| Owner | Filings | Most Recent |
|---|---|---|
| Calvary Baptist Church | 22 | 07/08/2026 |
| 125 West 57th Property Owner | 20 | 03/22/2026 |
| Trident General Contracting | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/15/2021 | $130.0M | — | — → — | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| WSP | 43 | 09/17/2026 |
| JLN Associates | 8 | 08/31/2026 |
| Severud Associates | 6 | 05/26/2026 |
| Eric Ettinger | 3 | 02/23/2026 |
| Harrison Yamamoto | 1 | 02/06/2026 |
| Fxcollaborative Architects | 9 | 02/05/2026 |
| Bruce Carlson | 1 | 02/05/2026 |
| Revans Design PE | 1 | 02/03/2026 |
| Akfengineers | 6 | 11/11/2025 |
| Universal Builders Supply | 14 | 11/04/2025 |
| Gensler | 1 | 05/06/2025 |
| PCS Engineering | 1 | 03/12/2025 |
| Skyline Rigging | 15 | 02/18/2025 |
| Black Sheep Engineering Group | 4 | 02/13/2025 |
| Patuxent Engineering | 4 | 01/24/2025 |
| Cpengineering | 1 | 11/11/2024 |
| Lombardo Professional Engineering | 7 | 09/10/2024 |
| Doka USA | 2 | 11/28/2023 |
| Mayrich Construction | 1 | 08/22/2022 |
| KZ Engineering | 9 | 07/19/2022 |
| Breeze National | 2 | 04/04/2022 |
| Wavic Engineering | 1 | 12/15/2021 |
| Paul Perdek, Prof. Engineering | 2 | 09/10/2021 |
| SRL Associates | 2 | 08/16/2021 |
| FL&M Engineering Design & Inspection | 1 | 09/04/2020 |
| Haider Engineering, P.E | 1 | 08/09/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| William Vitacco Associates | 67 | 03/21/2026 |
| Eurocelt Expediting | 36 | 03/21/2026 |
| Patuxent Engineering | 8 | 03/21/2026 |
| Lombardo Building Consultants | 5 | 03/21/2026 |
| Lombardo Professional Engineering | 5 | 03/21/2026 |
| Smep Design & Consultation | 2 | 03/21/2026 |
| Synergy Building Consultants | 11 | 03/21/2026 |
| Suska | 2 | 03/21/2026 |
| SNR Expediting Design | 2 | 03/21/2026 |
| Expediter | 2 | 03/21/2026 |
| A1 Expediting Service | 4 | 03/21/2026 |
| Rigging Consultants | 2 | 03/21/2026 |
| R Germain | 2 | 03/21/2026 |
| Green Studio | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JRM Construction Management | General Contractor | 13 | 09/12/2026 |
| Universal Builders Supply | Scaffold | 7 | 07/08/2026 |
| Leeding Builders Group | General Contractor | 7 | 07/08/2026 |
| A Plus Plumbing | Plumbing | 4 | 07/08/2026 |
| Tri-Star Construction | General Contractor | 4 | 07/08/2026 |
| Rael Automatic Sprinkler Co | Fire Protection | 4 | 07/08/2026 |
| Inter Connection Electric | Electrical | 3 | 03/21/2026 |
| A + Sprinkler | Fire Protection | 3 | 07/08/2026 |
| A&H Express Plumbing & Heating | Plumbing | 3 | 09/22/2026 |
| Doria Scaffolding | Scaffold | 2 | 03/21/2026 |
| Donato Plumbing Group | Plumbing | 2 | 07/08/2026 |
| Leeding Builders Group | Scaffold | 1 | 07/08/2026 |
| Inter Connection Eletric | Electrical | 1 | 03/22/2026 |
| 4IR Ideal | General Contractor | 1 | 07/08/2026 |
| Donato | General Contractor | 1 | 03/22/2026 |
| Agir Electrical Ltd D/B/A | Electrical | 1 | 03/22/2026 |
| A Plus Plumbing | Fire Protection | 1 | 06/28/2026 |
| Donato Plumbing | Plumbing | 1 | 07/08/2026 |
| Full Capacity Fire | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Eti Consultants | 7694 | 13 | 09/17/2026 |
| AK Engineering | 678 | 7 | 08/31/2026 |
| Special Testing & Consulting | 1688 | 43 | 02/19/2026 |
| Domani Inspection Service | 843 | 4 | 02/18/2026 |
| Metric Consulting and Ins | 1803 | 1 | 02/05/2026 |
| Revans Design PE | 4617 | 1 | 02/03/2026 |
| Skyline Rigging | 7880 | 15 | 02/18/2025 |
| Severud Associates | 2224 | 2 | 02/03/2023 |
| Socotec Engineering | 4983 | 2 | 04/04/2022 |
| Wavic Engineering | 1733 | 1 | 12/15/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | A&H Express Plumbing & Heating | 09/21/2026 |
| DOB NOW | Sprinklers | Permit Issued | A&H Express Plumbing & Heating | 09/21/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | JRM Construction Management | 09/10/2026 |
| DOB NOW | General Construction | Permit Issued | JRM Construction Management | 09/09/2026 |
| DOB NOW | Plumbing | Permit Issued | A&H Express Plumbing & Heating | 07/15/2026 |
| DOB NOW | General Construction | Permit Issued | JRM Construction Management | 06/04/2026 |
| DOB NOW | Structural | Signed-off | JRM Construction Management | 06/04/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | 4IR Ideal | 05/29/2026 |
| DOB NOW | Sprinklers | Permit Issued | Full Capacity Fire | 04/30/2026 |
| DOB NOW | Plumbing | Permit Issued | A Plus Plumbing | 04/29/2026 |
| DOB NOW | Sprinklers | Permit Issued | A Plus Plumbing | 04/29/2026 |
| DOB NOW | Plumbing | Permit Issued | Donato Plumbing | 04/16/2026 |
| DOB NOW | Mechanical Systems | Signed-off | JRM Construction Management | 04/10/2026 |
| DOB NOW | General Construction | Signed-off | JRM Construction Management | 04/07/2026 |
| DOB NOW | Mechanical Systems | Signed-off | Leeding Builders Group | 02/19/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Tri-Star Construction | 02/19/2026 |
| DOB NOW | Structural | Signed-off | Leeding Builders Group | 02/12/2026 |
| DOB NOW | General Construction | Permit Issued | Tri-Star Construction | 02/12/2026 |
| DOB NOW | Structural | Permit Issued | Tri-Star Construction | 02/12/2026 |
| DOB NOW | General Construction | Signed-off | Leeding Builders Group | 02/11/2026 |
| DOB NOW | Sprinklers | Permit Issued | A + Sprinkler | 01/26/2026 |
| DOB NOW | Plumbing | Signed-off | A Plus Plumbing | 01/12/2026 |
| DOB NOW | Plumbing | Signed-off | A Plus Plumbing | 01/06/2026 |
| DOB NOW | Sprinklers | Permit Issued | A + Sprinkler | 01/06/2026 |
| DOB NOW | Plumbing | Permit Issued | A Plus Plumbing | 01/06/2026 |
| DOB NOW | Sprinklers | Signed-off | A + Sprinkler | 01/06/2026 |
| DOB NOW | General Construction | Signed-off | JRM Construction Management | 12/18/2025 |
| DOB NOW | General Construction | Signed-off | JRM Construction Management | 12/18/2025 |
| DOB NOW | General Construction | Signed-off | JRM Construction Management | 12/17/2025 |
| DOB NOW | Mechanical Systems | Signed-off | JRM Construction Management | 12/17/2025 |
| DOB NOW | Mechanical Systems | Signed-off | JRM Construction Management | 12/17/2025 |
| DOB NOW | Mechanical Systems | Signed-off | JRM Construction Management | 12/16/2025 |
| DOB NOW | General Construction | Signed-off | JRM Construction Management | 12/15/2025 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | Universal Build Supp | 11/06/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Leeding Builders Group | 08/22/2025 |
| DOB NOW | Sprinklers | Signed-off | Rael Automatic Sprinkler Co | 08/21/2025 |
| DOB NOW | General Construction | Signed-off | Leeding Builders Group | 08/21/2025 |
| DOB NOW | Standpipe | Signed-off | Rael Automatic Sprinkler Co | 07/15/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | Structural Preservation System | 07/15/2025 |
| DOB NOW | Sprinklers | Signed-off | Rael Automatic Sprinkler Co | 07/15/2025 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/31/2026 | Permit Issued | JRM Construction Management | Air Conditioning Systems | — |
| 02/03/2026 | Permit Issued | 4IR Ideal | Others | Other Smog-Hog PSG-13-3 AIOFPSB 3,500 CFM ×1 |
| 11/11/2025 | Signed-off | Leeding Builders Group | Associated Ducts and Piping, Heating and Air Conditioning Systems | Heat / Cool Aaon SA-035-8-A-ET09-EJN 425,000 BTU · Rooftop Unit ×6 WHA-015-B-A-C-2-0A0-00 14,140 BTU · Rooftop Unit ×4 SA-023-8-A-ER09-EJJ 231,000 BTU · Rooftop Unit ×2 SA-030-8-A-ET09-EJM 365,000 BTU · Rooftop Unit ×2 SA-030-8-B-ET09-EJM 365,000 BTU ×2 SA-030-8-B-ET09-EJN 368,000 BTU · Makeup Air ×2 SA-035-8-B-ET09-EJN 425,000 BTU · Rooftop Unit ×2 SB-016-8-0-E80A-E2N 184,000 BTU · Rooftop Unit ×2 SB-016-B-A-E80A-E2N 181,000 BTU · Rooftop Unit ×2 WHA-018-B-A-C-2-0A0-00 49,000 BTU · Ahu ×2 WHA-048-E-A--D-2-0A0-00 49,000 BTU · Ahu ×2 Climatemaster SCP048A-HS-C0S0VS 49,000 BTU · Wshp ×2 Ducts & Piping N/A N/A Ductwork ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/17/2026 | Permit Issued | A Plus Plumbing | Sprinkler System |
| 08/31/2026 | — | — | Sprinkler System |
| 12/16/2025 | Signed-off | A + Sprinkler | 86 heads |
| 12/12/2025 | Permit Issued | A + Sprinkler | Sprinkler System |
| 11/11/2025 | Signed-off | Rael Automatic Sprinkler Co | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/17/2026 | Permit Issued | A Plus Plumbing | Water/Sanitary |
| 08/31/2026 | Permit Issued | Dependable Mechanical | Water/Sanitary |
| 05/26/2026 | Permit Issued | Dependable Mechanical | Water/Sanitary |
| 12/16/2025 | Signed-off | A Plus Plumbing | — |
| 12/16/2025 | Signed-off | A Plus Plumbing | Water/Sanitary |
| 12/12/2025 | Permit Issued | A Plus Plumbing | Water/Sanitary |
| 11/11/2025 | Signed-off | Donato | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/08/2026 | Permit Issued | Erne Valley Electrical | General Wiring |
| 08/24/2026 | Complete | Knight Electrical Service | General Wiring |
| 07/23/2026 | Permit Issued | V Electric NY | — |
| 06/03/2026 | Complete | V Electric NY | — |
| 05/29/2026 | Complete | V Electric NY | General Wiring |
| 05/08/2026 | Permit Issued | Agir Electrical Ltd D/B/A | General Wiring |
| 04/22/2026 | Permit Issued | Inter Connection Eletric | — |
| 02/04/2026 | Complete | Inter Connection Eletric | General Wiring |
| 02/04/2026 | Complete | Inter Connection Eletric | General Wiring |
| 02/02/2026 | Complete | Inter Connection Eletric | General Wiring |
| 01/27/2026 | Complete | Inter Connection Eletric | — |
| 01/27/2026 | Complete | Inter Connection Eletric | — |
| 01/27/2026 | Complete | Inter Connection Eletric | — |
| 12/10/2025 | Permit Issued | JSP Electl CNTNG | General Wiring |
| 01/24/2025 | Complete | Centrifugal Electric | General Wiring, Lighting |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/26/2026 | Permit Issued | Dependable Mechanical | Steel |
| 02/05/2026 | Signed-off | Leeding Builders Group | Steel |
| 02/03/2026 | Permit Issued | 4IR Ideal | 1 scope_items |
| 11/11/2025 | Signed-off | Donato | Steel |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/29/2026 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 09/22/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/02/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/09/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/09/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/09/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/07/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/16/2026 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 05/19/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/19/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/15/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/14/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/13/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/13/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/08/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/01/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/21/2026 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 04/06/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/20/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/16/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/11/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/03/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 02/06/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/27/2024 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 10/08/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/15/2026 | Fire-Resistant Penetrations and Joints | ANTHONY MUSUMECI | special |
| 09/15/2026 | HVAC-R and service water heating system controls | ANTHONY MUSUMECI | energy_progress |
| 09/15/2026 | HVAC-R and service water heating equipment | ANTHONY MUSUMECI | energy_progress |
| 09/15/2026 | HVAC-R and service water piping design and insulation | ANTHONY MUSUMECI | energy_progress |
| 09/15/2026 | Post-installed Anchors | ANTHONY MUSUMECI | special |
| 09/01/2026 | Metering | Ari Kamo | energy_progress |
| 09/01/2026 | Lighting controls | Ari Kamo | energy_progress |
| 09/01/2026 | Interior lighting power | Ari Kamo | energy_progress |
| 08/18/2026 | HVAC-R and service water heating equipment | Ari Kamo | energy_progress |
| 08/18/2026 | HVAC-R and service water heating system controls | Ari Kamo | energy_progress |
| 08/18/2026 | Duct leakage testing, insulation and design | Ari Kamo | energy_progress |
| 08/18/2026 | HVAC-R and service water piping design and insulation | Ari Kamo | energy_progress |
| 08/05/2026 | Fire-Resistance Rated Construction | Ari Kamo | progress |
| 08/05/2026 | Energy Code Compliance Inspections | Ari Kamo | progress |
| 07/30/2026 | Post-installed Anchors | Ari Kamo | special |
| 07/30/2026 | HVAC-R and service water heating equipment | Ari Kamo | energy_progress |
| 07/30/2026 | HVAC-R and service water piping design and insulation | Ari Kamo | energy_progress |
| 07/30/2026 | HVAC-R and service water heating system controls | Ari Kamo | energy_progress |
| 07/30/2026 | Fire-Resistant Penetrations and Joints | Ari Kamo | special |
| 07/30/2026 | Fire-Resistant Penetrations and Joints | Ari Kamo | special |
| 07/30/2026 | Fire-Resistance Rated Construction | Ari Kamo | progress |
| 07/30/2026 | Sprayed fire-resistant materials | Ari Kamo | special |
| 07/02/2026 | Final | Ari Kamo | progress |
| 07/01/2026 | Sprinkler Systems | Ari Kamo | special |
| 07/01/2026 | Mechanical Systems | Ari Kamo | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Eldridge Industries | Office | Floors 24–26 | Project M01425082 Project M01393088 |
| Calvary Baptist Church | Religious | Sub-cellar, Cellar, Floors 1–6, Mezzanine | Project M01352421 Project M01333153 Project M08010598 |