← Back
Factory, light manufacturing
12-04 44 AVENUE
QUEENS · BIN 4005228
💬 Discuss this project
1931Year Built
1Stories
F5Building Class
M1-4AZoning
10,000 sfGross Floor Area
1Units
2 Open Violations 1 unresolved · 1 paperwork only ▸
Factory, light manufacturing · Owner of record: 12-12 44TH AVENUE NEW LLC · 10,000 sf lot · 1 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbingFire ProtectionGeneral
Roof1p · 1 filing · 12 docs
Floor 125p · 5 filings · 20 docs
Mezzanine12p · 3 filings · 20 docs
Cellar1p · 1 filing · 11 docs
Basement1p · 2 filings · 15 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
05/03/2022$4.7M—— → —$470/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PARALLEL ARCHITECTURAL GROUP, LLC1107/25/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
S M EXPEDITING2203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BENJAMIN DREBINElectrical103/21/2026
NEW ERA MECH SERVICE INCFire Protection107/08/2026
ART OF CONSTRUCTIONGeneral Contractor107/08/2026
NEW ERA MECHANICAL SER INPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SKYLINE ENGINEERING, PLLC267705/19/2023
Building Lifecycle
All (50)Filed (11)Permit Issued (3)Violation (2)Inspection (17)Objection (4)Special Inspection (13)
06/08/2026
Inspection — Pass-Final SP Permit Withdrawal
Pass
View inspection ↗
04/21/2026
Inspection — Fail-Final SP Permit Withdrawal
Fail
View inspection ↗
11/21/2023
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
11/17/2023
Inspection — Certified Sprinkler (SP) - Booster Pump Test
Certified
View inspection ↗
11/17/2023
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
08/11/2023
Special inspection requirement — Final
Matthew Wavro
07/25/2023
Filed — Alteration
ALTERATION TO INTERIOR SPACE TO ACCOMMODATE NEW SELF-SERVE LAUNDRY FACILITY (UG 6). RELOCATING BATHROOM BREAK ROOM & STAIRS. NEW PODIUM FOR WASHERS & ENCLOSURE FOR DRYERS AS SHOWN ON PLANS. THERE IS NO CHANGE IN USE, OCCUPANCY OR EGRESS.
Q08007931-P2
07/20/2023
Special inspection requirement — Final
Matthew Wavro
06/07/2023
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
05/25/2023
Objection resolved — Addressed
05/24/2023
Objection raised — Scope
05/19/2023
Filed — Alteration
Installation of new new self-service laundry facility (U.G. 6) . New washers, dryers, and bathrooms and water heater as shown on plans.
Q00763505-P2
05/16/2023
Special inspection requirement — Sprinkler Systems
Matthew Wavro
05/16/2023
Special inspection requirement — Energy Code Compliance Inspections
Matthew Wavro
05/10/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/01/2023
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
04/25/2023
Special inspection requirement — Mechanical Systems
Matthew Wavro
04/25/2023
Special inspection requirement — Energy Code Compliance Inspections
Matthew Wavro
04/25/2023
Special inspection requirement — Final
Matthew Wavro
04/24/2023
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
04/24/2023
Inspection — Certified Sprinkler - SP - Roughing
Certified
View inspection ↗
04/18/2023
Filed — Alteration
Installation of new new self-service laundry facility (U.G. 6) . New washers, dryers, and bathrooms and water heater as shown on plans.
Q00763505-P1
04/18/2023
Filed — Alteration
Installation of new exhaust and fresh intake ventilation for new dryers including dryer exhaust ductwork for break room and bathrooms for non-self serve laundromat. No change in occupancy, use or egress.
Q00763036-P1
04/17/2023
Special inspection requirement — Final
Matthew Wavro
04/17/2023
Special inspection requirement — Energy Code Compliance Inspections
Matthew Wavro
04/17/2023
Special inspection requirement — Mechanical Systems
Matthew Wavro
03/23/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
02/02/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
02/02/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
01/31/2023
Special inspection requirement — Sprinkler Systems
Matthew Wavro
01/25/2023
Filed — Alteration
Installation of new sprinkler heads for dryers as shown on submitted plans. No change in occupancy, use or egress.
Q08004312-P1
01/24/2023
Special inspection requirement — Sprinkler Systems
Matthew Wavro
01/18/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/19/2022
Filed — Alteration
ALTERATION TO INTERIOR SPACE TO ACCOMMODATE NEW SELF-SERVE LAUNDRY FACILITY (UG 6). RELOCATING BATHROOM BREAK ROOM & STAIRS. NEW PODIUM FOR WASHERS & ENCLOSURE FOR DRYERS AS SHOWN ON PLANS. THERE IS NO CHANGE IN USE, OCCUPANCY OR EGRESS.
Q08007931-P1
12/15/2022
Special inspection requirement — Final
Matthew Wavro
11/09/2022
Permit issued — Mechanical Systems
Q00763036-I1-MS
11/09/2022
Permit issued — Plumbing
Q00763505-I1-PL
11/09/2022
Permit issued — Sprinklers
Q08004312-I1-EW-SP
09/22/2022
Filed — Alteration
ALTERATION TO INTERIOR SPACE TO ACCOMMODATE NEW SELF-SERVE LAUNDRY FACILITY (UG 6). RELOCATING BATHROOM BREAK ROOM & STAIRS. NEW PODIUM FOR WASHERS & ENCLOSURE FOR DRYERS AS SHOWN ON PLANS. THERE IS NO CHANGE IN USE, OCCUPANCY OR EGRESS.
Q08007931-I1
09/15/2022
Filed — Alteration
Installation of new sprinkler heads for dryers as shown on submitted plans. No change in occupancy, use or egress.
Q08004312-I1
09/13/2022
Objection raised — Scope
07/05/2022
Objection raised — Scope
06/27/2022
Filed — Alteration
Installation of new exhaust and fresh intake ventilation for new dryers including dryer exhaust ductwork for break room and bathrooms for non-self serve laundromat. No change in occupancy, use or egress.
Q00763036-I1
06/27/2022
Filed — Alteration
Installation of new new self-service laundry facility (U.G. 6) . New washers, dryers, and bathrooms and water heater as shown on plans.
Q00763505-I1
06/23/2022
Filed — Alteration
Q00756801-I1
03/14/2022
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
03/14/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
03/14/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
04/06/2016
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
01/15/2016
Violation issued (ECB, open)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedART OF CONSTRUCTION11/09/2022
DOB NOWPlumbingPermit IssuedNEW ERA MECHANICAL SER IN11/09/2022
DOB NOWSprinklersPermit IssuedNEW ERA MECH SERVICE INC11/09/2022
BISOTISSUEDSEA BRIGHT SOLAR LLC07/05/2023
BISOTISSUEDJELM CONTRACTOR CORP11/29/2016
BISPLISSUEDFERKO PLUMBING & HEATING11/29/2016
BISPLISSUEDFERKO PLUMBING & HEATING11/07/2016
BISMHISSUEDJELM CONTRACTOR CORP04/14/2016
BISPLISSUEDPRECISION PLBG SVCS., INC01/29/2016
BISOTISSUEDEMB CONTRACTING CORP03/11/2014
1 project · most recent 04/18/2023
Associated Ducts and Piping Ventilation Systems
FiledStatusContractorScope
04/18/2023Permit IssuedART OF CONSTRUCTIONAssociated Ducts and Piping, Ventilation Systems
1 project · most recent 01/25/2023
FiledStatusContractorScope
01/25/2023Permit IssuedNEW ERA MECH SERVICE INC28 heads
1 project · most recent 05/19/2023
Gas Water/Sanitary
FiledStatusContractorScope
05/19/2023Permit IssuedNEW ERA MECHANICAL SER INGas, Water/Sanitary
3 projects · most recent 03/22/2024
General Wiring
FiledStatusContractorScope
03/22/2024CompleteOGC ELECTRICAL CONTRACTORGeneral Wiring
11/10/2023CompleteAMBER ELECTL CONTNG INC—
02/28/2023CancelledOPTIMUM ELECTL CONTNG LLCGeneral Wiring
▾Field Inspections (DOB CAP) — 17
DateTypeResultReport
06/08/2026Pass-Final SP Permit WithdrawalPassView ↗
04/21/2026Fail-Final SP Permit WithdrawalFailView ↗
11/21/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
11/17/2023Certified Sprinkler (SP) - Booster Pump TestCertifiedView ↗
11/17/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
06/07/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
05/10/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/01/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
04/24/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
04/24/2023Certified Sprinkler - SP - RoughingCertifiedView ↗
03/23/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
02/02/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
02/02/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
01/18/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/14/2022Certified Gas-Gas-Piping-RoughingCertifiedView ↗
03/14/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
03/14/2022Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 13
DateRequirementInspectorRole
08/11/2023FinalMatthew Wavroprogress
07/20/2023FinalMatthew Wavroprogress
05/16/2023Sprinkler SystemsMatthew Wavrospecial
05/16/2023Energy Code Compliance InspectionsMatthew Wavroprogress
04/25/2023Mechanical SystemsMatthew Wavrospecial
04/25/2023Energy Code Compliance InspectionsMatthew Wavroprogress
04/25/2023FinalMatthew Wavroprogress
04/17/2023FinalMatthew Wavroprogress
04/17/2023Energy Code Compliance InspectionsMatthew Wavroprogress
04/17/2023Mechanical SystemsMatthew Wavrospecial
01/31/2023Sprinkler SystemsMatthew Wavrospecial
01/24/2023Sprinkler SystemsMatthew Wavrospecial
12/15/2022FinalMatthew Wavroprogress
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Fs LaundryOther—
Project Q00763036 Alteration · Permit Entire · 06/27/2022
Read from each project’s drawing title blocks and cover sheets and checked twice; a name appears only when it is the occupant, never the owner, landlord or designer.
▾Documents — 116 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch11
08/26/2026Q00756801-I1Request digital key ↗
08/25/2026Q08007931-I1Request digital key ↗
08/25/2026Q08007931-P1Request digital key ↗
Showing 3 of 11 on file for this type
▸Applications & Permits16
▸BISPLAN / WORK APPROVAL APPLICATION9
09/06/2023440787070Open ↗
07/14/2023440787070Open ↗
06/23/2023440787070Open ↗
Showing 3 of 9 on file for this type
▸BISWORK PERMIT APPLICATION7
07/05/2023440787070Open ↗
11/30/2016421094755Open ↗
11/30/2016421094755Open ↗
Showing 3 of 7 on file for this type
▸Seals & Professional Certifications35
▸DOB NOWDPL-1: Design Professional Seal & Signature11
08/25/2026Q08004312-P1Open ↗
08/25/2026Q08004312-I1Open ↗
08/24/2026Q00763505-P1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWProgress Inspector Seal & Signature8
09/02/2026Q00763036-I1Open ↗
09/02/2026Q00763036-I1Open ↗
09/01/2026Q00763505-P2Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
09/02/2026Q00763036-I1Open ↗
09/01/2026Q00763505-P2Open ↗
08/27/2026Q08004312-P1Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST4
11/30/2016421094755Open ↗
04/21/2016421313518Open ↗
04/21/2016421313518Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION3
11/30/2016421094755Open ↗
04/21/2016421313518Open ↗
03/17/2014420955764Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT2
11/30/2016421094755Open ↗
03/17/2014420955764Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
06/12/2023440787070Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
06/12/2023440787070Open ↗
▸Trade Schedules & Equipment5
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE5
07/31/2017420955764Open ↗
04/11/2017421094755Open ↗
02/25/2017421094755Open ↗
Showing 3 of 5 on file for this type
▸Safety & Tenant Protection2
▸BISTenant Protection Plan and Notes1
04/21/2016421313518Open ↗
▸BISTPP1: TENANT PROTECTION PLAN1
06/28/2023440787070Open ↗
▸Environmental & Asbestos14
▸DOB NOWDEP ACP-5: Asbestos Assessment Report11
08/25/2026Q08004312-I1Open ↗
08/25/2026Q08004312-P1Open ↗
08/24/2026Q00763505-I1Open ↗
Showing 3 of 11 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)3
06/12/2023440787070Open ↗
11/30/2016421094755Open ↗
03/17/2014420955764Open ↗
▸Energy Compliance9
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
05/14/2024440787070Open ↗
06/28/2023440787070Open ↗
06/12/2023440787070Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS2
12/01/2016421094755Open ↗
03/17/2014420955764Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
09/27/2023440787070Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
05/14/2024440787070Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (FINAL)1
05/14/2024440787070Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
06/12/2023440787070Open ↗
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: RESPONSIBILITY3
05/14/2024440787070Open ↗
06/28/2023440787070Open ↗
06/12/2023440787070Open ↗
▸Approvals, Objections & Sign-offs5
▸BISADMINISTRATIVE OBJECTIONS3
12/01/2016421094755Open ↗
04/21/2016421313518Open ↗
03/17/2014420955764Open ↗
▸BISSUPERSEDING LETTER1
11/09/2016420955764Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
05/15/2024440787070Open ↗
▸Cost, Insurance & Ownership6
▸BISCOST AFFIDAVIT5
09/07/2023440787070Open ↗
06/12/2023440787070Open ↗
11/30/2016421094755Open ↗
Showing 3 of 5 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
05/14/2024440787070Open ↗
▸Filing & Intake Forms10
▸BISADDITIONAL INFORMATION6
09/27/2023440787070Open ↗
09/27/2023440787070Open ↗
08/10/2023440787070Open ↗
Showing 3 of 6 on file for this type
▸BISEFILING COVER SHEET3
11/29/2016421094755Open ↗
04/21/2016421313518Open ↗
03/17/2014420955764Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1