← Back
BuildNYC
Two family converted from one family
1215 EAST 22ND STREET
BROOKLYN · Midwood · BIN 3208382
💬 Discuss this project
1920Year Built
2Stories
B3Building Class
R2Zoning
2,278 sfGross Floor Area
2Units
3 Active Violations ▸FDNY Report ↗
Two family converted from one family · Owner of record: 1215 East 22nd Street Holdings · 3,500 sf lot · 0.65 FAR built · Flood zone X
Locations of Work
ArchitectureGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofUnder Construction4p · 1 filing · 2 docs
AtticUnder Construction2p · 1 filing · 2 docs
Floor 2Under Construction2p · 2 filings · 20 docs
Floor 1Unit 1AUnder Construction3p · 2 filings · 20 docs
CellarUnder Construction3p · 2 filings · 20 docs
Site & exteriorUnder Construction3p · 2 filings · 4 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
1215 East 22nd603/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
09/13/2023$1.4M—1215 EAST 22ND LLC → 1215 EAST 22ND STREET HOLDINGS LLC$622/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Q & F Construction207/01/2025
Rahman Consulting304/01/2025
MSM Engineering Services202/18/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
G Builders ManagementGeneral Contractor404/09/2026
G Builders ManagementScaffold404/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MSM Engineering Services8449107/01/2025
Building Lifecycle
11/12/2026
At time of inspection, i observed plumbing rough in installed. All work has been done without a plumbing permit.obtain a plumbing permit.
ECB violation · open
11/12/2026
At time of inspection, i observed on all 4 exposures inadequate supported scaffold not erected or maintained safely per bc.3314.1. Missing pins,…
ECB violation · open
11/12/2026
At time of inspection, i observed a stairway in the cellar consisting of 6 risers with no handrails bc 3301.2 & 27-1009(a)provide handrails as per…
ECB violation · open
06/19/2026
Objection resolved — Addressed
04/21/2026
Objection resolved — Addressed
79 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedG Builders Management03/02/2026
DOB NOWConstruction FencePermit IssuedG Builders Management03/02/2026
DOB NOWGeneral ConstructionPermit IssuedG Builders Management07/09/2025
DOB NOWConstruction FencePermit IssuedG Builders Management07/03/2025
1 project · most recent 12/19/2025
General Wiring
FiledStatusContractorScope
12/19/2025Permit IssuedEnercharge ElectricGeneral Wiring
1 project · most recent 04/01/2025
Steel Wood
FiledStatusContractorScope
04/01/2025——Steel, Wood
2 projects · most recent 05/06/2025
Fence
FiledStatusContractorScope
05/06/2025Permit IssuedG Builders ManagementFence
04/01/2025——Fence
▾Special Inspection Requirements (DOB NOW) — 36
DateRequirementInspectorRole
11/24/2025Subsurface Investigations (Borings/Test Pits)—special
11/24/2025Concrete - Cast-In-Place—special
03/31/2025Structural Steel - High Strength Bolting—special
03/31/2025Structural Steel - Details—special
03/31/2025Fire-Resistant Penetrations and Joints—special
03/31/2025Structural Cold-Formed Steel—special
03/31/2025Structural Steel - Welding—special
03/31/2025Excavations - Sheeting, Shoring, and Bracing—special
03/31/2025Structural Wood Frame—progress
03/31/2025Structural Steel - Welding—special
03/31/2025Structural Steel - High Strength Bolting—special
03/31/2025Structural Steel - Details—special
01/21/2025Electric vehicle service equipment requirements—energy_progress
01/21/2025Maintenance information—energy_progress
01/21/2025Structural Stability – Alterations of existing buildings—special
01/21/2025Structural Stability – Alterations of existing buildings—special
01/21/2025Structural Stability – Alterations of existing buildings—special
01/21/2025Fenestration areas—energy_progress
01/21/2025Metering—energy_progress
01/20/2025Footing and Foundation—progress
01/20/2025Final—progress
01/20/2025Final—progress
12/09/2024Interior lighting power—energy_progress
12/09/2024Structural Stability – Alterations of existing buildings—special
12/09/2024Fenestration and door U-factor and product ratings—energy_progress
Latest 25 of 36.
66 filed documents on file for this building. Sign in free to see the full history. Sign in · Create account