| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 02/03/2026 | $1.2M | — | 118-64 RIVERTON ST LLC → Private party | $813/sf building |
| 04/29/2025 | $720K | — | Private party → 118-64 RIVERTON ST LLC | $468/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| J.k.design | 7 | 03/19/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Infiniti Electric | Electrical | 1 | 03/22/2026 |
| Allied Safety Consultants | General Contractor | 1 | 04/09/2026 |
| Tri City Mechanical Group | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Askon Architect | 3596 | 7 | 03/19/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | Flavio Mechanical | 10/21/2025 |
| DOB NOW | Structural | Permit Issued | Allied Safety Consultants | 10/16/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/19/2026 | Signed-off | Tri City Mechanical Group | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/29/2025 | Complete | Infiniti Electric | General Wiring |
| 05/19/2025 | Complete | Infiniti Electric | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/19/2026 | Signed-off | Tri City Mechanical Group | Wood |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/27/2026 | Fire-Resistant Penetrations and Joints | Akeeb Shekoni | special |
| 03/27/2026 | Structural Stability – Alterations of existing buildings | Akeeb Shekoni | special |
| 03/27/2026 | Final | HANSA PERSAUD | progress |
| 03/27/2026 | Fire-Resistance Rated Construction | Akeeb Shekoni | progress |
| 03/27/2026 | Energy Code Compliance Inspections | Akeeb Shekoni | progress |
| 03/27/2026 | Structural Wood Frame | Akeeb Shekoni | progress |
| 03/27/2026 | Air barrier - visual inspection | Akeeb Shekoni | energy_progress |
| 03/27/2026 | Electric vehicle service equipment requirements | Akeeb Shekoni | energy_progress |
| 03/27/2026 | Interior lighting power | Akeeb Shekoni | energy_progress |
| 03/27/2026 | Fenestration areas | Akeeb Shekoni | energy_progress |
| 03/27/2026 | Permanent certificate | Akeeb Shekoni | energy_progress |
| 03/27/2026 | Insulation placement and R values | Akeeb Shekoni | energy_progress |
| 03/27/2026 | Maintenance information | Akeeb Shekoni | energy_progress |
| 03/27/2026 | Fenestration and door U-factor and product ratings | Akeeb Shekoni | energy_progress |
| 03/27/2026 | Fenestration air leakage | Akeeb Shekoni | energy_progress |
| 03/27/2026 | Metering | Akeeb Shekoni | energy_progress |
| 01/20/2026 | Maintenance information | Akeeb Shekoni | energy_progress |
| 01/20/2026 | Fire-Resistant Penetrations and Joints | Akeeb Shekoni | special |
| 01/20/2026 | Energy Code Compliance Inspections | Akeeb Shekoni | progress |
| 01/20/2026 | HVAC-R and service water heating equipment | Akeeb Shekoni | energy_progress |
| 01/20/2026 | HVAC-R and service water heating system controls | Akeeb Shekoni | energy_progress |
| 01/20/2026 | HVAC-R and service water piping design and insulation | Akeeb Shekoni | energy_progress |
| 11/27/2025 | Fire-Resistant Penetrations and Joints | Akeeb Shekoni | special |
| 11/27/2025 | Energy Code Compliance Inspections | Akeeb Shekoni | progress |
| 11/27/2025 | HVAC-R and service water heating equipment | Akeeb Shekoni | energy_progress |