Floor 3Under Construction18p · 2 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Removal of existing folding partition walls and installation of new sound rated walls between rooms 204/206 & 324/334. Provide mill work and new power and data outlets at the new wall. Scrape and repaint existing surfaces in rooms 204/206 & 324/334.
On file for this project
13 documents
REMOVE (2) SPRINKLER HEADS AND ASSOCIATED PIPING IN ROOM 336. BRANCH OFF FEEDING DEMOLISHED SPACE SHALL BE REROUTED TO ACCOMODATE RELOCATED SPRINKLER HEADS AS PER NEW ROOM LAYOUT.
On file for this project
52 documents · 1 drawing sheet
Floor 2Under Construction6p · 1 filing · 13 docs
Architecture
Issued Permit Scope
General Construction
Removal of existing folding partition walls and installation of new sound rated walls between rooms 204/206 & 324/334. Provide mill work and new power and data outlets at the new wall. Scrape and repaint existing surfaces in rooms 204/206 & 324/334.
On file for this project
13 documents
Floor 1Under Construction10p · 2 filings · 20 docs
ArchitectureGeneralMechanical
Issued Permit Scope
General Construction · Mechanical Systems
REMOVE (2) SPRINKLER HEADS AND ASSOCIATED PIPING IN ROOM 336. BRANCH OFF FEEDING DEMOLISHED SPACE SHALL BE REROUTED TO ACCOMODATE RELOCATED SPRINKLER HEADS AS PER NEW ROOM LAYOUT.
On file for this project
52 documents · 1 drawing sheet
Removing and replacing exiting concrete walkway from the main entrance. Providing epoxy injection crack repairs and sheet membrane waterproofing system as indicated on the foundation wall.
On file for this project
77 documents
Cellar1 filing · 20 docs
ArchitectureCivil
Issued Permit Scope
Earth Work · General Construction
Removing and replacing exiting concrete walkway from the main entrance. Providing epoxy injection crack repairs and sheet membrane waterproofing system as indicated on the foundation wall.
On file for this project
77 documents
Site & exterior8p · 3 filings · 20 docs
MechanicalPlumbingStructural
Issued Permit Scope
Construction Fence · Plumbing · Support of Excavation
Removing and replacing exiting concrete walkway from the main entrance. Providing epoxy injection crack repairs and sheet membrane waterproofing system as indicated on the foundation wall.
On file for this project
77 documents · 12 drawing sheets
PROPOSED: SUPPORT OF EXCAVATION TO PROVIDE SUPPORT FOR DRAINAGE PIPE REPLACEMENT AND WATERPROOFING EXTERIOR WALL. JOB FILED I N CONJUNCTION WITH DOB NOW # S00896316. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
On file for this project
8 documents · 5 drawing sheets
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE IN CONJUNCTION WITH DOB BIS JOB # S00896316
On file for this project
8 documents · 7 drawing sheets