| Owner | Filings | Most Recent |
|---|---|---|
| BUSHWICK PARK 1 LLC | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/16/2024 | $1.1M | — | Private party → BUSHWICK PARK 1 LLC | $395/sf building |
| 03/18/2021 | $200K | — | Private party → Private party | $70/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| CPENGINEERING PC | 7 | 09/19/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| CASA GROUP | 12 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| NTF MANAGEMENT INC | General Contractor | 5 | 07/08/2026 |
| P.S.I. MECHANICAL | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PSI AGENCY INC. | 254 | 5 | 09/19/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Signed-off | NTF MANAGEMENT INC | 09/24/2024 |
| DOB NOW | Mechanical Systems | Signed-off | NTF MANAGEMENT INC | 08/15/2024 |
| DOB NOW | Plumbing | Signed-off | P.S.I. MECHANICAL | 05/03/2024 |
| DOB NOW | General Construction | Permit Issued | NTF MANAGEMENT INC | 04/29/2024 |
| BIS | OT | ISSUED | WILLIAM JAMES BUSHELL COR | 08/02/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/20/2024 | Complete | KJK ELECTRIC INC | General Wiring |
| 04/29/2024 | Complete | KJK ELECTRIC INC | — |
| 07/06/2022 | Complete | S&R ELECTRICAL & MECHANIC | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/05/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/05/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/07/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/07/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/19/2024 | Fire-Resistant Penetrations and Joints | MAURICIO ANDRADE | special |
| 09/19/2024 | Mechanical Systems | MAURICIO ANDRADE | special |
| 09/19/2024 | Final | MAURICIO ANDRADE | progress |
| 09/19/2024 | Energy Code Compliance Inspections | MAURICIO ANDRADE | progress |
| 09/19/2024 | HVAC-R and service water heating equipment | MAURICIO ANDRADE | energy_progress |
| 09/19/2024 | HVAC-R and service water heating system controls | MAURICIO ANDRADE | energy_progress |
| 09/19/2024 | HVAC-R and service water piping design and insulation | MAURICIO ANDRADE | energy_progress |
| 05/13/2024 | Final | MAURICIO ANDRADE | progress |
| 05/10/2024 | HVAC-R and service water heating equipment | MAURICIO ANDRADE | energy_progress |
| 05/10/2024 | HVAC-R and service water heating system controls | MAURICIO ANDRADE | energy_progress |
| 05/10/2024 | HVAC-R and service water piping design and insulation | MAURICIO ANDRADE | energy_progress |
| 05/10/2024 | Fire-Resistant Penetrations and Joints | MAURICIO ANDRADE | special |
| 05/08/2024 | HVAC-R and service water piping design and insulation | MAURICIO ANDRADE | energy_progress |
| 05/08/2024 | HVAC-R and service water heating equipment | MAURICIO ANDRADE | energy_progress |
| 05/08/2024 | HVAC-R and service water heating system controls | MAURICIO ANDRADE | energy_progress |
| 05/08/2024 | Fire-Resistant Penetrations and Joints | MAURICIO ANDRADE | special |