 | Signed-off | SUNRUN INSTALLATION SVC | 25 panels, 10.25 kw, 528 roof_area_sqft |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/27/2024 | Fire-Resistant Penetrations and Joints | Walid Abdulla | special |
| 11/27/2024 | Structural Stability – Alterations of existing buildings | Walid Abdulla | special |
| 11/27/2024 | Energy Code Compliance Inspections | Walid Abdulla | progress |
| 11/27/2024 | Final | Walid Abdulla | progress |
| 11/27/2024 | Air barrier - visual inspection | Walid Abdulla | energy_progress |