← Back
Office with commercial, 1-6 stories
123 LAFAYETTE STREET
MANHATTAN · BIN 1002672
💬 Discuss this project
1920Year Built
5Stories
O5Building Class
M1-5/R10Zoning
17,260 sfGross Floor Area
8Units
7 Open Violations 4 unresolved · 3 paperwork only ▸FDNY Report ↗
Office with commercial, 1-6 stories · Owner of record: 7G 123 LAFAYETTE PARTNERS LLC · 3,227 sf lot · 5.35 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbingFire ProtectionGeneralOther
Permit Issued — active, not yet Signed-off
RoofUnder Construction1p · 1 filing · 10 docs
Floor 64p · 1 filing · 7 docs
Floor 53p · 1 filing · 8 docs
Floor 4
Floor 34p · 2 filings · 16 docs
Floor 211p · 4 filings · 20 docs
Floor 111p · 4 filings · 20 docs
5 jobs · most recent 03/20/2026
General Wiring Lighting
FiledStatusContractorScope
03/20/2026Permit IssuedINPUT ELECTRIC CORPGeneral Wiring
11/05/2024Permit IssuedRICHARD NEU—
09/07/2022Permit IssuedFALCO ELEC'L SERVICES INCGeneral Wiring
01/05/2022Permit IssuedJOSEPH WEINSTEIN ELECTRICGeneral Wiring
06/06/2018Permit IssuedA & A ELEC'L CONTR'G CORPGeneral Wiring, Lighting
2 jobs · most recent 10/23/2024
Scaffold Sidewalk Shed
FiledStatusContractorScope
10/23/2024Permit IssuedSAFETECH ENTERPRISES CORPScaffold, Sidewalk Shed
07/07/2020Permit IssuedRELIABLE ENTERPRISES INCScaffold
1 job · most recent 10/08/2024
Suspended Scaffold (SC)
FiledStatusContractorScope
10/08/2024Permit IssuedSAFETECH ENTERPRISES CORPSuspended Scaffold (SC)
Building Lifecycle
All (157)Filed (23)Permit Issued (19)Signed Off (8)Violation (54)Inspection (9)Objection (14)Special Inspection (30)
08/25/2026
Filed — Alteration
NON-ILLUMINATED NON-ADVERTISING DOUBLE-FACE PROJECTING ACCESSORY BANNER SIGN ON EXISTING BRACKET ARMS - NINE MOONS PIERCING. NO CHANGE OF USE, EGRESS OR OCCUPANCY.
M01442700-I1
08/25/2026
Special inspection requirement — Final
BIANCA SKVIRSKY
05/08/2026
Permit issued — Suspended Scaffold
M00966587-I1-SC
04/29/2026
Special inspection requirement — Final
Hany Rizkalla
04/22/2026
Filed — Alteration
Removal of non load bearing partitions, removal of plumbing fixtures and dropped ceiling. Add 3 office partitions and replace plumbing fixtures in place under separate LAA permit.
M01310111-P1
04/15/2026
Special inspection requirement — Final
Hany Rizkalla
12/24/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
12/08/2025
Permit issued — General Construction
M01310111-I1-GC
11/14/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
11/13/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
11/06/2025
Filed — Alteration
Removal of non load bearing partitions, removal of plumbing fixtures and dropped ceiling. Add 3 office partitions and replace plumbing fixtures in place under separate LAA permit.
M01310111-I1
11/06/2025
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
09/08/2025
Permit issued — Suspended Scaffold
M01098207-I1-SC
08/18/2025
Permit issued — General Construction
M01170035-I1-GC-CX
03/10/2025
Filed — Alteration
M01170035-I1
02/13/2025
Special inspection requirement — Energy Code Compliance Inspections
Ryan Johnson
02/13/2025
Special inspection requirement — Structural Steel - Welding
alon egozi
02/13/2025
Special inspection requirement — Masonry
Ryan Johnson
02/13/2025
Special inspection requirement — Post-installed Anchors
Ryan Johnson
02/13/2025
Special inspection requirement — Air barrier - visual inspection
Ryan Johnson
01/28/2025
Permit issued — Suspended Scaffold
M00966587-I1-SC
01/21/2025
Special inspection requirement — Structural Steel - Details
alon egozi
01/21/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Ryan Johnson
01/21/2025
Special inspection requirement — Final
Ryan Johnson
11/08/2024
Permit issued — Sidewalk Shed
M01131154-I1-SH
11/07/2024
Permit issued — Supported Scaffold
M01131154-I1-SF
11/01/2024
Objection resolved — Addressed
10/28/2024
Objection raised — Other
10/23/2024
Filed — Alteration
INSTALLATION OF 300PSF SIDEWALK SHED AND PIPE SCAFFOLDING AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CH #33 OF THE NYC CODE 2022. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
M01131154-I1
10/17/2024
Permit issued — Suspended Scaffold
M01098207-P1-SC
10/17/2024
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
Michael Walsh
10/17/2024
Special inspection requirement — Post-installed Anchors
Michael Walsh
10/16/2024
Objection resolved — Addressed
10/15/2024
Objection raised — Other
10/08/2024
Filed — Alteration
FACADE RESTORATION VIA SUSPENDED SCAFFOLDING
M01098207-P1
10/08/2024
Special inspection requirement — Post-installed Anchors
Michael Walsh
10/08/2024
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
Michael Walsh
08/27/2024
Permit issued — Suspended Scaffold
M01098207-I1-SC
08/27/2024
Objection raised — Other
08/27/2024
Objection resolved — Addressed
08/21/2024
Filed — Alteration
FACADE RESTORATION VIA SUSPENDED SCAFFOLDING
M01098207-I1
07/25/2024
Violation issued (ECB, closed)
Signs
07/25/2024
Violation issued (ECB, closed)
Signs
07/25/2024
Violation issued (ECB, closed)
Construction
07/25/2024
Violation issued (ECB, closed)
Signs
07/25/2024
Violation issued (ECB, closed)
Construction
05/23/2024
Violation issued (ECB, closed)
Construction
05/23/2024
Violation issued (ECB, closed)
Signs
03/13/2024
Filed — Alteration
M00997803-I1
12/05/2023
Permit issued — Suspended Scaffold
M00966587-I1-SC
12/04/2023
Signed off — Alteration
INTERIOR NON-STRUCTURAL DEMOLITION AND CONSTRUCTION OF SECOND FLOOR.
M00733448-I1
11/29/2023
Filed — Alteration
Painting
M00966587-I1
10/20/2022
Signed off — Alteration
MINOR RENOVATION TO EXISTING SPRINKLER SYSTEM TO ADJUST TO NEW FLOOR LAYOUT. NO CHANGE IN USE, EGRESS OR OCCUPANCY
M00636504-I1
10/18/2022
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
09/29/2022
Signed off — Alteration
INTERIOR NON-STRUCTURAL DEMOLITION AND RENOVATION TO 1ST FLOOR RETAIL. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
M00635770-I1
09/16/2022
Special inspection requirement — Lighting controls
Adrian Figueroa
09/16/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Adrian Figueroa
09/16/2022
Special inspection requirement — Final
Spencer Goroff
09/16/2022
Special inspection requirement — Interior lighting power
Adrian Figueroa
09/14/2022
Filed — Alteration
INTERIOR NON-STRUCTURAL DEMOLITION AND RENOVATION TO 1ST FLOOR RETAIL. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
M00635770-P1
Latest 60 of 157 events.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
SAFETECH ENTERPRISES607/08/2026
RELIABLE ENTERPRISES503/22/2026
123 LAFAYETTE CORP1303/22/2026
KUNBING3303/22/2026
ONWER OF 123 LAFAYETTE ST103/22/2026
OWNER OF 123 LAFAYETTE ST103/22/2026
123 LAFAYETTE ST. CORP203/22/2026
EAGLE CONSTRUCTION103/22/2026
OUTDOOR INSTALLATIONS LLC103/21/2026
THE PUBLIC THEATER103/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
08/15/2025$21.8M—— → —$1,265/sf building
01/12/2016$33.5M—— → —$1,941/sf building
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NORTHEAST EXPEDITING203/21/2026
SRA ARCHITECTURE + ENGINEERING1403/21/2026
RIGGING CONSULTANTS203/21/2026
ADVANCED BUILDERS SERVICES103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Z BARCLAY GROUP NYC CORPGeneral Contractor807/08/2026
SAFETECH ENTERPRISES CORPGeneral Contractor707/08/2026
ARMANI DESIGN AND DEVELOPGeneral Contractor303/21/2026
RELIABLE ENTERPRISES INCGeneral Contractor303/21/2026
EMPIRE GROUP NYC LLCGeneral Contractor303/21/2026
SAMUEL & SONS P & H INCPlumbing207/08/2026
EXPERT FIRE SPRINKLER,LLCFire Protection107/08/2026
MARIO CASTROElectrical103/21/2026
JOSEPH WEINSTEIN ELECTRICElectrical103/22/2026
JOHN JR MARIElectrical103/21/2026
IRVING BAPTISTEElectrical103/21/2026
FRANCIS RICHARDSElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ASE ENGINEERING PLLC5785103/10/2025
PARTRIDGE VENTURE ENGINEE7690103/10/2025
SYED ENGINEERING, P.C.7054110/23/2024
PCS ENGINEERING3745210/08/2024
SRA INSPECTIONS3461903/13/2024
SE INSPECTIONS7486201/05/2022
HATFIELD GROUP ENGINEERIN7367102/26/2021
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSuspended ScaffoldPermit IssuedOVERALL MURALS INC05/08/2026
DOB NOWGeneral ConstructionPermit IssuedARMANI DESIGN AND DEVELOP12/08/2025
DOB NOWSuspended ScaffoldPermit IssuedSAFETECH ENTERPRISES CORP09/08/2025
DOB NOWGeneral ConstructionPermit IssuedSAFETECH ENTERPRISES CORP08/18/2025
DOB NOWSuspended ScaffoldPermit IssuedOVERALL MURALS INC01/28/2025
DOB NOWSidewalk ShedPermit IssuedSAFETECH ENTERPRISES CORP11/08/2024
DOB NOWSupported ScaffoldPermit IssuedSAFETECH ENTERPRISES CORP11/07/2024
DOB NOWSuspended ScaffoldPermit IssuedSAFETECH ENTERPRISES CORP10/17/2024
DOB NOWSuspended ScaffoldPermit IssuedSAFETECH ENTERPRISES CORP08/27/2024
DOB NOWSuspended ScaffoldPermit IssuedOVERALL MURALS INC12/05/2023
DOB NOWGeneral ConstructionSigned-offZ BARCLAY GROUP NYC CORP08/16/2022
DOB NOWSprinklersSigned-offEXPERT FIRE SPRINKLER,LLC05/27/2022
DOB NOWPlumbingSigned-offSAMUEL & SONS P & H INC03/19/2022
DOB NOWGeneral ConstructionSigned-offZ BARCLAY GROUP NYC CORP02/14/2022
DOB NOWGeneral ConstructionSigned-offZ BARCLAY GROUP NYC CORP01/07/2022
DOB NOWPlumbingSigned-offSAMUEL & SONS P & H INC09/29/2021
DOB NOWStructuralSigned-offZ BARCLAY GROUP NYC CORP08/03/2021
DOB NOWGeneral ConstructionSigned-offEMPIRE GROUP NYC LLC06/08/2021
DOB NOWSupported ScaffoldPermit IssuedRELIABLE ENTERPRISES INC07/16/2020
BISOTISSUEDHIRSCH CONSTRUCTION CORP06/28/2018
BISOTISSUEDHIRSCH CONSTRUCTION CORP06/28/2018
BISOTISSUEDHIRSCH CONSTRUCTION CORP06/28/2018
BISMHISSUEDHIRSCH CONSTRUCTION CORP06/28/2018
BISOTISSUEDHIRSCH CONSTRUCTION CORP06/28/2018
BISSPISSUEDBIG APPLE FIRE SPRKL CO I06/15/2018
BISPLISSUEDM&M PLBG & HTG INC06/12/2018
BISMHISSUEDHIRSCH CONSTRUCTION CORP05/18/2018
BISOTISSUEDHIRSCH CONSTRUCTION CORP05/18/2018
BISOTISSUEDHIRSCH CONSTRUCTION CORP05/04/2018
BISOTISSUEDHIRSCH CONSTRUCTION CORP05/04/2018
BISOTISSUEDHIRSCH CONSTRUCTION CORP04/30/2018
BISOTISSUEDEMPRISE CONSTRUCTION INC04/11/2018
BISOTISSUEDMONTESBUILD INC02/28/2018
BISSPISSUEDBIG APPLE FIRE SPRKL CO I01/29/2018
BISPLISSUEDSAMUEL & SONS P & H INC10/20/2017
BISOTISSUEDLYNN AND SONS NY CONSULT10/16/2017
BISPLISSUEDMATTIELLO PLBG & HTG INC08/23/2017
BISOTISSUEDACCARDI CONSTRUCTION CORP07/28/2017
BIS—ISSUEDNEPTUNE SIGNS&AWNINGS INC04/14/2016
BIS—ISSUEDNEPTUNE SIGNS&AWNINGS INC04/13/2016
+ 29 more permits on file
▾Field Inspections (DOB CAP) — 9
DateTypeResultReport
12/24/2025Pass-Final CND-Occupancy InspectionPassView ↗
11/14/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
11/13/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
11/06/2025Fail-Final CND-Occupancy InspectionFailView ↗
10/18/2022Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
06/15/2022Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
03/30/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/29/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/01/2021Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 34
DateRequirementInspectorRole
08/25/2026FinalBIANCA SKVIRSKYprogress
04/29/2026FinalHany Rizkallaprogress
04/15/2026FinalHany Rizkallaprogress
02/13/2025Energy Code Compliance InspectionsRyan Johnsonprogress
02/13/2025Structural Steel - Weldingalon egozispecial
02/13/2025MasonryRyan Johnsonspecial
02/13/2025Post-installed AnchorsRyan Johnsonspecial
02/13/2025Air barrier - visual inspectionRyan Johnsonenergy_progress
01/21/2025Structural Steel - Detailsalon egozispecial
01/21/2025Structural Stability – Alterations of existing buildingsRyan Johnsonspecial
01/21/2025FinalRyan Johnsonprogress
10/17/2024Alternative Materials - OTCR Buildings Bulletin NumberMichael Walshspecial
10/17/2024Post-installed AnchorsMichael Walshspecial
10/08/2024Post-installed AnchorsMichael Walshspecial
10/08/2024Alternative Materials - OTCR Buildings Bulletin NumberMichael Walshspecial
09/16/2022Lighting controlsAdrian Figueroaenergy_progress
09/16/2022Fire-Resistant Penetrations and JointsAdrian Figueroaspecial
09/16/2022FinalSpencer Goroffprogress
09/16/2022Interior lighting powerAdrian Figueroaenergy_progress
09/06/2022Lighting controlsAdrian Figueroaenergy_progress
09/06/2022Final—progress
09/06/2022Fire-Resistant Penetrations and JointsAdrian Figueroaspecial
09/06/2022Interior lighting powerAdrian Figueroaenergy_progress
08/25/2022FinalSpencer Goroffprogress
08/25/2022Fire-Resistant Penetrations and JointsAdrian Figueroaspecial
Latest 25 of 34.
▾Documents — 518 on file (BIS + DOB NOW)
▸Plans & Drawings21
▸DOB NOWPlans/Sketch15
09/03/2026M00627933-P1Request digital key ↗
09/03/2026M00636504-I1Request digital key ↗
09/03/2026M00636481-I1Request digital key ↗
Showing 3 of 15 on file for this type
▸DOB NOWPlans/Sketch - General Construction3
09/03/2026M00470642-P1Request digital key ↗
09/03/2026M00470642-I1Request digital key ↗
09/03/2026M00470642-P2Request digital key ↗
▸DOB NOWPlans/Sketch - Supported Scaffold1
09/04/2026M00360610-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing1
09/04/2026M00470665-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Structural1
09/04/2026M00471927-I1Request digital key ↗
▸Applications & Permits92
▸BISPLAN / WORK APPROVAL APPLICATION52
01/06/2026102882132Open ↗
01/18/2023102882132Open ↗
08/27/2021102882132Open ↗
Showing 3 of 52 on file for this type
▸BISWORK PERMIT APPLICATION40
06/29/2018123444585Open ↗
06/29/2018123444585Open ↗
06/29/2018123206636Open ↗
Showing 3 of 40 on file for this type
▸Seals & Professional Certifications135
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION51
02/14/2020123444585Open ↗
02/14/2020123444585Open ↗
02/14/2020123444585Open ↗
Showing 3 of 51 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature18
09/03/2026M00627933-I1Open ↗
09/02/2026M00733448-I1Open ↗
09/02/2026M00733448-P1Open ↗
Showing 3 of 18 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST15
08/30/2018123547670Open ↗
05/01/2018123447813Open ↗
05/01/2018123447813Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWProgress Inspector Seal & Signature15
09/28/2026M00627933-P1Open ↗
09/23/2026M01442700-I1Open ↗
09/01/2026M00635770-I1Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature14
09/01/2026M00635770-I1Open ↗
08/31/2026M00470642-P1Open ↗
08/31/2026M00470642-I1Open ↗
Showing 3 of 14 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT8
08/30/2018123547670Open ↗
05/01/2018123447813Open ↗
05/01/2018123447813Open ↗
Showing 3 of 8 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISPC FULL REPORT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISProfessional and Owner Certification (POC3)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Trade Schedules & Equipment25
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE10
10/31/2018123444576Open ↗
10/31/2018123444585Open ↗
09/17/2018123444576Open ↗
Showing 3 of 10 on file for this type
▸BISEQUIPMENT USE PERMITS6
02/13/2020123444585Open ↗
02/13/2020123444585Open ↗
02/13/2020123444585Open ↗
Showing 3 of 6 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT4
02/13/2020123444585Open ↗
04/24/2018123444585Open ↗
Showing 2 of 4 on file for this type
▸BISSELF-CERT PLUMBING NOTICE3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISSCHEDULE B - PLUMBING2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Safety & Tenant Protection3
▸BISTenant Protection Plan and Notes3
05/01/2018123447813Open ↗
04/24/2018123444576Open ↗
04/24/2018123444585Open ↗
▸Environmental & Asbestos38
▸DOB NOWDEP ACP-5: Asbestos Assessment Report14
09/03/2026M00627933-I1Open ↗
09/02/2026M00733448-I1Open ↗
09/02/2026M00733448-P1Open ↗
Showing 3 of 14 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)8
05/01/2018123447813Open ↗
04/24/2018123444576Open ↗
04/24/2018123444585Open ↗
Showing 3 of 8 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸DOB NOWOER: Notice to Proceed4
09/02/2026M00733448-I1Open ↗
08/13/2026M01170035-I1Open ↗
08/13/2026M00997803-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWOER: Notice of Satisfaction3
09/02/2026M00733448-I1Open ↗
08/13/2026M01170035-I1Open ↗
08/13/2026M00635770-I1Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISASBESTOS: EXEMPTION (ASB4)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form1
08/13/2026M01170035-I1Open ↗
▸Energy Compliance22
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS14
02/14/2020123444585Open ↗
02/14/2020123444585Open ↗
01/30/2019123447813Open ↗
Showing 3 of 14 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS6
02/14/2020123444585Open ↗
02/14/2020123444585Open ↗
01/30/2019123447813Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT: ENERGY1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWEN2: As Built Energy Analysis1
08/13/2026M00635770-I1Open ↗
▸Inspections & Test Reports6
▸BISHYDRAULIC FLOW CALCULATIONS2
05/30/2018123444576Open ↗
05/30/2018123444576Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISINSPECTION REPORT - SUPPORTING DOCUMENTATION2
07/20/2018102882132Open ↗
Showing 1 of 2 on file for this type
▸Approvals, Objections & Sign-offs64
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST31
02/14/2020123444585Open ↗
01/30/2019123447813Open ↗
01/28/2019123444576Open ↗
Showing 3 of 31 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE16
08/27/2021102882132Open ↗
08/13/2021102882132Open ↗
08/03/2021102882132Open ↗
Showing 3 of 16 on file for this type
▸BISADMINISTRATIVE OBJECTIONS7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION7
06/20/2018123037445Open ↗
Showing 1 of 7 on file for this type
▸BISSUPERSEDING LETTER3
05/22/2018123206636Open ↗
Showing 1 of 3 on file for this type
▸Cost, Insurance & Ownership33
▸BISCOST AFFIDAVIT33
02/14/2020123444585Open ↗
01/30/2019123447813Open ↗
01/28/2019123444576Open ↗
Showing 3 of 33 on file for this type
▸Filing & Intake Forms72
▸BISBOROUGH INTAKE FORM32
02/14/2020123444585Open ↗
03/27/2019102882132Open ↗
03/15/2019102882132Open ↗
Showing 3 of 32 on file for this type
▸BISADDITIONAL INFORMATION21
03/03/2026102882132Open ↗
03/03/2026102882132Open ↗
03/03/2026102882132Open ↗
Showing 3 of 21 on file for this type
▸BISEFILING COVER SHEET15
08/30/2018123547670Open ↗
05/01/2018123447813Open ↗
05/01/2018123447813Open ↗
Showing 3 of 15 on file for this type
▸BISeFiling Job Application Cover Sheet4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸Other Documents7
▸DOB NOWManufacturer's Specifications3
08/13/2026M01098207-P1Open ↗
08/13/2026M01098207-I1Open ↗
08/13/2026M00966587-I1Open ↗
▸DOB NOWCalculations3
08/13/2026M00966587-I1Open ↗
08/13/2026M01098207-P1Open ↗
08/13/2026M01098207-I1Open ↗
▸DOB NOWPARTIAL DEMO: 10-DAY Notice1
08/13/2026M01170035-I1Open ↗