| Owner | Filings | Most Recent |
|---|---|---|
| MJH CONSTRUCTION | 3 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 03/05/2025 | $800K | — | EULAKIN HOLDING, LLC → 1251 MANAGEMENT LLC | $314/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| AG ENGINEERING PLLC | 1 | 12/12/2025 |
| XPDITE GROUP LLC | 7 | 08/25/2025 |
| VASILIOS ARTEMIOU PE | 2 | 04/03/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| XPDITE GROUP LLC (104) | 10 | 03/21/2026 |
| XPDITE GROUP LLC 104 | 2 | 03/21/2026 |
| XPDITE GROUP LLC 105 | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MJH CONSTRUCTION CORP | General Contractor | 4 | 07/08/2026 |
| QUALITY PIPING, INC | Fire Protection | 1 | 07/08/2026 |
| NESS MECHANICAL P & H INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SHAHRISH SHUVO ENGINEERIN | 8524 | 1 | 12/12/2025 |
| HRF SERVICES CORP | 5616 | 9 | 08/25/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Signed-off | MJH CONSTRUCTION CORP | 01/05/2026 |
| DOB NOW | General Construction | Permit Issued | MJH CONSTRUCTION CORP | 05/27/2025 |
| DOB NOW | Sprinklers | Signed-off | QUALITY PIPING, INC | 04/28/2025 |
| DOB NOW | Plumbing | Signed-off | NESS MECHANICAL P & H INC | 04/10/2025 |
| DOB NOW | General Construction | Permit Issued | MJH CONSTRUCTION CORP | 04/01/2025 |
| DOB NOW | Mechanical Systems | Signed-off | MJH CONSTRUCTION CORP | 03/28/2025 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 12/12/2025 | Signed-off | MJH CONSTRUCTION CORP | Heating and Air Conditioning Systems | Heat / Cool Daikin 2MXM18AVJU9 24,000 BTU · Split System ×5 3MXM24AVJU9 18,900 BTU · Split System ×2 4MXM36AVJU9 36,000 BTU · Split System ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/12/2025 | Signed-off | QUALITY PIPING, INC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/12/2025 | Signed-off | QUALITY PIPING, INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/25/2025 | Complete | S&R ELECTRICAL & MECHANIC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/12/2025 | Signed-off | MJH CONSTRUCTION CORP | Steel |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/14/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/25/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/09/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 07/07/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/06/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/28/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 04/23/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/04/2025 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 09/04/2025 | Interior lighting power | FAHAD FATEH | energy_progress |
| 09/04/2025 | Permanent certificate | FAHAD FATEH | energy_progress |
| 09/04/2025 | Maintenance information | FAHAD FATEH | energy_progress |
| 09/04/2025 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 09/04/2025 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 09/04/2025 | Fenestration areas | FAHAD FATEH | energy_progress |
| 09/04/2025 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 09/04/2025 | Metering | FAHAD FATEH | energy_progress |
| 09/04/2025 | Structural Stability – Alterations of existing buildings | FAHAD FATEH | special |
| 09/04/2025 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 09/04/2025 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 08/25/2025 | Structural Stability – Alterations of existing buildings | FAHAD FATEH | special |
| 08/25/2025 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 08/25/2025 | Maintenance information | FAHAD FATEH | energy_progress |
| 08/25/2025 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 08/25/2025 | Permanent certificate | FAHAD FATEH | energy_progress |
| 08/25/2025 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 08/25/2025 | Metering | FAHAD FATEH | energy_progress |
| 08/25/2025 | Interior lighting power | FAHAD FATEH | energy_progress |
| 08/25/2025 | Fenestration areas | FAHAD FATEH | energy_progress |
| 08/25/2025 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 08/25/2025 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 08/25/2025 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 06/19/2025 | Structural Stability – Alterations of existing buildings | FAHAD FATEH | special |