| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/15/2025 | $825K | — | Private party → Private party | $445/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| TEHN DESIGN GROUP | 1 | 11/21/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| JENNY FLORES EXPEDITING | 1 | 03/21/2026 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/21/2025 | — | — | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/21/2025 | — | — | Concrete |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/03/2026 | Air barrier - visual inspection | — | energy_progress |
| 03/03/2026 | Structural Stability – Alterations of existing buildings | — | special |
| 03/03/2026 | Energy Code Compliance Inspections | — | progress |
| 11/21/2025 | Concrete - Cast-In-Place | — | special |
| 11/21/2025 | Structural Wood Frame | — | progress |
| 10/31/2025 | Lowest Floor Elevation | — | progress |
| 10/10/2025 | Footing and Foundation | — | progress |
| 10/10/2025 | Final | — | progress |