| Owner | Filings | Most Recent |
|---|---|---|
| TOTAL NY CONSTRUCTION | 4 | 07/08/2026 |
| 120 EAST 78 STREET | 2 | 03/22/2026 |
| 120 EAST 78TH STREET | 5 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/21/2022 | $9.2M | — | Private party → 120 EAST 78 STREET ASSOCIATES LLC | $1,112/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| GLICKMAN SCHLESINGER ARCHITECTS | 6 | 07/03/2024 |
| JACK GREEN ASSOCIATES | 5 | 05/08/2024 |
| CORNERSTONE ARCHITECTS | 2 | 10/26/2023 |
| AP PROFESSIONAL ENGINEERING PLLC | 1 | 03/15/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| SANDEEP KAUR | 1 | 03/21/2026 |
| JAM CONSULTANTS, INC. | 21 | 03/21/2026 |
| NORTHEAST EXPEDITING | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| AFGO MECHANICAL SVCS INC | General Contractor | 2 | 03/21/2026 |
| FREEDOM GS INC | General Contractor | 2 | 03/21/2026 |
| TOTAL NY CONSTRUCTION CORP | General Contractor | 2 | 07/08/2026 |
| ACCURATE MECHANICAL INC | Plumbing | 1 | 07/08/2026 |
| VELOCITY PLUMBING & HEAT | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| JACK GREEN ASSOCIATES | 422 | 5 | 05/08/2024 |
| ASE ENGINEERING PLLC | 5785 | 2 | 10/26/2023 |
| GLICKMAN SCHLESINGER ARCH | 6768 | 1 | 01/10/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | AFGO MECHANICAL SVCS | 09/01/2023 |
| DOB NOW | General Construction | Signed-off | TOTAL NY CONSTRUCTION COR | 06/12/2023 |
| DOB NOW | Plumbing | Signed-off | VELOCITY PLUMBING & HEAT | 05/09/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | TOTAL NY CONSTRUCTION COR | 03/16/2023 |
| DOB NOW | Plumbing | Signed-off | ANTHONY DISABATO | 01/20/2023 |
| DOB NOW | General Construction | Signed-off | FREEDOM GS | 01/17/2023 |
| BIS | EQ | ISSUED | BAY RESTORATION CORP | 06/15/2010 |
| BIS | OT | ISSUED | INTEGRITY CONTRACTING INC | 04/24/2007 |
| BIS | OT | ISSUED | INTEGRITY CONTRACTING INC | 04/24/2007 |
| BIS | OT | ISSUED | 3-D LABORATORY INC | 06/13/2006 |
| BIS | OT | ISSUED | 3-D LABORATORY INC | 06/13/2006 |
| BIS | OT | ISSUED | KULHMANN ASSOC. | 07/01/1997 |
| BIS | PL | ISSUED | RANGER PLUMBING INC | 04/10/1997 |
| BIS | EQ | ISSUED | MARCO MARTELLI ASSOCIATES | 03/07/1997 |
| BIS | OT | RE-ISSUED | KULHMANN ASSOC. | 11/27/1996 |
| BIS | MH | RE-ISSUED | KULHMANN ASSOC,. | 11/27/1996 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/12/2023 | Complete | CENTENNIAL ELEVATOR INDUS | General Wiring |
| 03/31/2023 | Complete | BDS ELECTRIC CORP. | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/01/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/01/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/16/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/06/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/29/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/07/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/12/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/17/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/08/2024 | Final | LAWRENCE GREEN | progress |
| 05/08/2024 | HVAC-R and service water piping design and insulation | LAWRENCE GREEN | energy_progress |
| 05/08/2024 | Maintenance information | LAWRENCE GREEN | energy_progress |
| 05/08/2024 | HVAC-R and service water heating system controls | LAWRENCE GREEN | energy_progress |
| 05/08/2024 | HVAC-R and service water heating equipment | LAWRENCE GREEN | energy_progress |
| 05/08/2024 | Mechanical Systems | LAWRENCE GREEN | special |
| 05/02/2024 | Final | LAWRENCE GREEN | progress |
| 05/02/2024 | HVAC-R and service water piping design and insulation | LAWRENCE GREEN | energy_progress |
| 05/02/2024 | HVAC-R and service water heating equipment | LAWRENCE GREEN | energy_progress |
| 05/02/2024 | Maintenance information | LAWRENCE GREEN | energy_progress |
| 05/02/2024 | HVAC-R and service water heating system controls | LAWRENCE GREEN | energy_progress |
| 05/02/2024 | Mechanical Systems | LAWRENCE GREEN | special |
| 10/30/2023 | Structural Stability – Alterations of existing buildings | alon egozi | special |
| 10/30/2023 | Energy Code Compliance Inspections | Mark Ellis | progress |
| 10/30/2023 | Final | Mark Ellis | progress |
| 10/30/2023 | Air barrier - visual inspection | Mark Ellis | energy_progress |
| 10/30/2023 | Masonry | alon egozi | special |
| 10/19/2023 | Masonry | alon egozi | special |
| 10/19/2023 | Structural Stability – Alterations of existing buildings | alon egozi | special |
| 10/19/2023 | Energy Code Compliance Inspections | Mark Ellis | progress |
| 10/19/2023 | Final | Mark Ellis | progress |
| 10/19/2023 | Air barrier - visual inspection | Mark Ellis | energy_progress |
| 08/22/2023 | Fire-Resistant Penetrations and Joints | LAWRENCE GREEN | special |
| 07/24/2023 | Fire-Resistant Penetrations and Joints | LAWRENCE GREEN | special |