RoofUnder Construction3p · 2 filings · 20 docs
ArchitectureMechanicalPlumbing
Temp Standpipe for parking garage (Hardrock)
On file for this project
117 documents · 2 drawing sheets
FILING HEREWITH TEMPORARY CONSTRUCTION TRAILERS AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION. FILED UNDER MPP Project-000000254 AND ASSOCIATED WITH NF NB# Q01275341, SF NB# Q01267398 AND IR NB# Q01274555.
On file for this project
3 documents · 1 drawing sheet
BulkheadUnder Construction1p · 1 filing · 20 docs
Plumbing
Temp Standpipe for parking garage (Hardrock)
On file for this project
117 documents · 1 drawing sheet
Floor 8Under Construction13p · 2 filings · 20 docs
GeneralMechanicalStructural
Issued Permit Scope
Mechanical Systems · Structural
Temp Standpipe for parking garage (Hardrock)
On file for this project
117 documents
FILING HEREWITH INSTALLATION OF PRE-CONSTRUCTION TEST PILES AND TEST PITS WITH SITE RESTORATION AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION. FILED UNDER MPP Project-000000254 AND NB# Q01275341.
On file for this project
12 documents
Floor 7Under Construction93p · 1 filing · 20 docs
Fire ProtectionMechanicalStructural
Issued Permit Scope
Mechanical Systems · Standpipe · Structural
Temp Standpipe for parking garage (Hardrock)
On file for this project
117 documents
Floor 6Under Construction93p · 1 filing · 20 docs
Fire ProtectionMechanicalStructural
Issued Permit Scope
Mechanical Systems · Standpipe · Structural
Temp Standpipe for parking garage (Hardrock)
On file for this project
117 documents
Floor 5Under Construction70p · 1 filing · 20 docs
MechanicalStructural
Issued Permit Scope
Mechanical Systems · Structural
Temp Standpipe for parking garage (Hardrock)
On file for this project
117 documents
Floor 4Under Construction70p · 1 filing · 20 docs
MechanicalStructural
Issued Permit Scope
Mechanical Systems · Structural
Temp Standpipe for parking garage (Hardrock)
On file for this project
117 documents
Floor 3Under Construction112p · 1 filing · 20 docs
ArchitectureFire ProtectionMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Standpipe · Structural
Temp Standpipe for parking garage (Hardrock)
On file for this project
117 documents
Floor 2Under Construction112p · 1 filing · 20 docs
ArchitectureFire ProtectionMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Standpipe · Structural
Temp Standpipe for parking garage (Hardrock)
On file for this project
117 documents
Floor 1Under Construction132p · 2 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Construction Fence · General Construction · Mechanical Systems · Plumbing · Standpipe · Structural
Temp Standpipe for parking garage (Hardrock)
On file for this project
117 documents
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AS PER PLANS IN CONJUNCTION WITH NB CONSTRUCTION. NO CHANGE IN USE, EGRESS OR OCCUPANCY. FENCE SHALL COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE OF 2022.
On file for this project
3 documents
MezzanineUnder Construction20p · 1 filing · 20 docs
Architecture
Issued Permit Scope
General Construction
Temp Standpipe for parking garage (Hardrock)
On file for this project
117 documents
CellarUnder Construction47p · 1 filing · 20 docs
MechanicalPlumbing
Issued Permit Scope
Mechanical Systems · Plumbing
Temp Standpipe for parking garage (Hardrock)
On file for this project
117 documents