1945Year Built
1.67Stories
A0Building Class
R2AZoning
1,377 sfGross Floor Area
1Units
Cape Cod · 3,800 sf lot · 0.36 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
05/18/2018$463K—Private party → Private party$336/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR204/15/2025
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281204/15/2025
Building Lifecycle
All (9)Filed (2)Permit Issued (1)Signed Off (1)Special Inspection (5)
07/01/2025
Signed off — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 14 Panels, 5.74 kW
Q01155601-I1
04/15/2025
Filed — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 14 Panels, 5.74 kW
Q01155601-P1
04/15/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
04/15/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
04/15/2025
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
04/15/2025
Special inspection requirement — Final
Mina Makar
04/15/2025
Special inspection requirement — Air barrier - visual inspection
Mina Makar
12/17/2024
Permit issued — Solar
Q01155601-I1-SL
12/13/2024
Filed — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 14 Panels, 5.74 kW
Q01155601-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offMOMENTUM SOLAR12/17/2024
1 project · most recent 12/13/2024
FiledStatusContractorScope
12/13/2024CompleteISLAND ELECTRIC CORP—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
04/15/2025Fire-Resistant Penetrations and JointsMina Makarspecial
04/15/2025Structural Stability – Alterations of existing buildingsMina Makarspecial
04/15/2025Energy Code Compliance InspectionsMina Makarprogress
04/15/2025FinalMina Makarprogress
04/15/2025Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 10 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/20/2026Q01155601-I1Request digital key ↗
08/20/2026Q01155601-P1Request digital key ↗
▸Seals & Professional Certifications5
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/20/2026Q01155601-I1Open ↗
08/20/2026Q01155601-P1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
09/02/2026Q01155601-P1Open ↗
09/02/2026Q01155601-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
09/02/2026Q01155601-P1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/20/2026Q01155601-I1Open ↗
08/20/2026Q01155601-P1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/20/2026Q01155601-I1Open ↗