← Back
Public elementary, junior or senior high
128-02 7 AVENUE
QUEENS · College Point · BIN 4616894
💬 Discuss this project
1933Year Built
4Stories
W1Building Class
R2AZoning
171,435 sfGross Floor Area
1Units
LL97 Covered7 Open Violations 5 unresolved · 2 paperwork only ▸FDNY Report ↗
Public elementary, junior or senior high · Owner of record: NYC DEPARTMENT OF EDUCATION · 90,000 sf lot · 1.9 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbing
Basement4p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
TECHNICO CONSTRUCTION SER403/22/2026
NYC SCHOOL CONSTRUCTION AUTHORITY1903/21/2026
NYCSCA303/21/2026
SCHOOL OF CONSTRUCTION AUTHORITY103/21/2026
NYC SCHOOL CONSTRUCTION203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
STV INCORPORATED406/04/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
STV803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ARCADIA ELECTL CO INC 002039General Contractor103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
UNIVERSAL TESTING AND INS400210/27/2021
Building Lifecycle
All (46)Filed (4)Violation (12)Objection (6)Special Inspection (24)
11/18/2025
Violation issued (FDNY_NOV, closed)
07/22/2025
Special inspection requirement — Post-installed Anchors
07/22/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
06/13/2025
Objection raised — Other
06/13/2025
Objection resolved — Addressed
06/13/2025
Objection raised — Other
06/13/2025
Objection resolved — Addressed
06/04/2025
Filed — Alteration
Q129_Demolish concrete equipment pad and provide new. Remove window with fixed louver and replace with new window. Remove existing vent between gas-fired heater and masonry chimney.
Q01234912-I1
06/04/2025
Filed — Alteration
Q129_Demolish concrete equipment pad and provide new. Remove window with fixed louver and replace with new window. Remove existing vent between gas-fired heater and masonry chimney.
Q01234912-S1
06/04/2025
Special inspection requirement — HVAC-R and service water heating system controls
06/04/2025
Special inspection requirement — Energy Code Compliance Inspections
06/04/2025
Special inspection requirement — Electrical motors and elevators
06/04/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
06/04/2025
Special inspection requirement — Maintenance information
06/04/2025
Special inspection requirement — HVAC-R and service water heating equipment
06/04/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
06/02/2025
Special inspection requirement — Final
06/02/2025
Special inspection requirement — Mechanical Systems
06/30/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/30/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
04/25/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
04/25/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
02/23/2022
Special inspection requirement — Energy Code Compliance Inspections
NELSON LOPEZ
02/23/2022
Special inspection requirement — Electrical motors and elevators
NELSON LOPEZ
11/01/2021
Objection raised — Other
11/01/2021
Objection resolved — Addressed
10/27/2021
Filed — Alteration
Q129_Remove and replace motorized damper, fire damper, and concrete pad. Provide new gas vent, stainless steel pipe liner, barometric damper, drain pipe and p-trap.
Q00617294-S1
10/25/2021
Special inspection requirement — Shutoff dampers
NELSON LOPEZ
10/25/2021
Special inspection requirement — Mechanical Systems
NELSON LOPEZ
10/25/2021
Special inspection requirement — Chimneys and vents
NELSON LOPEZ
10/25/2021
Special inspection requirement — Final
NELSON LOPEZ
10/25/2021
Special inspection requirement — Energy Code Compliance Inspections
NELSON LOPEZ
10/22/2021
Filed — Alteration
Q129_Remove and replace motorized damper, fire damper, and concrete pad. Provide new gas vent, stainless steel pipe liner, barometric damper, drain pipe and p-trap.
Q00617294-I1
10/22/2021
Special inspection requirement — Post-installed Anchors
NELSON LOPEZ
10/22/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
NELSON LOPEZ
10/22/2021
Special inspection requirement — Maintenance information
NELSON LOPEZ
10/22/2021
Special inspection requirement — HVAC-R and service water heating system controls
NELSON LOPEZ
10/22/2021
Special inspection requirement — HVAC-R and service water piping design and insulation
NELSON LOPEZ
10/22/2021
Special inspection requirement — HVAC-R and service water heating equipment
NELSON LOPEZ
01/05/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
08/13/2020
Violation issued (FDNY_ORDER, closed)
01/27/2020
Violation issued (ECB, closed)
Construction
01/27/2020
Violation issued (ECB, closed)
Construction
01/27/2020
Violation issued (ECB, closed)
Construction
01/27/2020
Violation issued (ECB, closed)
Construction
04/18/2019
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
BISPLISSUEDVITAL PLUMBING, INC08/17/2023
BISPLISSUEDVITAL PLUMBING, INC09/28/2022
BIS—ISSUEDTECHNICO CONSTRUCTION03/22/2022
BIS—ISSUEDTECHNICO CONSTRUCTION03/22/2022
BISPLISSUEDVITAL PLUMBING, INC10/01/2021
BIS—ISSUEDTECHNICO CONSTRUCTION03/23/2021
BIS—ISSUEDTECHNICO CONSTRUCTION03/23/2021
BIS—ISSUEDTECHNICO CONSTRUCTION03/11/2021
BIS—ISSUEDTECHNICO CONSTRUCTION03/11/2021
BISPLISSUEDVITAL PLUMBING, INC10/09/2020
BISOTISSUEDNYC SCHOOL CONSTRUCTION AUTHORIT07/23/2020
BIS—ISSUEDTECHNICO CONSTRUCTION03/26/2020
BIS—ISSUEDTECHNICO CONSTRUCTION03/26/2020
BIS—ISSUEDTECHNICO CONSTRUCTION12/26/2019
BISPLISSUEDMACCARONE PLUMBING INC10/18/2019
BISPLISSUEDVITAL PLUMBING, INC10/04/2019
BISEQISSUEDROMA SCAFFOLDING INC09/16/2019
BISOTISSUEDDARCON CONSTRUCTION INC09/13/2019
BIS—ISSUEDTECHNICO CONSTRUCTION12/31/2018
BIS—ISSUEDTECHNICO CONSTRUCTION12/31/2018
BISPLISSUEDMACCARONE PLUMBING INC10/25/2018
BISEQISSUEDROMA SCAFFOLDING INC10/23/2018
BISPLISSUEDVITAL PLUMBING, INC10/12/2018
BIS—ISSUEDTECHNICO CONSTRUCTION10/12/2018
BISOTISSUEDDARCON CONSTRUCTION INC10/12/2018
BISEQISSUEDROMA SCAFFOLDING INC09/13/2018
1 project · most recent 06/04/2025
Gas Water/Sanitary
FiledStatusContractorScope
06/04/2025——Gas, Water/Sanitary
3 projects · most recent 07/30/2019
General Wiring
FiledStatusContractorScope
07/30/2019CompleteARCADIA ELECT'L CO. INC.General Wiring
04/09/2019CompleteARCADIA ELECT'L CO. INC.General Wiring
09/11/2018CompleteSTANCO SYSTEM ELEC'L CONT—
▾Special Inspection Requirements (DOB NOW) — 24
DateRequirementInspectorRole
07/22/2025Post-installed Anchors—special
07/22/2025Fire-Resistant Penetrations and Joints—special
06/04/2025HVAC-R and service water heating system controls—energy_progress
06/04/2025Energy Code Compliance Inspections—progress
06/04/2025Electrical motors and elevators—energy_progress
06/04/2025HVAC-R and service water piping design and insulation—energy_progress
06/04/2025Maintenance information—energy_progress
06/04/2025HVAC-R and service water heating equipment—energy_progress
06/04/2025Fire-Resistant Penetrations and Joints—special
06/02/2025Final—progress
06/02/2025Mechanical Systems—special
02/23/2022Energy Code Compliance InspectionsNELSON LOPEZprogress
02/23/2022Electrical motors and elevatorsNELSON LOPEZenergy_progress
10/25/2021Shutoff dampersNELSON LOPEZenergy_progress
10/25/2021Mechanical SystemsNELSON LOPEZspecial
10/25/2021Chimneys and ventsNELSON LOPEZspecial
10/25/2021FinalNELSON LOPEZprogress
10/25/2021Energy Code Compliance InspectionsNELSON LOPEZprogress
10/22/2021Post-installed AnchorsNELSON LOPEZspecial
10/22/2021Fire-Resistant Penetrations and JointsNELSON LOPEZspecial
10/22/2021Maintenance informationNELSON LOPEZenergy_progress
10/22/2021HVAC-R and service water heating system controlsNELSON LOPEZenergy_progress
10/22/2021HVAC-R and service water piping design and insulationNELSON LOPEZenergy_progress
10/22/2021HVAC-R and service water heating equipmentNELSON LOPEZenergy_progress
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Queens P.S. 129Education—
Project Q00617294 Alteration · Approved · 10/22/2021
Read from each project’s drawing title blocks and cover sheets and checked twice; a name appears only when it is the occupant, never the owner, landlord or designer.
▾Documents — 35 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/27/2026Q00617294-I1Request digital key ↗
08/15/2026Q01234912-I1Request digital key ↗
08/15/2026Q01234912-S1Request digital key ↗
Showing 3 of 4 on file for this type
▸Applications & Permits1
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
06/15/2020421106172Open ↗
▸Seals & Professional Certifications10
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/20/2026Q01234912-S1Open ↗
08/20/2026Q01234912-I1Open ↗
08/13/2026Q00617294-S1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
08/25/2026Q00617294-I1Open ↗
08/25/2026Q00617294-I1Open ↗
08/22/2026Q00617294-S1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature2
08/25/2026Q00617294-I1Open ↗
08/22/2026Q00617294-S1Open ↗
▸Trade Schedules & Equipment1
▸BISFA - FDNY APPROVAL : FD-FAA1
07/29/2022421106047Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form1
08/13/2026Q00617294-I1Open ↗
▸Approvals, Objections & Sign-offs13
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter4
08/13/2026Q01234912-S1Open ↗
08/13/2026Q01234912-I1Open ↗
08/13/2026Q00617294-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)4
08/13/2026Q00617294-S1Open ↗
08/13/2026Q00617294-I1Open ↗
08/13/2026Q01234912-I1Open ↗
Showing 3 of 4 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST3
02/10/2021421106172Open ↗
11/12/2020421106172Open ↗
08/14/2020421106172Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION2
11/12/2020421106172Open ↗
11/12/2020421106172Open ↗
▸Filing & Intake Forms1
▸BISBOROUGH INTAKE FORM1
06/08/2020421106172Open ↗
▸Other Documents4
▸DOB NOWNYCSCA - BCC Plan Examination Transmittal4
08/13/2026Q01234912-I1Open ↗
08/13/2026Q00617294-I1Open ↗
08/13/2026Q00617294-S1Open ↗
Showing 3 of 4 on file for this type