| Owner | Filings | Most Recent |
|---|---|---|
| HINES INTERESTS LIMITED PARTNERSHIP | 74 | 08/29/2026 |
| 3BP PROPERTY OWNER | 9 | 03/21/2026 |
| HINES | 6 | 03/21/2026 |
| EQUITY OFFICE PROPERTIES | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| VOCON | 3 | 08/05/2026 |
| MDEAS ARCHITECTS | 2 | 08/04/2026 |
| FL&M ENGINEERING DESIGN &INSPECTION | 1 | 11/20/2025 |
| GILSANZ MURRAY STEFICEK LLP | 5 | 09/02/2025 |
| STANTEC CONSULTING | 3 | 08/26/2025 |
| GOLDMAN COPELAND ASSOCIATES | 1 | 06/23/2025 |
| LB ENGINEERING PC | 4 | 06/10/2025 |
| CLIP ARCHITECTS | 2 | 06/10/2025 |
| ROBERT DERECTOR ASSOCIATES | 1 | 04/02/2025 |
| AKF ENGINEERS, LLP | 3 | 02/08/2024 |
| NATASHA L SUZANSKY ARCHITECT | 1 | 02/06/2024 |
| CHRISTOPHER PAGLIARO ARCHITECTS | 3 | 02/27/2023 |
| PATTI & ANTHES CONSULTING ENGINEERS | 4 | 12/08/2021 |
| STRUCTURAL ENGINEERING BURO | 1 | 06/29/2021 |
| HNY CONSULTING ENGINEERS LLC | 5 | 01/22/2021 |
| WALTER T. GORMAN, P.E., P.C. | 2 | 01/15/2021 |
| BAILEYS ENGINEERING PC | 2 | 10/11/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| RIZZO GROUP | 31 | 03/21/2026 |
| K M DOB CONSULTING | 12 | 03/21/2026 |
| WALTER T. GORMAN, PE, PC | 2 | 03/21/2026 |
| AE DESIGN SOLUTION | 4 | 03/21/2026 |
| WALTER T GORMAN P E P C | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| AMA DESIGN BUILD LLC | General Contractor | 14 | 07/04/2026 |
| SPRING SCAFFOLDING LLC | General Contractor | 7 | 07/08/2026 |
| HOLT CONSTRUCTION CORP | General Contractor | 6 | 07/08/2026 |
| BENCHMARK BUILDERS LLC | General Contractor | 5 | 07/08/2026 |
| JAMES E FITZGERALD INC | General Contractor | 5 | 07/08/2026 |
| R.N.K. ROMEO CONST INC | General Contractor | 4 | 07/08/2026 |
| TA MECHANICAL GROUP INC | General Contractor | 4 | 07/08/2026 |
| VERSATILE SERVICES LLC | General Contractor | 3 | 07/08/2026 |
| SIRINA FIRE PROT CORP | Fire Protection | 2 | 07/08/2026 |
| ARMON MECHANICAL INC | Plumbing | 1 | 07/08/2026 |
| GEORGE BRESLAW PLBNG LLC | Plumbing | 1 | 07/08/2026 |
| HP SERVICES INC | Plumbing | 1 | 07/08/2026 |
| JOSEPH D'AMBROSIO | Electrical | 1 | 03/21/2026 |
| TRISTATE PLBG SVCS CORP | Plumbing | 1 | 07/08/2026 |
| AGGRESSIVE FIRE PROT LLC | Fire Protection | 1 | 07/08/2026 |
| ARMON MECHANICAL INC | Fire Protection | 1 | 07/08/2026 |
| ASHLAR MECHANICAL CORP | Fire Protection | 1 | 07/08/2026 |
| EXPERT FIRE SPRINKLER,LLC | Fire Protection | 1 | 07/08/2026 |
| BRESLAW MARC | General Contractor | 1 | 03/21/2026 |
| BROOKLINE MECHANICAL INC | General Contractor | 1 | 07/08/2026 |
| TRISTATE PLBG SVCS | General Contractor | 1 | 03/21/2026 |
| ADVANCED PLUMBING MECH | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CATALPA SPECIAL INSPECTIO | 2004 | 2 | 08/04/2026 |
| METRIC CONSULTING AND INS | 1803 | 1 | 09/02/2025 |
| MEP INSPECTIONS, INC | 1102 | 10 | 09/02/2025 |
| GOLDMAN COPELAND ASSOCIAT | 2826 | 1 | 06/23/2025 |
| NKM ENGINEERING PLLC | 6244 | 6 | 06/10/2025 |
| SKYLINE ENGINEERING, PLLC | 267 | 2 | 04/10/2025 |
| GILSANZ MURRAY STEFICEK | 240 | 3 | 02/08/2024 |
| CROSSCHECK INSPECTION SER | 544 | 4 | 12/08/2021 |
| STRUCTURAL ENGINEERING BU | 5883 | 1 | 06/29/2021 |
| QUALITY TESTING, LLC | 7344 | 2 | 01/22/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Protection and Mechanical Methods | Signed-off | JAMES E FITZGERALD INC | 11/24/2025 |
| DOB NOW | Structural | Signed-off | JAMES E FITZGERALD INC | 09/04/2025 |
| DOB NOW | Sprinklers | Signed-off | ARMON MECHANICAL INC | 08/28/2025 |
| DOB NOW | Plumbing | Signed-off | ARMON MECHANICAL INC | 08/28/2025 |
| DOB NOW | General Construction | Signed-off | JAMES E FITZGERALD INC | 08/27/2025 |
| DOB NOW | Mechanical Systems | Signed-off | JAMES E FITZGERALD INC | 08/27/2025 |
| DOB NOW | General Construction | Permit Issued | AMA DESIGN BUILD LLC | 08/22/2025 |
| DOB NOW | Structural | Permit Issued | AMA DESIGN BUILD LLC | 08/22/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | AMA DESIGN BUILD LLC | 08/22/2025 |
| DOB NOW | Standpipe | Permit Issued | SIRINA FIRE PROT CORP | 06/26/2025 |
| DOB NOW | General Construction | Permit Issued | AMA DESIGN BUILD LLC | 04/17/2025 |
| DOB NOW | Structural | Permit Issued | AMA DESIGN BUILD LLC | 04/16/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | AMA DESIGN BUILD LLC | 04/09/2025 |
| DOB NOW | General Construction | Signed-off | BENCHMARK BUILDERS LLC | 09/19/2024 |
| DOB NOW | Plumbing | Signed-off | EXPERT FIRE SPRINKLER,LLC | 06/24/2024 |
| DOB NOW | Plumbing | Signed-off | HP SERVICES INC | 06/18/2024 |
| DOB NOW | Mechanical Systems | Signed-off | R.N.K. ROMEO CONST INC | 06/13/2024 |
| DOB NOW | General Construction | Signed-off | R.N.K. ROMEO CONST INC | 06/12/2024 |
| DOB NOW | Mechanical Systems | Signed-off | BROOKLINE MECHANICAL INC | 04/30/2024 |
| DOB NOW | Sprinklers | Signed-off | AGGRESSIVE FIRE PROT LLC | 03/01/2024 |
| DOB NOW | Structural | Signed-off | BENCHMARK BUILDERS LLC | 03/01/2024 |
| DOB NOW | Plumbing | Signed-off | GEORGE BRESLAW PLBNG LLC | 02/27/2024 |
| DOB NOW | General Construction | Signed-off | BENCHMARK BUILDERS LLC | 02/07/2024 |
| DOB NOW | General Construction | Signed-off | VERSATILE SERVICES LLC | 03/01/2023 |
| DOB NOW | Structural | Signed-off | VERSATILE SERVICES LLC | 10/31/2022 |
| DOB NOW | Sprinklers | Signed-off | SIRINA FIRE PROT CORP | 07/15/2021 |
| DOB NOW | Plumbing | Signed-off | ADVANCED PLUMBING MECH | 07/15/2021 |
| DOB NOW | Mechanical Systems | Signed-off | HOLT CONSTRUCTION CORP | 07/02/2021 |
| DOB NOW | General Construction | Signed-off | HOLT CONSTRUCTION CORP | 07/01/2021 |
| DOB NOW | Structural | Signed-off | HOLT CONSTRUCTION CORP | 07/01/2021 |
| DOB NOW | General Construction | Signed-off | HOLT CONSTRUCTION CORP | 04/07/2021 |
| DOB NOW | Mechanical Systems | Signed-off | TA MECHANICAL GROUP INC | 10/29/2020 |
| DOB NOW | Sprinklers | Signed-off | ASHLAR MECHANICAL CORP | 10/14/2020 |
| DOB NOW | Mechanical Systems | Signed-off | TA MECHANICAL GROUP INC | 01/28/2020 |
| DOB NOW | Plumbing | Signed-off | TRISTATE PLBG SVCS CORP | 01/28/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 10/15/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 12/26/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 10/18/2018 |
| BIS | OT | ISSUED | CONSTRUCTION MANAGEMENT & | 01/17/2020 |
| BIS | OT | ISSUED | CONSTRUCTION MANAGEMENT & | 01/17/2020 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/23/2025 | Permit Issued | SIRINA FIRE PROT CORP | 1 outlets |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/23/2025 | — | — | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/01/2026 | Complete | ACCURATE ELEC'L CONTR'S C | General Wiring |
| 01/24/2025 | Complete | KWONG MING ELECTRIC INC | General Wiring |
| 07/11/2024 | Complete | CORZO ELECTL SYS CORP | General Wiring |
| 06/15/2023 | Complete | E-J ELEC. INSTALLATION CO | General Wiring |
| 09/08/2022 | Complete | ALLAN/BRITE-WAY ELEC'L CO | General Wiring |
| 03/01/2021 | Complete | PATRIOT ELECTRIC CORP | General Wiring |
| 01/20/2020 | Complete | PATRIOT ELECTRIC CORP | — |
| 11/05/2019 | Complete | STAR-DELTA ELECTRIC, LLC | — |
| 10/15/2019 | Complete | TOP SHELF ELECTRIC CORP | — |
| 10/05/2018 | Complete | TOP SHELF ELECTRIC CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/10/2025 | Permit Issued | AMA DESIGN BUILD LLC | Steel, Concrete |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/08/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/30/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/23/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/23/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/02/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/12/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/05/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/12/2025 | Certified StandPipe-Fire Pump (SD)-Fire Pump Test | Certified | View ↗ |
| 07/29/2025 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 07/02/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/21/2025 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 06/12/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/05/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/02/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/08/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/06/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 01/02/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/20/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/17/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/16/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/30/2021 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/29/2021 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/01/2021 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/01/2021 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/28/2021 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/04/2026 | Exterior Insulation and Finish Systems (EIFS) | ERIC BERLENT | special |
| 08/04/2026 | Final | Michael Zaborski | progress |
| 08/04/2026 | Fire-Resistance Rated Construction | ERIC BERLENT | progress |
| 08/04/2026 | Sprayed fire-resistant materials | ERIC BERLENT | special |
| 08/04/2026 | Fire-Resistant Penetrations and Joints | ERIC BERLENT | special |
| 07/17/2025 | Sprinkler Systems | Nicolas Crosetto | special |
| 07/17/2025 | Fire-Resistant Penetrations and Joints | Nicolas Crosetto | special |
| 07/17/2025 | Fire-Resistant Penetrations and Joints | Nicolas Crosetto | special |
| 06/11/2025 | Sprinkler Systems | NARESH MAHANGU | special |
| 06/11/2025 | Lighting controls | NARESH MAHANGU | energy_progress |
| 06/11/2025 | Interior lighting power | NARESH MAHANGU | energy_progress |
| 06/11/2025 | Fire-Resistant Penetrations and Joints | NARESH MAHANGU | special |
| 06/11/2025 | Energy Code Compliance Inspections | NARESH MAHANGU | progress |
| 06/11/2025 | Fire-Resistant Penetrations and Joints | NARESH MAHANGU | special |
| 06/10/2025 | Heating Systems | NARESH MAHANGU | special |
| 06/10/2025 | Fire-Resistant Penetrations and Joints | NARESH MAHANGU | special |
| 06/10/2025 | Energy Code Compliance Inspections | NARESH MAHANGU | progress |
| 06/10/2025 | HVAC-R and service water heating equipment | NARESH MAHANGU | energy_progress |
| 06/10/2025 | Maintenance information | NARESH MAHANGU | energy_progress |
| 06/10/2025 | HVAC-R and service water heating system controls | NARESH MAHANGU | energy_progress |
| 06/10/2025 | Duct leakage testing, insulation and design | NARESH MAHANGU | energy_progress |
| 06/10/2025 | Mechanical Systems | NARESH MAHANGU | special |
| 06/10/2025 | Shutoff dampers | NARESH MAHANGU | energy_progress |
| 06/10/2025 | Ventilation and air distribution system | NARESH MAHANGU | energy_progress |
| 06/10/2025 | Final | FAZAL BANGASH | progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Standard Chartered Bank | Office | Floor 3 | Project M01196086 |
| Bank | Office | Floor 3 | Project M01196047 |
| Rosetta Bakery | Restaurant / Food Service | Floor 1 | Project M01047976 Project M01048077 Project M01047934 |
| Valbella | Restaurant / Food Service | — | Project M00524368 Project M00524395 |