← Back
Miscellaneous one family
123 EAST 91 STREET
MANHATTAN · Upper East Side-Carnegie Hill · BIN 1048295
💬 Discuss this project
1886Year Built
4Stories
A9Building Class
R8BZoning
3,401 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Miscellaneous one family · 1,762 sf lot · 1.93 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbingGeneral
Floor 11p · 1 filing · 13 docs
Cellar3p · 1 filing · 13 docs
Sub-Basement3p · 1 filing · 13 docs
Filed — no permit issued4p · 1 filing · 6 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
SR CONSULTANT103/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/04/2024$5.9M—— → —$1,746/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
INGA CONSULTING ENGINEERS306/15/2026
W. ALLEN ENGINEERING PLLC101/22/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
LAVB DESIGN CONSULTANTS203/21/2026
SR CONSULTANT103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MORELL BUILDERS INCGeneral Contractor107/08/2026
ANGELO ANDREW INCPlumbing106/28/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CL ENGINEERING P.C.6781103/04/2025
W. ALLEN ENGINEERING PLLC664101/22/2025
Building Lifecycle
All (19)Filed (4)Permit Issued (2)Violation (4)Inspection (5)Special Inspection (4)
06/15/2026
Filed — Alteration
PLUMBING APPLICATION OF CELLAR AND BASEMENT OF AN EXISTING 4 STORY BUILDING W/ BASEMENT & CELLAR NO CHANGE OF USE EGRESS OR OCCUPANCY.
M01181271-P1
10/06/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
09/22/2025
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
08/21/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
08/20/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
04/23/2025
Permit issued — Plumbing
M01181271-S1-PL
04/23/2025
Inspection — Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet)
Certified
View inspection ↗
03/10/2025
Filed — Alteration
PLUMBING APPLICATION OF CELLAR AND BASEMENT OF AN EXISTING 4 STORY BUILDING W/ BASEMENT & CELLAR NO CHANGE OF USE EGRESS OR OCCUPANCY.
M01181271-S1
03/06/2025
Permit issued — General Construction
M01181271-I1-GC
03/04/2025
Filed — Alteration
PLUMBING APPLICATION OF CELLAR AND BASEMENT OF AN EXISTING 4 STORY BUILDING W/ BASEMENT & CELLAR NO CHANGE OF USE EGRESS OR OCCUPANCY.
M01181271-I1
01/22/2025
Filed — Alteration
M01131884-I1
12/29/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
WAYNE ALLEN
12/16/2024
Special inspection requirement — Energy Code Compliance Inspections
WAYNE ALLEN
10/24/2024
Special inspection requirement — Mechanical Systems
WAYNE ALLEN
10/24/2024
Special inspection requirement — Final
06/24/2019
Violation issued (ECB, closed)
Construction
02/22/1990
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
09/21/1989
Violation issued (ECB, closed)
Construction
09/09/1988
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offANGELO ANDREW INC04/23/2025
DOB NOWGeneral ConstructionPermit IssuedMORELL BUILDERS INC03/06/2025
1 project · most recent 06/15/2026
Gas Water/Sanitary
FiledStatusContractorScope
06/15/2026Signed-offANGELO ANDREW, INCGas, Water/Sanitary
1 project · most recent 05/07/2025
General Wiring
FiledStatusContractorScope
05/07/2025Permit IssuedFSM ELECTRICAL CORPORATIOGeneral Wiring
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
10/06/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/22/2025Fail-Final PL - Up to 3 Requested FloorsFailView ↗
08/21/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
08/20/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/23/2025Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet)CertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 4
DateRequirementInspectorRole
12/29/2024Fire-Resistant Penetrations and JointsWAYNE ALLENspecial
12/16/2024Energy Code Compliance InspectionsWAYNE ALLENprogress
10/24/2024Mechanical SystemsWAYNE ALLENspecial
10/24/2024Final—progress
▾Documents — 19 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/25/2026M01131884-I1Request digital key ↗
08/24/2026M01181271-P1Request digital key ↗
08/24/2026M01181271-S1Request digital key ↗
Showing 3 of 4 on file for this type
▸Applications & Permits4
▸DOB NOWLPC Approval/Permit4
08/24/2026M01181271-P1Open ↗
08/13/2026M01131884-I1Open ↗
08/13/2026M01181271-S1Open ↗
Showing 3 of 4 on file for this type
▸Seals & Professional Certifications8
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/24/2026M01181271-P1Open ↗
08/24/2026M01181271-S1Open ↗
08/13/2026M01181271-S1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature2
09/02/2026M01131884-I1Open ↗
09/02/2026M01131884-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature1
09/02/2026M01131884-I1Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/24/2026M01181271-P1Open ↗
08/13/2026M01181271-S1Open ↗
08/13/2026M01181271-I1Open ↗