| Owner | Filings | Most Recent |
|---|---|---|
| NEW YORK CITY DEPT OF ENVIRONMENTA | 30 | 07/08/2026 |
| DEP | 1 | 03/21/2026 |
| NYC DEPARTMENT OF ENVIRONMENTAL | 6 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| HAZEN AND SAWYER | 7 | 07/20/2026 |
| BROWN AND CALDWELL | 1 | 10/24/2025 |
| SAVIN ENGINEERS | 4 | 10/09/2025 |
| PATUXENT ENGINEERING LLC | 1 | 09/25/2024 |
| B4 ARCHITECTURE LLC | 9 | 08/12/2024 |
| GREELEY AND HANSEN | 8 | 05/17/2024 |
| STV INCORPORATED | 6 | 09/09/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| HAZEN & SAWYER, P.C. | 20 | 03/21/2026 |
| GREELEY AND HANSEN | 12 | 03/21/2026 |
| BROWN & CALDWELL | 2 | 03/21/2026 |
| PATUXENT ENGINEERING | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| R.J. INDUSTRIES INC | General Contractor | 21 | 07/08/2026 |
| WDF INC | Plumbing | 14 | 07/08/2026 |
| WELKIN MECHANICAL, LLC | General Contractor | 11 | 07/08/2026 |
| R.J.I. MECHANICAL INC | Plumbing | 5 | 07/08/2026 |
| WDF INC | General Contractor | 5 | 07/08/2026 |
| ADVANCED SCAFFOLD SER.LLC | General Contractor | 3 | 03/21/2026 |
| WMP PLUMBING LLC | Plumbing | 3 | 07/08/2026 |
| SHEEHAN, EDWARD | Electrical | 1 | 03/21/2026 |
| BAUMERT, CHRISTOPHER | Electrical | 1 | 03/21/2026 |
| WM PLUMBING | Plumbing | 1 | 08/25/2026 |
| ZUCKERBERG, CHARLES | Electrical | 1 | 03/21/2026 |
| CUIFFO, JAMES | Electrical | 1 | 03/21/2026 |
| HOWARD LEWIN | Electrical | 1 | 03/21/2026 |
| KELLEHER, VINCENT | Electrical | 1 | 03/21/2026 |
| LENDER, H | Electrical | 1 | 03/21/2026 |
| PAUL KLEINBERG | Electrical | 1 | 03/21/2026 |
| RAMNAUTH, RAMANAND | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AMARACON TESTING & INSPEC | 5842 | 9 | 07/20/2026 |
| COLE TECHNOLOGIES/CONTROL | 1290 | 8 | 11/27/2024 |
| JPC LOGISTICS DBA JPCL EN | 351 | 3 | 07/28/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | WM PLUMBING | 08/24/2026 |
| DOB NOW | Plumbing | Permit Issued | WDF INC | 06/18/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | R.J. INDUSTRIES INC | 06/05/2026 |
| DOB NOW | General Construction | Permit Issued | WELKIN MECHANICAL, LLC | 03/11/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | WELKIN MECHANICAL, LLC | 03/11/2026 |
| DOB NOW | Plumbing | Permit Issued | R.J.I. MECHANICAL INC | 03/05/2026 |
| DOB NOW | General Construction | Permit Issued | R.J. INDUSTRIES INC | 02/26/2026 |
| DOB NOW | General Construction | Permit Issued | R.J. INDUSTRIES INC | 02/25/2026 |
| DOB NOW | General Construction | Permit Issued | WELKIN MECHANICAL, LLC | 12/16/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | WELKIN MECHANICAL, LLC | 12/16/2025 |
| DOB NOW | Plumbing | Permit Issued | WMP PLUMBING LLC | 12/01/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | R.J. INDUSTRIES INC | 06/11/2025 |
| DOB NOW | Plumbing | Permit Issued | R.J.I. MECHANICAL INC | 03/10/2025 |
| DOB NOW | Plumbing | Permit Issued | R.J.I. MECHANICAL INC | 03/05/2025 |
| DOB NOW | General Construction | Permit Issued | R.J. INDUSTRIES INC | 03/04/2025 |
| DOB NOW | General Construction | Permit Issued | R.J. INDUSTRIES INC | 03/04/2025 |
| DOB NOW | Plumbing | Permit Issued | WMP PLUMBING LLC | 02/26/2025 |
| DOB NOW | General Construction | Permit Issued | WELKIN MECHANICAL, LLC | 12/16/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | WELKIN MECHANICAL, LLC | 12/16/2024 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | ADVANCED SCAFFOLD SER.LLC | 09/26/2024 |
| DOB NOW | Plumbing | Permit Issued | R.J.I. MECHANICAL INC | 08/07/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | WELKIN MECHANICAL, LLC | 07/09/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | R.J. INDUSTRIES INC | 06/17/2024 |
| DOB NOW | Plumbing | Permit Issued | R.J.I. MECHANICAL INC | 06/12/2024 |
| DOB NOW | Plumbing | Permit Issued | WDF INC | 06/04/2024 |
| DOB NOW | Mechanical Systems | Signed-off | WDF INC | 05/29/2024 |
| DOB NOW | Plumbing | Signed-off | WDF INC | 05/24/2024 |
| DOB NOW | General Construction | Signed-off | WDF INC | 05/24/2024 |
| DOB NOW | Plumbing | Signed-off | WDF INC | 05/24/2024 |
| DOB NOW | Plumbing | Signed-off | WDF INC | 05/24/2024 |
| DOB NOW | Plumbing | Permit Issued | WMP PLUMBING LLC | 03/28/2024 |
| DOB NOW | General Construction | Permit Issued | R.J. INDUSTRIES INC | 03/15/2024 |
| DOB NOW | General Construction | Permit Issued | R.J. INDUSTRIES INC | 03/15/2024 |
| DOB NOW | General Construction | Permit Issued | WELKIN MECHANICAL, LLC | 03/08/2024 |
| DOB NOW | General Construction | Permit Issued | R.J. INDUSTRIES INC | 10/11/2023 |
| DOB NOW | Plumbing | Signed-off | WDF INC | 09/27/2023 |
| DOB NOW | General Construction | Permit Issued | R.J. INDUSTRIES INC | 09/06/2023 |
| DOB NOW | Mechanical Systems | Signed-off | WDF INC | 05/09/2023 |
| DOB NOW | Plumbing | Signed-off | WDF INC | 04/06/2023 |
| DOB NOW | Plumbing | Permit Issued | WDF INC | 04/06/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 10/09/2025 | Permit Issued | WELKIN MECHANICAL, LLC | Heating Systems, Ventilation Systems | |
| 05/16/2024 | Permit Issued | R.J. INDUSTRIES INC | Heating and Air Conditioning Systems | Heat / Cool |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/17/2024 | Permit Issued | R.J.I. MECHANICAL INC | Water/Sanitary |
| 09/09/2022 | Permit Issued | WDF INC | Water/Sanitary |
| 09/09/2022 | Signed-off | WDF INC | Storm |
| 09/09/2022 | Signed-off | WDF INC | Storm |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/18/2025 | Complete | KLEINBERG ELECTRIC, INC. | — |
| 06/06/2024 | Permit Issued | A TECH ELEC ENTERPRISES | General Wiring |
| 02/22/2024 | Permit Issued | GILSTON ELEC'L CONTNG LLC | — |
| 02/22/2024 | Permit Issued | GILSTON ELEC'L CONTNG LLC | General Wiring |
| 10/12/2023 | Complete | P & M ELECT'L CONTR. CORP | General Wiring |
| 10/11/2023 | Complete | WINDSOR ELEC CONT'G INC. | General Wiring |
| 07/14/2023 | Permit Issued | GILSTON ELEC'L CONTNG LLC | General Wiring |
| 04/27/2023 | Complete | ELEMCO SERVICES, INC | — |
| 04/14/2023 | Permit Issued | GILSTON ELEC'L CONTNG LLC | — |
| 12/23/2022 | Complete | A TECH ELEC ENTERPRISES | General Wiring |
| 07/14/2022 | Permit Issued | A TECH ELEC ENTERPRISES | General Wiring |
| 05/13/2022 | Permit Issued | A TECH ELEC ENTERPRISES | General Wiring |
| 03/29/2022 | Complete | EIA ELECTRIC, INC | General Wiring |
| 02/17/2019 | Complete | PJS ELECTRIC, INC. | — |
| 10/31/2018 | Complete | ELDOR ELECTRIC LLC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/24/2025 | — | — | Concrete |
| 08/17/2023 | Permit Issued | R.J. INDUSTRIES INC | 1 scope_items |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/06/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 08/05/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/03/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/10/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 07/28/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/16/2025 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 09/25/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/03/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/24/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/18/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/02/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/22/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/07/2026 | Fire-Resistant Penetrations and Joints | CONNIE PISANI | special |
| 11/07/2025 | HVAC and service water heating equipment | CONNIE PISANI | energy_progress |
| 11/07/2025 | HVAC and service water heating system controls | CONNIE PISANI | energy_progress |
| 11/07/2025 | Shutoff dampers | CONNIE PISANI | energy_progress |
| 11/07/2025 | Mechanical Systems | CONNIE PISANI | special |
| 11/07/2025 | Final | CONNIE PISANI | progress |
| 11/07/2025 | Maintenance information | CONNIE PISANI | energy_progress |
| 11/07/2025 | HVAC insulation and sealing | CONNIE PISANI | energy_progress |
| 11/07/2025 | Duct leakage testing | CONNIE PISANI | energy_progress |
| 11/07/2025 | Electrical motors | CONNIE PISANI | energy_progress |
| 06/25/2025 | Post-installed Anchors | — | special |
| 06/02/2025 | Final | — | progress |
| 08/20/2024 | Fire-Resistant Penetrations and Joints | GEORGE ANDERSEN | special |
| 08/20/2024 | Final | GEORGE ANDERSEN | progress |
| 08/13/2024 | Post-installed Anchors | GEORGE ANDERSEN | special |
| 08/13/2024 | Energy Code Compliance Inspections | GEORGE ANDERSEN | progress |
| 08/13/2024 | Exterior lighting power | GEORGE ANDERSEN | energy_progress |
| 08/13/2024 | Fenestration and door U-factor and product ratings | GEORGE ANDERSEN | energy_progress |
| 08/13/2024 | Fire-Resistant Penetrations and Joints | GEORGE ANDERSEN | special |
| 08/12/2024 | Final | GEORGE ANDERSEN | progress |
| 07/29/2024 | Final | Asma Hashmi | progress |
| 07/29/2024 | Mechanical Systems | Asma Hashmi | special |
| 07/29/2024 | Duct leakage testing, insulation and design | Asma Hashmi | energy_progress |
| 07/29/2024 | HVAC-R and service water heating system controls | Asma Hashmi | energy_progress |
| 07/29/2024 | HVAC-R and service water piping design and insulation | Asma Hashmi | energy_progress |