| Owner | Filings | Most Recent |
|---|---|---|
| 230-30 BDS | 14 | 07/08/2026 |
| 12046 144 Holdings | 4 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 08/19/2022 | $1.2M | — | 12046 144 HOLDINGS LLC → Private party | $635/sf building |
| 06/24/2020 | $300K | — | Private party → 12046 144 HOLDINGS LLC | $156/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| Sion Consulting Engineering | 4 | 03/11/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| Sion Consulting Engineering | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Eastern BH Mechanical | Scaffold | 4 | 07/08/2026 |
| Eastern BH Mechanical | specialty_contractor | 1 | 07/08/2026 |
| All Pro Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Sion Consulting Engineering | 1108 | 2 | 03/11/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | Eastern BH Mechanical | 10/07/2021 |
| DOB NOW | Plumbing | Signed-off | All Pro Plumbing & Heating | 07/09/2021 |
| DOB NOW | Construction Fence | Signed-off | Eastern BH Mechanical | 05/28/2021 |
| DOB NOW | Construction Fence | Signed-off | Eastern BH Mechanical | 10/30/2020 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/26/2021 | Complete | Trincity Electric | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/12/2022 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 01/07/2022 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 11/18/2021 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/12/2021 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 07/28/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/21/2022 | HVAC-R and service water heating system controls | sion hourizadeh | energy_progress |
| 03/21/2022 | Fire-Resistant Penetrations and Joints | sion hourizadeh | special |
| 03/21/2022 | Energy Code Compliance Inspections | sion hourizadeh | progress |
| 03/21/2022 | HVAC-R and service water piping design and insulation | sion hourizadeh | energy_progress |
| 03/21/2022 | HVAC-R and service water heating equipment | sion hourizadeh | energy_progress |
| 03/21/2022 | Maintenance information | sion hourizadeh | energy_progress |
| 03/03/2022 | Maintenance information | sion hourizadeh | energy_progress |
| 03/03/2022 | Fire-Resistant Penetrations and Joints | sion hourizadeh | special |
| 03/03/2022 | Energy Code Compliance Inspections | sion hourizadeh | progress |
| 03/03/2022 | HVAC-R and service water piping design and insulation | sion hourizadeh | energy_progress |
| 03/03/2022 | HVAC-R and service water heating system controls | sion hourizadeh | energy_progress |
| 03/03/2022 | HVAC-R and service water heating equipment | sion hourizadeh | energy_progress |
| 08/24/2020 | Final | sion hourizadeh | progress |