← Back
One family attached or semi-detached
119 PENDLETON PLACE
STATEN ISLAND · BIN 5002065
💬 Discuss this project
1943Year Built
2Stories
A5Building Class
R3-2Zoning
1,240 sfGross Floor Area
1Units
One family attached or semi-detached · 2,000 sf lot · 0.62 FAR built · Flood zone X
Locations of Work
Architecture
Roof1p · 1 filing · 7 docs
Basement1p · 1 filing · 7 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
M-CON ENGINEERING, PC102/20/2025
MICHAEL DERUVO & ASSOC. ARCHITECTS212/18/2020
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
PATRICIA L. GASS403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUSTAINABLE STRATEGIESGeneral Contractor203/21/2026
KCM PLUMBING & HEATING COPlumbing207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
M-CON ENGINEERING7341102/20/2025
Building Lifecycle
All (7)Filed (3)Permit Issued (3)Signed Off (1)
04/10/2025
Signed off — Alteration
INSTALLATION OF SOLAR ELECTRIC GENERATION SYSTEM FOR UTILITY INTERCONNECTION
S01184327-I1
02/28/2025
Permit issued — Solar
S01184327-I1-SL
02/20/2025
Filed — Alteration
INSTALLATION OF SOLAR ELECTRIC GENERATION SYSTEM FOR UTILITY INTERCONNECTION
S01184327-I1
05/07/2021
Permit issued — Plumbing
S00437245-I1-PL
02/16/2021
Permit issued — Plumbing
S00437245-I1-PL
12/18/2020
Filed — Alteration
APPLICATION FILED TO REMOVE OLD HW HEATER AND BOILER AND INSTALL (1) NEW GAS HW HEATER AND (1) NEW GAS BOILER WITH NEW GAS PIPING AT CELLAR OF EXISTING RESIDENCE.
S00437245-P1
12/09/2020
Filed — Alteration
APPLICATION FILED TO REMOVE OLD HW HEATER AND BOILER AND INSTALL (1) NEW GAS HW HEATER AND (1) NEW GAS BOILER WITH NEW GAS PIPING AT CELLAR OF EXISTING RESIDENCE.
S00437245-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSUSTAINABLE STRATEGIES02/28/2025
DOB NOWPlumbingSigned-offKCM PLUMBING & HEATING CO05/07/2021
DOB NOWPlumbingSigned-offKCM PLUMBING & HEATING CO02/16/2021
1 job · most recent 12/18/2020
Gas
FiledStatusContractorScope
12/18/2020Signed-offKCM PLUMBING & HEATING COGas
1 job · most recent 01/31/2025
FiledStatusContractorScope
01/31/2025CompleteSOURCE ELECTRIC INC1 meters
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
02/20/2025Fire-Resistant Penetrations and JointsMichelle Contrispecial
02/20/2025Structural Stability – Alterations of existing buildingsMichelle Contrispecial
02/20/2025Energy Code Compliance InspectionsMichelle Contriprogress
02/20/2025FinalMichelle Contriprogress
02/20/2025Air barrier - visual inspectionMichelle Contrienergy_progress
▾Documents — 11 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch - Plumbing2
08/25/2026S00437245-I1Request digital key ↗
08/15/2026S00437245-P1Request digital key ↗
▸DOB NOWPlans/Sketch1
08/20/2026S01184327-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/25/2026S00437245-P1Open ↗
08/25/2026S00437245-I1Open ↗
08/13/2026S01184327-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
09/01/2026S01184327-I1Open ↗
09/01/2026S01184327-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
09/01/2026S01184327-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026S01184327-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026S01184327-I1Open ↗