| Owner | Filings | Most Recent |
|---|---|---|
| 128 Newport Owners CP | 4 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Eoc-NY | 3 | 11/17/2026 |
| Azimuth Engineering | 1 | 12/16/2022 |
| Syed Engineering | 1 | 10/06/2021 |
| Dooling & Company Architects | 1 | 10/15/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| AE Design Solution | 2 | 03/21/2026 |
| Biltmore Group | 2 | 03/21/2026 |
| Expediting | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Topline NYC Contracting | Scaffold | 3 | 03/21/2026 |
| Core Scaffold Systems | Scaffold | 3 | 03/21/2026 |
| Gotham Communications | specialty_contractor | 3 | 03/21/2026 |
| Zanis Restoration | specialty_contractor | 1 | 07/08/2026 |
| Sega Renovation | General Contractor | 1 | 11/08/2026 |
| A&C Combustion Service | General Contractor | 1 | 05/13/2003 |
| A.G.S. Improvements | General Contractor | 1 | 10/04/2019 |
| Berniler Communications | General Contractor | 1 | 10/15/1999 |
| Odyssia Global Commercial | General Contractor | 1 | 07/09/2012 |
| Red Wing Electric | General Contractor | 1 | 10/09/2014 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AK Consulting Services, I | 6198 | 1 | 05/06/2026 |
| Eoc-NY | 6548 | 2 | 05/06/2026 |
| Jeremy K McKeon, P.E. | 7263 | 1 | 12/16/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | Sega Renovation | 11/04/2026 |
| DOB NOW | Antenna | Signed-off | Gotham Communications | 05/12/2023 |
| DOB NOW | General Construction | Signed-off | Zanis Restoration | 03/25/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | Topline NYC Contracting | 10/07/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | Core Scaffold Systems | 10/16/2019 |
| BIS | OT | ISSUED | A.G.S. Improvements | 10/04/2019 |
| BIS | OT | ISSUED | Crosslink Wireless | 10/09/2014 |
| BIS | OT | ISSUED | Odyssia Global Commercial | 07/09/2012 |
| BIS | OT | ISSUED | A&C Combustion Service | 05/13/2003 |
| BIS | OT | ISSUED | Berniler Communications | 10/15/1999 |
| BIS | OT | ISSUED | GJF Construction Corp.d/B/A NYC | 03/19/1997 |
| BIS | OT | ISSUED | GJF Construction Corp.d/B/A NYC Buildings | 11/25/1996 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/12/2021 | Complete | Richard Neu | — |
| 10/10/2019 | Complete | V. Vass Electric | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/06/2026 | Tenant Protection Plan Compliance | — | special |
| 02/18/2026 | Final | — | progress |
| 02/18/2026 | Concrete - Cast-In-Place | — | special |
| 02/18/2026 | Post-installed Anchors | — | special |
| 02/18/2026 | Structural Stability – Alterations of existing buildings | — | special |
| 12/14/2021 | Masonry | David Merabyan | special |
| 12/14/2021 | Post-installed Anchors | David Merabyan | special |
| 12/14/2021 | Structural Stability – Alterations of existing buildings | David Merabyan | special |
| 12/14/2021 | Final | David Merabyan | progress |
| 10/11/2019 | Final | MARK DOOLING | progress |