1900Year Built
6Stories
C4Building Class
C6-2GZoning
11,365 sfGross Floor Area
24Units
Rent Stabilized8 Open Violations ▸
Old law tenement · Owner of record: 126 ELIZABETH STREET, LLC · 2,520 sf lot · 4.51 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Permit Issued — active, not yet Signed-off
Floor 6Under Construction6p · 1 filing · 10 docs
Floor 55p · 1 filing · 20 docs
Floor 4
Floor 3
Floor 25p · 1 filing · 20 docs
Floor 1
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
WILLIAM GOTTLIEB MANAGEMENT2107/08/2026
126 ELIZABETH STREET1303/22/2026
W. GOTTLIEB REALTY103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
BRENT M. PORTER, ARCHITECT, AND ASS202/02/2026
ARQUITECTURA VARELA509/09/2025
GRAFEDE ARCHITECTURE, PLLC109/04/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
CM3 DESIGN STUDIO503/21/2026
ENKAY DESIGN CONSULTING403/21/2026
SOL BUILDING CONSULTING SERVICES103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NYC PAINTING CONTRACTING*General Contractor207/08/2026
HT PLUMBING & HEATING CORPlumbing207/08/2026
BABICH, ETTOREElectrical103/21/2026
CADOGAN, JOELElectrical103/21/2026
CLIFFORD, NICHOLASElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
INTEGRITY CONSULTING SERV666702/02/2026
Building Lifecycle
All (138)Filed (8)Permit Issued (5)Violation (60)Inspection (12)Objection (23)Special Inspection (30)
04/15/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/14/2026
Inspection — Certified StandPipe - SD - Alarm Sys 64/09 - Finish
Certified
View inspection ↗
04/14/2026
Inspection — Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet)
Certified
View inspection ↗
04/14/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
03/24/2026
Permit issued — General Construction
M01253279-I1-GC
03/23/2026
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
03/23/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
03/12/2026
Permit issued — Plumbing
M01253279-S1-PL
03/12/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/02/2026
Filed — Alteration
INTERIOR RENOVATION: REMOVAL OF GWB, FLR, CLG & WALL FINISHES & LIGHT FIXTS. INSTALL NEW GWB, FLR, CLG & WALL FINISHES. INSTALL REPLACEMENT LIGHT FIXTS. NO PROPOSED CHANGE TO USE, EGRESS OR OCCUPANCY. NO ENLARGEMENT OR DEVELOPMENT.
M01253279-S1
10/10/2025
Permit issued — General Construction
M01253279-I1-GC
09/29/2025
Objection raised — Admin
09/09/2025
Filed — Alteration
PLUMBING SCOPE OF WORK IN-CONJUNCTION WITH GENERAL CONSTRUCTION INTERIOR RENOVATION APPLICATION. NO CHANGE TO USE, EGRESS OR OCCUPANCY
M08052224-P3
09/05/2025
Filed — Alteration
INTERIOR RENOVATION: REMOVAL OF GWB, FLR, CLG & WALL FINISHES & LIGHT FIXTS. INSTALL NEW GWB, FLR, CLG & WALL FINISHES. INSTALL REPLACEMENT LIGHT FIXTS. NO PROPOSED CHANGE TO USE, EGRESS OR OCCUPANCY. NO ENLARGEMENT OR DEVELOPMENT.
M01253279-I1
07/11/2025
Special inspection requirement — Tenant Protection Plan Compliance
ALEKSANDR LEVIN
07/09/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
ALEKSANDR LEVIN
07/09/2025
Special inspection requirement — Tenant Protection Plan Compliance
ALEKSANDR LEVIN
07/09/2025
Special inspection requirement — Energy Code Compliance Inspections
ALEKSANDR LEVIN
07/09/2025
Special inspection requirement — Tenant Protection Plan Compliance
07/09/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
ALEKSANDR LEVIN
07/09/2025
Special inspection requirement — Lighting controls
ALEKSANDR LEVIN
07/09/2025
Special inspection requirement — Lighting in dwelling units
ALEKSANDR LEVIN
07/09/2025
Special inspection requirement — Fire-Resistance Rated Construction
ALEKSANDR LEVIN
07/09/2025
Special inspection requirement — Final
ALEKSANDR LEVIN
07/09/2025
Special inspection requirement — Energy Code Compliance Inspections
ALEKSANDR LEVIN
07/07/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
06/18/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
06/05/2025
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
04/23/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
04/15/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
04/11/2025
Special inspection requirement — Tenant Protection Plan Compliance
04/11/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
ALEKSANDR LEVIN
04/11/2025
Special inspection requirement — Energy Code Compliance Inspections
ALEKSANDR LEVIN
04/10/2025
Special inspection requirement — Lighting in dwelling units
ALEKSANDR LEVIN
04/10/2025
Special inspection requirement — Lighting controls
ALEKSANDR LEVIN
04/10/2025
Special inspection requirement — Final
ALEKSANDR LEVIN
04/10/2025
Special inspection requirement — Fire-Resistance Rated Construction
ALEKSANDR LEVIN
04/10/2025
Special inspection requirement — Energy Code Compliance Inspections
ALEKSANDR LEVIN
04/10/2025
Special inspection requirement — Tenant Protection Plan Compliance
04/10/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
ALEKSANDR LEVIN
04/01/2025
Filed — Alteration
PLUMBING SCOPE OF WORK IN-CONJUNCTION WITH GENERAL CONSTRUCTION INTERIOR RENOVATION APPLICATION. NO CHANGE TO USE, EGRESS OR OCCUPANCY
M08052224-P1
04/01/2025
Filed — Alteration
PLUMBING SCOPE OF WORK IN-CONJUNCTION WITH GENERAL CONSTRUCTION INTERIOR RENOVATION APPLICATION. NO CHANGE TO USE, EGRESS OR OCCUPANCY
M08052224-P2
03/12/2025
Special inspection requirement — Energy Code Compliance Inspections
ALEKSANDR LEVIN
03/12/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
ALEKSANDR LEVIN
03/12/2025
Special inspection requirement — Tenant Protection Plan Compliance
03/12/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
ALEKSANDR LEVIN
03/12/2025
Special inspection requirement — Tenant Protection Plan Compliance
03/12/2025
Special inspection requirement — Energy Code Compliance Inspections
ALEKSANDR LEVIN
03/12/2025
Special inspection requirement — Final
ALEKSANDR LEVIN
03/12/2025
Special inspection requirement — Fire-Resistance Rated Construction
ALEKSANDR LEVIN
03/12/2025
Special inspection requirement — Lighting controls
ALEKSANDR LEVIN
03/11/2025
Permit issued — Plumbing
M08052224-S1-PL
02/20/2025
Objection resolved — Addressed
02/20/2025
Objection resolved — Addressed
02/20/2025
Objection resolved — Addressed
02/20/2025
Objection resolved — Addressed
02/04/2025
Objection raised — Scope
02/04/2025
Objection raised — Other
02/04/2025
Objection raised — Other
02/04/2025
Objection raised — Scope
Latest 60 of 138 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedNYC PAINTING CONTRACTING*03/24/2026
DOB NOWPlumbingPermit IssuedHT PLUMBING & HEATING COR03/12/2026
DOB NOWGeneral ConstructionPermit IssuedTT & T CONSTRUCTION INC10/10/2025
DOB NOWPlumbingSigned-offHT PLUMBING & HEATING COR03/11/2025
DOB NOWGeneral ConstructionPermit IssuedNYC PAINTING CONTRACTING*02/03/2025
BISPLISSUEDMARATHON MECHANICAL LLC03/26/2015
BISOTISSUEDJEPOL CONSTRUCTION INC02/24/2015
BISBLISSUEDMARATHON MECHANICAL LLC11/29/2007
BISPLISSUEDS&B PLBG CORP03/12/1999
BISOTISSUEDWILLIAM GOTTLIEB03/12/1999
BISOTISSUEDWILLIAM GOTTLIEB01/07/1999
BISOTISSUEDWILLIAM GOTTLIEB01/05/1998
BISOTISSUEDWILLIAM GOTTLIEB01/06/1997
BISOTISSUEDWILLIAM GOTTLIEB01/22/1996
BISOTISSUEDWILLIAM GOTTLIEB01/09/1995
BISOTISSUEDWILLIAM GOTTLIEB12/28/1993
BISPLISSUEDNEW TOWN PLG & HTG04/30/1993
BISOTISSUEDWILLIAM GOTTLIEB01/08/1993
BISMHISSUEDWILLIAM GOTTLIEB01/24/1992
1 project · most recent 09/09/2025
Gas Water/Sanitary
FiledStatusContractorScope
09/09/2025Signed-offHT PLUMBING & HEATING CORGas, Water/Sanitary
1 project · most recent 04/15/2025
General Wiring
FiledStatusContractorScope
04/15/2025CompleteREDGRAVE ELECTL MAINTNCEGeneral Wiring
1 project · most recent 09/04/2024
Masonry
FiledStatusContractorScope
09/04/2024——Masonry
▾Field Inspections (DOB CAP) — 12
DateTypeResultReport
04/15/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/14/2026Certified StandPipe - SD - Alarm Sys 64/09 - FinishCertifiedView ↗
04/14/2026Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet)CertifiedView ↗
04/14/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/23/2026Certified Gas-Gas-Piping-RoughingCertifiedView ↗
03/23/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
03/12/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/07/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/18/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
06/05/2025Fail-Final PL - Up to 3 Requested FloorsFailView ↗
04/23/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
04/15/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 31
DateRequirementInspectorRole
07/11/2025Tenant Protection Plan ComplianceALEKSANDR LEVINspecial
07/09/2025Fire-Resistant Penetrations and JointsALEKSANDR LEVINspecial
07/09/2025Tenant Protection Plan ComplianceALEKSANDR LEVINspecial
07/09/2025Energy Code Compliance InspectionsALEKSANDR LEVINprogress
07/09/2025Tenant Protection Plan Compliance—special
07/09/2025Fire-Resistant Penetrations and JointsALEKSANDR LEVINspecial
07/09/2025Lighting controlsALEKSANDR LEVINenergy_progress
07/09/2025Lighting in dwelling unitsALEKSANDR LEVINenergy_progress
07/09/2025Fire-Resistance Rated ConstructionALEKSANDR LEVINprogress
07/09/2025FinalALEKSANDR LEVINprogress
07/09/2025Energy Code Compliance InspectionsALEKSANDR LEVINprogress
04/11/2025Tenant Protection Plan Compliance—special
04/11/2025Fire-Resistant Penetrations and JointsALEKSANDR LEVINspecial
04/11/2025Energy Code Compliance InspectionsALEKSANDR LEVINprogress
04/10/2025Lighting in dwelling unitsALEKSANDR LEVINenergy_progress
04/10/2025Lighting controlsALEKSANDR LEVINenergy_progress
04/10/2025FinalALEKSANDR LEVINprogress
04/10/2025Fire-Resistance Rated ConstructionALEKSANDR LEVINprogress
04/10/2025Energy Code Compliance InspectionsALEKSANDR LEVINprogress
04/10/2025Tenant Protection Plan Compliance—special
04/10/2025Fire-Resistant Penetrations and JointsALEKSANDR LEVINspecial
03/12/2025Energy Code Compliance InspectionsALEKSANDR LEVINprogress
03/12/2025Fire-Resistant Penetrations and JointsALEKSANDR LEVINspecial
03/12/2025Tenant Protection Plan Compliance—special
03/12/2025Fire-Resistant Penetrations and JointsALEKSANDR LEVINspecial
Latest 25 of 31.
▾Documents — 89 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch8
08/24/2026M08052224-P2Request digital key ↗
08/24/2026M08052224-I1Request digital key ↗
08/24/2026M08052224-P3Request digital key ↗
Showing 3 of 8 on file for this type
▸Applications & Permits12
▸BISPLAN / WORK APPROVAL APPLICATION8
09/28/2020140954536Open ↗
02/25/2019123491024Open ↗
03/08/2018121917523Open ↗
Showing 3 of 8 on file for this type
▸BISWORK PERMIT APPLICATION4
04/10/2015121917523Open ↗
02/28/2015121917523Open ↗
11/30/2007110036354Open ↗
Showing 3 of 4 on file for this type
▸Seals & Professional Certifications35
▸DOB NOWProgress Inspector Seal & Signature9
09/14/2026M08052224-P1Open ↗
09/14/2026M08052224-P1Open ↗
09/01/2026M08052224-I1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature8
08/24/2026M08052224-P1Open ↗
08/24/2026M08052224-I1Open ↗
08/24/2026M08052224-S1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature7
09/29/2026M01253279-S1Open ↗
09/14/2026M08052224-P1Open ↗
09/01/2026M08052224-I1Open ↗
Showing 3 of 7 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST3
02/25/2019123491024Open ↗
02/11/2014121917523Open ↗
11/23/2007110036354Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION3
02/25/2019123491024Open ↗
06/26/2018121917523Open ↗
02/11/2014121917523Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT2
02/25/2019123491024Open ↗
02/11/2014121917523Open ↗
▸BISPC FULL REPORT1
11/23/2007110036354Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
09/28/2020140954536Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
11/23/2007110036354Open ↗
▸Trade Schedules & Equipment4
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE3
02/25/2019123491024Open ↗
09/03/2015121917523Open ↗
02/11/2014121917523Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
11/23/2007110036354Open ↗
▸Safety & Tenant Protection2
▸BISTENANT PROTECTION PLAN AND NOTES2
09/28/2020140954536Open ↗
02/25/2019123491024Open ↗
▸Environmental & Asbestos7
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/13/2026M01253279-S1Open ↗
08/13/2026M01253279-I1Open ↗
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form2
08/24/2026M08052224-S1Open ↗
08/24/2026M08052224-I1Open ↗
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
02/28/2015121917523Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
09/28/2020140954536Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
11/23/2007110036354Open ↗
▸Energy Compliance5
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS3
02/25/2019123491024Open ↗
06/26/2018121917523Open ↗
02/11/2014121917523Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
06/26/2018121917523Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
09/28/2020140954536Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY1
09/28/2020140954536Open ↗
▸BISNOTIF.-PROPOSED STEAM/HOT WATER INSPECTION1
11/23/2007110036354Open ↗
▸Approvals, Objections & Sign-offs2
▸BISADMINISTRATIVE OBJECTIONS1
11/23/2007110036354Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
06/26/2018121917523Open ↗
▸Cost, Insurance & Ownership6
▸BISCOST AFFIDAVIT6
09/28/2020140954536Open ↗
02/25/2019123491024Open ↗
06/26/2018121917523Open ↗
Showing 3 of 6 on file for this type
▸Filing & Intake Forms6
▸BISEFILING COVER SHEET2
02/25/2019123491024Open ↗
02/11/2014121917523Open ↗
▸BISBOROUGH INTAKE FORM2
06/26/2018121917523Open ↗
12/08/2017121917523Open ↗
▸BISADDITIONAL INFORMATION1
03/08/2018121917523Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
09/28/2020140954536Open ↗