← Back
Zoned residential, not Manhattan
121 MT HOPE PLACE
BRONX · BIN 2007633
💬 Discuss this project
0Year Built
—Stories
V0Building Class
R8Zoning
0 sfGross Floor Area
0Units
0 Open Violations
Zoned residential, not Manhattan · Owner of record: 121 MOUNT HOPE LLC · 3,125 sf lot · 0 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire Protection
Roof52p · 2 filings · 20 docs
Floor 843p · 1 filing · 20 docs
Floor 747p · 1 filing · 20 docs
Floor 643p · 1 filing · 20 docs
Floor 543p · 1 filing · 20 docs
Floor 442p · 1 filing · 20 docs
Floor 342p · 1 filing · 20 docs
Floor 246p · 2 filings · 20 docs
Floor 148p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
OWNERS REP1004/09/2026
ABOVE BUILDER GROUP904/09/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
08/27/2024$975K—Private party → 121 MOUNT HOPE LLC— not available
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
XPDITE GROUP LLC (104)1603/21/2026
AE DESIGN SOLUTION403/21/2026
GEIGER E A GROUP203/21/2026
XPDITE GROUP 103803/21/2026
XPDITE GROUP LLC 104803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ABOVE BUILDER GROUP LLCGeneral Contractor1004/09/2026
CORE SCAFFOLD SYSTEMS INC.General Contractor404/09/2026
HEXAGON INDUSTRIES INCGeneral Contractor104/09/2026
PLATINUM SERVICES NY LLCGeneral Contractor104/09/2026
PRIME PIPING & HEATING INPlumbing107/08/2026
GWT ENTERPRISES INCGeneral Contractor104/09/2026
PRIME PIPING & HEATING INFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP56161505/15/2026
ADROIT ENGINEERING PLLC8885109/25/2024
Building Lifecycle
All (100)Filed (22)Permit Issued (17)Signed Off (11)Violation (10)Inspection (7)Special Inspection (30)Tax Incentive (3)
05/22/2026
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
05/22/2026
Special inspection requirement — Fenestration areas
FAHAD FATEH
05/22/2026
Special inspection requirement — Protection of exposed foundation insulation
FAHAD FATEH
05/22/2026
Special inspection requirement — Fire-Resistance Rated Construction
FAHAD FATEH
05/22/2026
Special inspection requirement — Metering
FAHAD FATEH
05/22/2026
Special inspection requirement — Air barrier — testing
FAHAD FATEH
05/22/2026
Special inspection requirement — Electrical motors and elevators
FAHAD FATEH
05/22/2026
Special inspection requirement — Fenestration air leakage
FAHAD FATEH
05/22/2026
Special inspection requirement — Interior lighting power
FAHAD FATEH
05/22/2026
Special inspection requirement — Lighting in dwelling units
FAHAD FATEH
05/22/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
05/22/2026
Special inspection requirement — Insulation placement and R values
FAHAD FATEH
05/22/2026
Special inspection requirement — Exterior lighting power
FAHAD FATEH
05/22/2026
Special inspection requirement — Lighting controls
FAHAD FATEH
05/22/2026
Special inspection requirement — Air barrier - visual inspection
FAHAD FATEH
05/22/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
FAHAD FATEH
05/15/2026
Filed — New Building
PLUMBING APPLICATION FILED HEREWITH IN CONJUNCTION TO NB APPLICATION X01103331-I1.
X01103331-A1
05/14/2026
Special inspection requirement — Interior lighting power
FAHAD FATEH
05/14/2026
Special inspection requirement — Electrical motors and elevators
FAHAD FATEH
05/14/2026
Special inspection requirement — Lighting controls
FAHAD FATEH
05/14/2026
Special inspection requirement — Fire-Resistance Rated Construction
FAHAD FATEH
05/14/2026
Special inspection requirement — Metering
FAHAD FATEH
05/14/2026
Special inspection requirement — Air barrier — testing
FAHAD FATEH
05/14/2026
Special inspection requirement — Fenestration air leakage
FAHAD FATEH
05/14/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
05/14/2026
Special inspection requirement — Insulation placement and R values
FAHAD FATEH
05/14/2026
Special inspection requirement — Protection of exposed foundation insulation
FAHAD FATEH
05/14/2026
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
05/14/2026
Special inspection requirement — Lighting in dwelling units
FAHAD FATEH
05/14/2026
Special inspection requirement — Air barrier - visual inspection
FAHAD FATEH
05/14/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
FAHAD FATEH
05/11/2026
Violation issued (HPD, closed)
A
03/25/2026
Signed off — New Building
PLUMBING APPLICATION FILED HEREWITH IN CONJUNCTION TO NB APPLICATION X01103331-I1.
X01103331-S4
03/25/2026
Signed off — New Building
PLUMBING APPLICATION FILED HEREWITH IN CONJUNCTION TO NB APPLICATION X01103331-I1.
X01103331-S5
02/12/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
02/11/2026
Filed — New Building
PLUMBING APPLICATION FILED HEREWITH IN CONJUNCTION TO NB APPLICATION X01103331-I1.
X01103331-P9
02/10/2026
Signed off — New Building
PLUMBING APPLICATION FILED HEREWITH IN CONJUNCTION TO NB APPLICATION X01103331-I1.
X01103331-S6
01/09/2026
Filed — New Building
PLUMBING APPLICATION FILED HEREWITH IN CONJUNCTION TO NB APPLICATION X01103331-I1.
X01103331-P7
01/05/2026
Signed off — New Building
PLUMBING APPLICATION FILED HEREWITH IN CONJUNCTION TO NB APPLICATION X01103331-I1.
X01103331-S3
12/31/2025
Signed off — New Building
PLUMBING APPLICATION FILED HEREWITH IN CONJUNCTION TO NB APPLICATION X01103331-I1.
X01103331-S1
12/31/2025
Signed off — Alteration
INSTALLATION OF 300 PSF SIDEWALK SHED AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
X01160088-I1
12/29/2025
Filed — New Building
PLUMBING APPLICATION FILED HEREWITH IN CONJUNCTION TO NB APPLICATION X01103331-I1.
X01103331-P8
12/24/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
12/23/2025
Signed off — Alteration
X01138469-I1
12/22/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
12/15/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
X01245961-I1
12/15/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
X01253773-I1
12/15/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
12/02/2025
Permit issued — Mechanical Systems
X01103331-S5-MS
12/01/2025
485-x construction completed
11/23/2025
Signed off — New Building
PLUMBING APPLICATION FILED HEREWITH IN CONJUNCTION TO NB APPLICATION X01103331-I1.
X01103331-S2
11/21/2025
Permit issued — Construction Fence
X01138469-I1-FN
11/19/2025
Permit issued — Sidewalk Shed
X01160088-I1-SH
11/05/2025
Permit issued — General Construction
X01103331-I1-GC
09/11/2025
Violation issued (ECB, closed)
Unknown
09/11/2025
Violation issued (ECB, closed)
Construction
09/11/2025
Violation issued (ECB, closed)
Construction
09/09/2025
Signed off — Full Demolition
X01076538-I1
09/07/2025
Violation issued (ECB, closed)
Construction
09/07/2025
Violation issued (ECB, closed)
Unknown
Latest 60 of 100 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offABOVE BUILDER GROUP LLC12/02/2025
DOB NOWConstruction FenceSigned-offABOVE BUILDER GROUP LLC11/21/2025
DOB NOWSidewalk ShedSigned-offPLATINUM SERVICES NY LLC11/19/2025
DOB NOWGeneral ConstructionPermit IssuedABOVE BUILDER GROUP LLC11/05/2025
DOB NOWSupported ScaffoldSigned-offCORE SCAFFOLD SYSTEMS INC07/10/2025
DOB NOWSidewalk ShedSigned-offCORE SCAFFOLD SYSTEMS INC06/26/2025
DOB NOWSprinklersSigned-offA M B MECHANICAL INC06/04/2025
DOB NOWPlumbingSigned-offPRIME PIPING & HEATING IN05/30/2025
DOB NOWGeneral ConstructionPermit IssuedABOVE BUILDER GROUP LLC04/29/2025
DOB NOWStructuralSigned-offABOVE BUILDER GROUP LLC04/04/2025
DOB NOWSupport of ExcavationSigned-offABOVE BUILDER GROUP LLC04/03/2025
DOB NOWEarth WorkSigned-offABOVE BUILDER GROUP LLC04/03/2025
DOB NOWGeneral ConstructionPermit IssuedABOVE BUILDER GROUP LLC02/27/2025
DOB NOWSidewalk ShedSigned-offGWT ENTERPRISES INC12/26/2024
DOB NOWFull DemolitionSigned-offHEXAGON INDUSTRIES INC12/19/2024
DOB NOWGeneral ConstructionPermit IssuedABOVE BUILDER GROUP LLC11/29/2024
DOB NOWConstruction FenceSigned-offABOVE BUILDER GROUP LLC11/20/2024
1 project · most recent 05/15/2026
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
05/15/2026Signed-offABOVE BUILDER GROUP LLCHeating and Air Conditioning Systems
Heat / Cool
Mitsubishi Electric MXZ-3C24NA3-U1 25,000 BTU · Split System ×18
PUZ-A18NKA7 22,000 BTU · Split System ×12
MXZ-SM36NAM2-U1 41,000 BTU · Split System ×10
MXZ-2C20NA4-U1 22,000 BTU · Split System ×8
MXZ-4C36NA4-U1 36,000 BTU · Split System ×4
MXZ-3C30NA3-U1 28,600 BTU · Heat Pump Outdoor ×2
Daikin RXF12BVJU9 13,500 BTU · Heat Pump Outdoor ×2
1 project · most recent 05/15/2026
Sprinkler System
FiledStatusContractorScope
05/15/2026Signed-offPRIME PIPING & HEATING INSprinkler System
1 project · most recent 05/15/2026
Gas Storm Water/Sanitary
FiledStatusContractorScope
05/15/2026Signed-offPRIME PIPING & HEATING INGas, Storm, Water/Sanitary
4 projects · most recent 04/30/2026
General Wiring
FiledStatusContractorScope
04/30/2026CompleteHIVOLTS ELECTRICAL INCGeneral Wiring
09/03/2025CompletePOWER DIRECT ELECTRIC INC—
06/26/2025CompleteSOLAS ELECTRICAL CORP—
02/26/2025CompleteHIVOLTS ELECTRICAL INC—
1 project · most recent 05/15/2026
FiledStatusContractorScope
05/15/2026Signed-offABOVE BUILDER GROUP LLC1 scope_items
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
02/12/2026Pass-Final CND-Occupancy InspectionPassView ↗
12/24/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
12/22/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
12/15/2025Pass-Final CND-Occupancy InspectionPassView ↗
08/01/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
06/12/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
06/12/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 104
DateRequirementInspectorRole
05/22/2026Air barrier — testing FAHAD FATEHenergy_progress
05/22/2026Fenestration areasFAHAD FATEHenergy_progress
05/22/2026Air barrier - visual inspectionFAHAD FATEHenergy_progress
05/22/2026Fenestration and door U-factor and product ratingsFAHAD FATEHenergy_progress
05/22/2026Lighting controlsFAHAD FATEHenergy_progress
05/22/2026Insulation placement and R valuesFAHAD FATEHenergy_progress
05/22/2026Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
05/22/2026Energy Code Compliance InspectionsFAHAD FATEHprogress
05/22/2026Fire-Resistance Rated ConstructionFAHAD FATEHprogress
05/22/2026Lighting in dwelling unitsFAHAD FATEHenergy_progress
05/22/2026Interior lighting powerFAHAD FATEHenergy_progress
05/22/2026Protection of exposed foundation insulationFAHAD FATEHenergy_progress
05/22/2026Fenestration air leakageFAHAD FATEHenergy_progress
05/22/2026Electrical motors and elevatorsFAHAD FATEHenergy_progress
05/22/2026MeteringFAHAD FATEHenergy_progress
05/22/2026Exterior lighting powerFAHAD FATEHenergy_progress
05/14/2026Fenestration air leakageFAHAD FATEHenergy_progress
05/14/2026Lighting in dwelling unitsFAHAD FATEHenergy_progress
05/14/2026Protection of exposed foundation insulationFAHAD FATEHenergy_progress
05/14/2026Lighting controlsFAHAD FATEHenergy_progress
05/14/2026Interior lighting powerFAHAD FATEHenergy_progress
05/14/2026Fire-Resistance Rated ConstructionFAHAD FATEHprogress
05/14/2026Energy Code Compliance InspectionsFAHAD FATEHprogress
05/14/2026Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
05/14/2026Fenestration areasFAHAD FATEHenergy_progress
Latest 25 of 104.
▾Documents — 140 on file (BIS + DOB NOW)
▸Plans & Drawings22
▸DOB NOWPlans/Sketch22
08/20/2026X01076538-I1Request digital key ↗
08/20/2026X01138469-I1Request digital key ↗
08/20/2026X01160088-I1Request digital key ↗
Showing 3 of 22 on file for this type
▸Applications & Permits5
▸BISPLAN / WORK APPROVAL APPLICATION5
01/12/2026240361023Open ↗
01/05/2026240361023Open ↗
12/05/2025240361023Open ↗
Showing 3 of 5 on file for this type
▸Zoning, Tax Lot & Property Records11
▸DOB NOWZD1: DOB Zoning Diagram4
08/16/2026X01103331-A1Open ↗
08/16/2026X01103331-P1Open ↗
08/13/2026X01103331-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWZoning Exhibit form (1-5)4
08/16/2026X01103331-A1Open ↗
08/16/2026X01103331-P1Open ↗
08/13/2026X01103331-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWHouse Number Verification: TOPO Stamp3
08/16/2026X01103331-P1Open ↗
08/13/2026X01103331-I1Open ↗
08/13/2026X01103331-P8Open ↗
▸Seals & Professional Certifications53
▸DOB NOWDPL-1: Design Professional Seal & Signature22
08/20/2026X01160088-I1Open ↗
08/19/2026X01245961-I1Open ↗
08/19/2026X01253773-I1Open ↗
Showing 3 of 22 on file for this type
▸DOB NOWProgress Inspector Seal & Signature17
09/21/2026X01103331-P7Open ↗
09/21/2026X01103331-P7Open ↗
09/01/2026X01103331-S4Open ↗
Showing 3 of 17 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature13
09/23/2026X01103331-S6Open ↗
09/21/2026X01103331-P7Open ↗
09/01/2026X01103331-S4Open ↗
Showing 3 of 13 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
01/24/2025240361023Open ↗
▸Trade Schedules & Equipment7
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)3
08/16/2026X01103331-P1Open ↗
08/13/2026X01103331-I1Open ↗
08/13/2026X01103331-P8Open ↗
▸DOB NOWElectric Cut-Off1
08/13/2026X01076538-I1Open ↗
▸DOB NOWWater Cut-Off1
08/13/2026X01076538-I1Open ↗
▸DOB NOWSewer Cut-Off1
08/13/2026X01076538-I1Open ↗
▸DOB NOWGas Cut-Off1
08/13/2026X01076538-I1Open ↗
▸Safety & Tenant Protection8
▸DOB NOWStreet Tree Checklist4
08/16/2026X01103331-P1Open ↗
08/16/2026X01103331-A1Open ↗
08/16/2026X01103331-P8Open ↗
Showing 3 of 4 on file for this type
▸BISBPP: STREET TREES SITE PLAN1
01/20/2026240361023Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026X01103331-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026X01103331-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026X01103331-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026X01076538-I1Open ↗
▸DOB NOWRodent Control1
08/13/2026X01076538-I1Open ↗
▸Energy Compliance2
▸DOB NOWPreliminary Commissioning Report Certification2
08/16/2026X01103331-S5Open ↗
08/16/2026X01103331-S4Open ↗
▸Inspections & Test Reports6
▸DOB NOWSOIL REPORT4
08/13/2026X01103331-S2Open ↗
08/13/2026X01103331-S1Open ↗
08/13/2026X01103331-P6Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWTR4 Test Report and Plot Diagram2
08/13/2026X01103331-S1Open ↗
08/13/2026X01103331-S2Open ↗
▸Filing & Intake Forms2
▸BISEFILING JOB APPLICATION COVER SHEET1
01/24/2025240361023Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
01/20/2026240361023Open ↗
▸Other Documents22
▸DOB NOWProperty Ownership Certification5
08/16/2026X01103331-P8Open ↗
08/16/2026X01103331-A1Open ↗
08/16/2026X01103331-P1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSite Survey: Initial4
08/16/2026X01103331-P1Open ↗
08/16/2026X01103331-A1Open ↗
08/13/2026X01103331-P8Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone4
08/16/2026X01103331-A1Open ↗
08/16/2026X01103331-P1Open ↗
08/13/2026X01103331-P8Open ↗
Showing 3 of 4 on file for this type
▸BISBPP - SUPPORTING DOCUMENTATION2
01/20/2026240361023Open ↗
01/20/2026240361023Open ↗
▸DOB NOWAdjoining Owners Notification2
08/13/2026X01103331-S1Open ↗
08/13/2026X01103331-S2Open ↗
▸DOB NOWFinal Survey2
08/16/2026X01103331-I1Open ↗
08/13/2026X01103331-I1Open ↗
▸DOB NOWCommunity Board Notification1
08/13/2026X01076538-I1Open ↗
▸DOB NOWFull Demo: 10-Day Notice1
08/13/2026X01076538-I1Open ↗
▸DOB NOWStructure Photographs1
08/13/2026X01076538-I1Open ↗