← Back
Two stories - detached, small or mid-size
12-43 162 STREET
QUEENS · Whitestone-Beechhurst · BIN 4620932
💬 Discuss this project
2021Year Built
2.5Stories
A1Building Class
R2AZoning
2,980 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · Owner of record: HUIWEI REALTY LLC · 5,050 sf lot · 0.59 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
HUIWEI REALTY303/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
07/26/2019$853K—— → —— not available
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AMERILAND BROOK LLC509/18/2023
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
DHC CONTRACTING INCGeneral Contractor107/08/2026
DYNASTY CONTRACTING LLCGeneral Contractor107/08/2026
THC CONSTRUCTION INCGeneral Contractor107/08/2026
WATSON'S PLBG, HTG, & BDGPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AMERILAND BROOK LLC1506304/29/2023
Building Lifecycle
All (42)Filed (5)Permit Issued (4)Signed Off (3)Inspection (6)Special Inspection (24)
10/20/2023
Signed off — Alteration
FILE PL WORKTYPE IN CONJUNCTION WITH NB JOB#421735386
Q00321170-I1
10/20/2023
Signed off — Alteration
INSTALL 12' DROP CURB WITH 1'-6" SPLAYS ON BOTH SIDE.
Q00863700-I1
10/16/2023
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
09/22/2023
Permit issued — Curb Cut
Q00863700-I1-CC
09/18/2023
Filed — Alteration
INSTALL 12' DROP CURB WITH 1'-6" SPLAYS ON BOTH SIDE.
Q00863700-I1
07/17/2023
Signed off — Alteration
INSTALL CONSTRUCTION FENCE AT ABOVE ADDRESS. NO CHANGE IN USE, OCCUPANCY OR EGRESS.
Q00433487-I1
05/01/2023
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
XIAOHONG ZHAO
05/01/2023
Special inspection requirement — Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities
XIAOHONG ZHAO
05/01/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
XIAOHONG ZHAO
05/01/2023
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
XIAOHONG ZHAO
05/01/2023
Special inspection requirement — Energy Code Compliance Inspections
XIAOHONG ZHAO
05/01/2023
Special inspection requirement — HVAC insulation and sealing
XIAOHONG ZHAO
05/01/2023
Special inspection requirement — HVAC and service water heating equipment
XIAOHONG ZHAO
05/01/2023
Special inspection requirement — HVAC and service water heating system controls
XIAOHONG ZHAO
04/29/2023
Filed — Alteration
FILE PL WORKTYPE IN CONJUNCTION WITH NB JOB#421735386
Q00321170-P2
04/22/2023
Special inspection requirement — HVAC and service water heating equipment
XIAOHONG ZHAO
04/22/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
XIAOHONG ZHAO
04/22/2023
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
XIAOHONG ZHAO
04/22/2023
Special inspection requirement — Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities
XIAOHONG ZHAO
04/22/2023
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
XIAOHONG ZHAO
04/22/2023
Special inspection requirement — Energy Code Compliance Inspections
XIAOHONG ZHAO
04/22/2023
Special inspection requirement — HVAC insulation and sealing
XIAOHONG ZHAO
04/22/2023
Special inspection requirement — HVAC and service water heating system controls
XIAOHONG ZHAO
09/16/2022
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
09/16/2022
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
09/16/2022
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
09/16/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
09/16/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
09/03/2022
Filed — Alteration
FILE PL WORKTYPE IN CONJUNCTION WITH NB JOB#421735386
Q00321170-P1
09/03/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
XIAOHONG ZHAO
09/03/2022
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
XIAOHONG ZHAO
09/03/2022
Special inspection requirement — Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities
XIAOHONG ZHAO
09/03/2022
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
XIAOHONG ZHAO
09/03/2022
Special inspection requirement — Energy Code Compliance Inspections
XIAOHONG ZHAO
09/03/2022
Special inspection requirement — HVAC insulation and sealing
XIAOHONG ZHAO
09/03/2022
Special inspection requirement — HVAC and service water heating system controls
XIAOHONG ZHAO
09/03/2022
Special inspection requirement — HVAC and service water heating equipment
XIAOHONG ZHAO
05/11/2022
Permit issued — Plumbing
Q00321170-I1-PL
03/24/2022
Permit issued — Construction Fence
Q00433487-I1-FN
09/13/2021
Permit issued — Construction Fence
Q00433487-I1-FN
09/04/2021
Filed — Alteration
INSTALL CONSTRUCTION FENCE AT ABOVE ADDRESS. NO CHANGE IN USE, OCCUPANCY OR EGRESS.
Q00433487-I1
11/26/2020
Filed — Alteration
FILE PL WORKTYPE IN CONJUNCTION WITH NB JOB#421735386
Q00321170-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWCurb CutSigned-offTHC CONSTRUCTION INC09/22/2023
DOB NOWPlumbingSigned-offWATSON'S PLBG, HTG, & BDG05/11/2022
DOB NOWConstruction FenceSigned-offALEXANDER CHAN03/24/2022
DOB NOWConstruction FenceSigned-offDYNASTY CONTRACTING LLC09/13/2021
BIS—ISSUEDTHC CONSTRUCTION INC08/01/2023
BIS—ISSUEDDHC CONTRACTING INC10/18/2022
BIS—ISSUEDDHC CONTRACTING INC09/12/2022
BIS—ISSUEDDHC CONTRACTING INC03/21/2022
BIS—ISSUEDDYNASTY CONTRACTING LLC11/12/2021
2 projects · most recent 06/20/2022
General Wiring
FiledStatusContractorScope
06/20/2022CancelledINTELOGIC ELECTRIC, INC.General Wiring
06/17/2022CompleteINTELOGIC ELECTRIC, INC.General Wiring
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
10/16/2023Pass-Final Curb Cut Non-Directive 14PassView ↗
09/16/2022Certified Gas-Gas-Piping-RoughingCertifiedView ↗
09/16/2022Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
09/16/2022Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
09/16/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/16/2022Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 24
DateRequirementInspectorRole
05/01/2023Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationXIAOHONG ZHAOspecial
05/01/2023Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention FacilitiesXIAOHONG ZHAOspecial
05/01/2023Fire-Resistant Penetrations and JointsXIAOHONG ZHAOspecial
05/01/2023Subsurface Investigations (Borings/Test Pits)XIAOHONG ZHAOspecial
05/01/2023Energy Code Compliance InspectionsXIAOHONG ZHAOprogress
05/01/2023HVAC insulation and sealing XIAOHONG ZHAOenergy_progress
05/01/2023HVAC and service water heating equipment XIAOHONG ZHAOenergy_progress
05/01/2023HVAC and service water heating system controls XIAOHONG ZHAOenergy_progress
04/22/2023HVAC and service water heating equipment XIAOHONG ZHAOenergy_progress
04/22/2023Fire-Resistant Penetrations and JointsXIAOHONG ZHAOspecial
04/22/2023Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationXIAOHONG ZHAOspecial
04/22/2023Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention FacilitiesXIAOHONG ZHAOspecial
04/22/2023Subsurface Investigations (Borings/Test Pits)XIAOHONG ZHAOspecial
04/22/2023Energy Code Compliance InspectionsXIAOHONG ZHAOprogress
04/22/2023HVAC insulation and sealing XIAOHONG ZHAOenergy_progress
04/22/2023HVAC and service water heating system controls XIAOHONG ZHAOenergy_progress
09/03/2022Fire-Resistant Penetrations and JointsXIAOHONG ZHAOspecial
09/03/2022Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationXIAOHONG ZHAOspecial
09/03/2022Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention FacilitiesXIAOHONG ZHAOspecial
09/03/2022Subsurface Investigations (Borings/Test Pits)XIAOHONG ZHAOspecial
09/03/2022Energy Code Compliance InspectionsXIAOHONG ZHAOprogress
09/03/2022HVAC insulation and sealing XIAOHONG ZHAOenergy_progress
09/03/2022HVAC and service water heating system controls XIAOHONG ZHAOenergy_progress
09/03/2022HVAC and service water heating equipment XIAOHONG ZHAOenergy_progress
▾Documents — 147 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch - Plumbing3
08/25/2026Q00321170-P2Request digital key ↗
08/25/2026Q00321170-I1Request digital key ↗
08/15/2026Q00321170-P1Request digital key ↗
▸DOB NOWPlans/Sketch1
08/24/2026Q00863700-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Construction Fence1
08/27/2026Q00433487-I1Request digital key ↗
▸Applications & Permits16
▸BISPLAN / WORK APPROVAL APPLICATION9
09/21/2023421778570Open ↗
06/02/2023421778570Open ↗
09/08/2022421735386Open ↗
Showing 3 of 9 on file for this type
▸BISWORK PERMIT APPLICATION4
10/11/2023421735386Open ↗
03/21/2022421735386Open ↗
02/07/2022421735386Open ↗
Showing 3 of 4 on file for this type
▸BISBPP-5 - Authorization to the Department of Transportation2
12/08/2021421778570Open ↗
01/02/2020421778570Open ↗
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
08/31/2023421735386Open ↗
▸Zoning, Tax Lot & Property Records3
▸BISVERIFY TAX LOT1
10/19/2023421735386Open ↗
▸BISCO OBJ: VERIFY ADDRESS-TOPO STAMP1
10/19/2023421735386Open ↗
▸BISZONING DIAGRAM1
02/27/2020421735386Open ↗
▸Seals & Professional Certifications34
▸DOB NOWProgress Inspector Seal & Signature12
08/27/2026Q00321170-P1Open ↗
08/27/2026Q00321170-P1Open ↗
08/27/2026Q00321170-P1Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature12
08/27/2026Q00321170-P1Open ↗
08/27/2026Q00321170-P1Open ↗
08/27/2026Q00321170-P1Open ↗
Showing 3 of 12 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION5
02/07/2022421735386Open ↗
02/07/2022421735386Open ↗
03/12/2020421735386Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/27/2026Q00433487-I1Open ↗
08/25/2026Q00321170-P1Open ↗
08/25/2026Q00321170-I1Open ↗
Showing 3 of 5 on file for this type
▸Trade Schedules & Equipment4
▸BISHVAC & SERVICE WATER HEATING EQUIPMENT1
10/19/2023421735386Open ↗
▸BISHVAC & SERVICE WATER HEATING SYSTEM CONTROLS1
10/19/2023421735386Open ↗
▸BISSPRINKLER SYSTEMS1
10/19/2023421735386Open ↗
▸BISDETECTOR:SMOKE-CERT. OF INSTALLATION1
10/19/2023421735386Open ↗
▸Safety & Tenant Protection7
▸BISSTREET TREE CHECKLIST2
01/02/2020421778570Open ↗
10/03/2019421735386Open ↗
▸BISSTREET TREES SITE PLAN2
10/19/2023421735386Open ↗
10/04/2023421778570Open ↗
▸BISSTREET TREE SIGNOFF2
10/19/2023421735386Open ↗
10/04/2023421778570Open ↗
▸BISEXCAVATION - SHEETING, SHORING, AND BRACING1
10/19/2023421735386Open ↗
▸Energy Compliance15
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS3
02/07/2022421735386Open ↗
01/03/2020421735386Open ↗
10/03/2019421735386Open ↗
▸BISFENESTRATION AIR LEAKAGE1
10/19/2023421735386Open ↗
▸BISAIR SEALING AND INSULATION - VISUAL1
10/19/2023421735386Open ↗
▸BISINTERIOR LIGHTING POWER1
10/19/2023421735386Open ↗
▸BIS* DUCT LEAKAGE TESTING1
10/19/2023421735386Open ↗
▸BISFENESTRATION U-FACTOR & PRODUCT RATING1
10/19/2023421735386Open ↗
▸BISFENESTRATION AREAS1
10/19/2023421735386Open ↗
▸BISAIR SEALING AND INSULATION - TESTING1
10/19/2023421735386Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
11/15/2021421735386Open ↗
▸BISINSULATION PLACEMENT & R VALUES1
10/19/2023421735386Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
10/19/2023421735386Open ↗
▸BIS* HVAC INSULATION AND SEALING1
10/19/2023421735386Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
10/19/2023421735386Open ↗
▸Inspections & Test Reports21
▸DOB NOWSOIL REPORT3
08/25/2026Q00321170-P1Open ↗
08/25/2026Q00321170-I1Open ↗
08/13/2026Q00321170-P2Open ↗
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER2
10/24/2023421735386Open ↗
02/07/2022421735386Open ↗
▸BISFRAME (2008)/STRUCTURAL WOOD FRAME (2014) INSPECTION1
10/19/2023421735386Open ↗
▸BISDEMOLITION (DM) JOB SIGNOFF1
10/19/2023421735386Open ↗
▸BISCONCRETE - CAST-IN-PLACE1
10/19/2023421735386Open ↗
▸BISTR2: CONCRETE FIELD TESTING TECHNICAL REPORT1
11/15/2021421735386Open ↗
▸BISSTRUCTURAL STEEL - DETAILS1
10/19/2023421735386Open ↗
▸BISTR3: CONCRETE DESIGN MIX TECHNICAL REPORT1
11/15/2021421735386Open ↗
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
10/19/2023421735386Open ↗
▸BISFIRE-RESISTIVE RATED CONSTRUCTION1
10/19/2023421735386Open ↗
▸BISFOOTING AND FOUNDATION INSPECTION1
10/19/2023421735386Open ↗
▸BISMASONRY1
10/19/2023421735386Open ↗
▸BISSTRUCTURAL STEEL - HIGH STRENGTH BOLTING1
10/19/2023421735386Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY1
11/15/2021421735386Open ↗
▸BISSTRUCTURAL STEEL - WELDING1
10/19/2023421735386Open ↗
▸BISSUBGRADE INSP / SOILS-SITE PREP1
10/19/2023421735386Open ↗
▸BISHYDRO FLOW TEST LETTER1
01/03/2020421735386Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026Q00321170-I1Open ↗
▸Approvals, Objections & Sign-offs7
▸BISSCHEDULE A - OCCUPANCY / USE3
09/08/2022421735386Open ↗
10/25/2021421735386Open ↗
01/02/2020421735386Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION3
03/12/2020421735386Open ↗
03/12/2020421735386Open ↗
01/16/2020421778570Open ↗
▸BISSUPERSEDING LETTER1
10/11/2023421735386Open ↗
▸Cost, Insurance & Ownership2
▸BISPROJECT SPECIFIC GENERAL LIABILITY INSURANCE2
10/11/2023421735386Open ↗
02/07/2022421735386Open ↗
▸Filing & Intake Forms11
▸BISADDITIONAL INFORMATION5
10/24/2023421735386Open ↗
07/11/2023421778570Open ↗
04/28/2023421735386Open ↗
Showing 3 of 5 on file for this type
▸BISBOROUGH INTAKE FORM3
10/11/2023421735386Open ↗
09/21/2023421778570Open ↗
01/21/2022421735386Open ↗
▸BISEFILING COVER SHEET2
01/02/2020421778570Open ↗
10/03/2019421735386Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
01/02/2020421778570Open ↗
▸Other Documents7
▸BISCHIMNEYS AND VENTS1
10/19/2023421735386Open ↗
▸BISPRELIMINARY1
10/19/2023421735386Open ↗
▸BISSHUTOFF DAMPERS1
10/19/2023421735386Open ↗
▸BISWOOD - METAL-PLATE-CONNECTED TRUSSES1
10/19/2023421735386Open ↗
▸BISMAINTENANCE INFORMATION1
10/19/2023421735386Open ↗
▸BISPERMANENT CERTIFICATE1
10/19/2023421735386Open ↗
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
01/26/2024421735386Open ↗