← Back
One story - permanent living quarter
128-36 HOOK CREEK BOULEVARD
QUEENS · Rosedale · BIN 4277226
💬 Discuss this project
1955Year Built
1.5Stories
A2Building Class
R2Zoning
1,119 sfGross Floor Area
1Units
One story - permanent living quarter · Owner of record: 12836 HOOKCREEK BLVD LLC · 3,920 sf lot · 0.29 FAR built · Flood zone X
Locations of Work
Structural
Permit Issued — active, not yet Signed-off
Roof1p · 1 filing · 7 docs
Floor 2Under Construction2p · 1 filing · 20 docs
Floor 1Under Construction2p · 1 filing · 20 docs
CellarUnder Construction3p · 2 filings · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
08/04/2025$590K—WEST GATE REALTY ADVISORS CORP. → 12836 HOOKCREEK BLVD LLC$527/sf building
06/24/2025$480K—— → —$429/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ARCHITECTURAL CONCEPT401/22/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ARCHITECTUAL CONCEPT803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ASSET EQUITY SOLUTIONSGeneral Contractor107/08/2026
BVC CONSULTING INCGeneral Contractor104/09/2026
RS DESIGN ASSOCIATES INCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ARCHITECTURAL CONCEPT3642112/30/2025
Building Lifecycle
All (36)Filed (4)Permit Issued (2)Special Inspection (30)
06/18/2026
Permit issued — Foundation
Q01334543-I1-GC-CX
05/29/2026
Special inspection requirement — Maintenance information
05/26/2026
Permit issued — Construction Fence
Q01325095-I1-FN
01/28/2026
Special inspection requirement — Duct leakage testing, insulation and design
MUZAFFAR JAMAL
01/28/2026
Special inspection requirement — Electric vehicle service equipment requirements
MUZAFFAR JAMAL
01/28/2026
Special inspection requirement — Insulation placement and R values
MUZAFFAR JAMAL
01/22/2026
Filed — Alteration CO
Q01334543-S1
01/22/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
01/22/2026
Special inspection requirement — Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities
01/22/2026
Special inspection requirement — Energy Code Compliance Inspections
01/22/2026
Special inspection requirement — HVAC-R and service water heating equipment
01/22/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
01/22/2026
Special inspection requirement — HVAC-R and service water heating system controls
01/22/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
12/30/2025
Filed — Alteration CO
Q01334543-I1
12/16/2025
Special inspection requirement — Structural Wood Frame
MUZAFFAR JAMAL
12/16/2025
Special inspection requirement — Air barrier - visual inspection
MUZAFFAR JAMAL
12/16/2025
Special inspection requirement — Fenestration air leakage
MUZAFFAR JAMAL
12/16/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
MUZAFFAR JAMAL
12/16/2025
Special inspection requirement — Fenestration areas
MUZAFFAR JAMAL
12/16/2025
Special inspection requirement — Mechanical Systems
MUZAFFAR JAMAL
12/16/2025
Special inspection requirement — HVAC-R and service water heating equipment
MUZAFFAR JAMAL
12/16/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
MUZAFFAR JAMAL
12/16/2025
Special inspection requirement — Ventilation and air distribution system
MUZAFFAR JAMAL
12/16/2025
Special inspection requirement — HVAC-R and service water heating system controls
MUZAFFAR JAMAL
12/16/2025
Special inspection requirement — Interior lighting power
MUZAFFAR JAMAL
12/16/2025
Special inspection requirement — Concrete - Cast-In-Place
MUZAFFAR JAMAL
12/16/2025
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
MUZAFFAR JAMAL
12/16/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
MUZAFFAR JAMAL
12/16/2025
Special inspection requirement — Heating Systems
MUZAFFAR JAMAL
12/16/2025
Special inspection requirement — Masonry
MUZAFFAR JAMAL
12/16/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
MUZAFFAR JAMAL
12/16/2025
Special inspection requirement — Final
Syed Naqvi
12/16/2025
Special inspection requirement — Footing and Foundation
MUZAFFAR JAMAL
12/04/2025
Filed — Alteration
Install new construction fence as per drawing.
Q01325095-I1
11/29/2025
Filed — Alteration
ADDITION & ALTERATION OF EXISTING ONE FAMILY HOUSE. CELLAR, / 1ST FLOOR, 2ND FLOOR ADDITION AS PER DRAWINGS HEREWITH FILED. NO CHANGE IN EGRESS, USE, OR OCCUPANCY
Q01324405-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWFoundationPermit IssuedASSET EQUITY SOLUTIONS06/18/2026
DOB NOWConstruction FencePermit IssuedRS DESIGN ASSOCIATES INC05/26/2026
1 project · most recent 11/29/2025
Heating and Air Conditioning Systems Others Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
11/29/2025——Heating and Air Conditioning Systems, Others, Ventilation Systems
Heat / Cool
Goodman AMST 36CU14 3 tons · Ahu ×2
Ventilation
Greenheck SP-C50-QD 50 CFM · Exhaust Fan ×5
SP-B90 100 CFM · Exhaust Fan ×1
Other
A.O. Smith GDHE75 75,000 BTU · Water Heater ×1
1 project · most recent 09/15/2026
General Wiring
FiledStatusContractorScope
09/15/2026Permit IssuedR.A. PHILLIPS ELEC'L CONTGeneral Wiring
1 project · most recent 11/29/2025
Wood
FiledStatusContractorScope
11/29/2025——Wood
1 project · most recent 12/04/2025
Fence
FiledStatusContractorScope
12/04/2025Permit IssuedRS DESIGN ASSOCIATES INCFence
▾Special Inspection Requirements (DOB NOW) — 32
DateRequirementInspectorRole
05/29/2026Maintenance information—energy_progress
01/28/2026Duct leakage testing, insulation and designMUZAFFAR JAMALenergy_progress
01/28/2026Electric vehicle service equipment requirementsMUZAFFAR JAMALenergy_progress
01/28/2026Insulation placement and R valuesMUZAFFAR JAMALenergy_progress
01/22/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation—special
01/22/2026Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities—special
01/22/2026Energy Code Compliance Inspections—progress
01/22/2026HVAC-R and service water heating equipment—energy_progress
01/22/2026HVAC-R and service water piping design and insulation—energy_progress
01/22/2026HVAC-R and service water heating system controls—energy_progress
01/22/2026Fire-Resistant Penetrations and Joints—special
12/16/2025Structural Wood FrameMUZAFFAR JAMALprogress
12/16/2025Air barrier - visual inspectionMUZAFFAR JAMALenergy_progress
12/16/2025Fenestration air leakageMUZAFFAR JAMALenergy_progress
12/16/2025HVAC-R and service water piping design and insulationMUZAFFAR JAMALenergy_progress
12/16/2025Fenestration areasMUZAFFAR JAMALenergy_progress
12/16/2025Mechanical SystemsMUZAFFAR JAMALspecial
12/16/2025HVAC-R and service water heating equipmentMUZAFFAR JAMALenergy_progress
12/16/2025Fenestration and door U-factor and product ratingsMUZAFFAR JAMALenergy_progress
12/16/2025Ventilation and air distribution systemMUZAFFAR JAMALenergy_progress
12/16/2025HVAC-R and service water heating system controlsMUZAFFAR JAMALenergy_progress
12/16/2025Interior lighting powerMUZAFFAR JAMALenergy_progress
12/16/2025Concrete - Cast-In-PlaceMUZAFFAR JAMALspecial
12/16/2025Excavations - Sheeting, Shoring, and BracingMUZAFFAR JAMALspecial
12/16/2025Fire-Resistant Penetrations and JointsMUZAFFAR JAMALspecial
Latest 25 of 32.
▾Documents — 30 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/18/2026Q01324405-I1Request digital key ↗
08/18/2026Q01325095-I1Request digital key ↗
08/17/2026Q01334543-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸Zoning, Tax Lot & Property Records4
▸DOB NOWZD1: DOB Zoning Diagram3
08/17/2026Q01334543-I1Open ↗
08/13/2026Q01324405-I1Open ↗
08/13/2026Q01334543-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026Q01334543-I1Open ↗
▸Seals & Professional Certifications8
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/13/2026Q01334543-S1Open ↗
08/13/2026Q01334543-I1Open ↗
08/13/2026Q01325095-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature3
08/25/2026Q01334543-I1Open ↗
08/25/2026Q01334543-I1Open ↗
08/25/2026Q01334543-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/25/2026Q01334543-I1Open ↗
▸Safety & Tenant Protection2
▸DOB NOWStreet Tree Checklist2
08/17/2026Q01334543-I1Open ↗
08/13/2026Q01334543-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/17/2026Q01334543-S1Open ↗
08/17/2026Q01334543-I1Open ↗
▸Inspections & Test Reports2
▸DOB NOWGeotechnical Report (BC 1803.6)2
08/13/2026Q01334543-I1Open ↗
08/13/2026Q01324405-I1Open ↗
▸Other Documents8
▸DOB NOWSite Survey: Initial2
08/13/2026Q01334543-I1Open ↗
08/13/2026Q01324405-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026Q01334543-I1Open ↗
08/13/2026Q01324405-I1Open ↗
▸DOB NOWPlot Diagram2
08/13/2026Q01324405-I1Open ↗
08/13/2026Q01334543-I1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/17/2026Q01334543-I1Open ↗
▸DOB NOWProperty Ownership Certification1
08/13/2026Q01334543-I1Open ↗