← Back
BuildNYC
Hospital, sanitarium, mental institution
NewYork-Presbyterian David H. Koch Center
1283 YORK AVENUE · BIN 1090254
💬 Discuss this project
2014Year Built
17Stories
I1Building Class
R10Zoning
733,747 sfGross Floor Area
1Units
LL97 CoveredRent Stabilized0 Active Violations 2 likely answered 1 old, status unconfirmed ▸FISP: SAFEFDNY Report ↗
Hospital, sanitarium, mental institution · Owner of record: The New York and Presbyterian Hospital · 42,677 sf lot · 17.19 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
Floor 17NewYork-PresbyterianUnder Construction10p · 1 filing · 10 docs
Floor 16NewYork-Presbyterian1p · 1 filing · 7 docs
Floor 15
Floor 14NewYork-Presbyterian8p · 2 filings · 6 docs
Floor 13
Floor 12
Floor 11
Floor 10
Floor 9
Floor 8NewYork-Presbyterian13p · 3 filings · 13 docs
Floor 7NewYork-PresbyterianUnder Construction39p · 3 filings · 16 docs
Floor 6NewYork-Presbyterian9p · 1 filing · 3 docs
Floor 5NewYork-Presbyterian33p · 4 filings · 16 docs
Floor 4NewYork-Presbyterian19p · 3 filings · 10 docs
Floor 3
Floor 2
Floor 1
CellarNewYork-PresbyterianUnder Construction1p · 1 filing · 10 docs
Sub-CellarNewYork-Presbyterian8p · 1 filing · 7 docs
Site & exteriorNewYork-Presbyterian7p · 3 filings · 15 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
New York Presbyterian Hospital15809/13/2026
Royal Charter Properties East3903/21/2026
New York Hospital403/21/2026
Phipps House Services303/21/2026
NYC Department of Housing Preservation and Development103/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Municipal Expediting3803/21/2026
A1 Expediting Service603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Safway AtlanticScaffold2407/08/2026
Riehm PlumbingPlumbing707/25/2026
H.M. Hughes CoGeneral Contractor307/08/2026
Cauldwell Wingate CoGeneral Contractor307/08/2026
Empire General ContractingGeneral Contractor307/08/2026
Sirina Fire ProtectionFire Protection207/08/2026
James E FitzgeraldGeneral Contractor207/08/2026
Turner Construction CompanyGeneral Contractor203/22/2026
Current Fire ProtectionFire Protection207/08/2026
Riehm PlumbingFire Protection207/08/2026
Adco ElectricalElectrical203/22/2026
E-J Electric Installation CoGeneral Contractor103/22/2026
Alliance PlumbingPlumbing107/08/2026
Freedom Electl & DataElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Fenagh6942503/20/2026
Alan Margolin & Associates423102/04/2026
Tectonic Engineering Cons106909/28/2023
Delta Testing Labs687307/21/2020
Building Lifecycle
All (203)Filed (24)Permit Issued (38)Signed Off (14)Facade (FISP) (16)Violation (60)Inspection (15)Objection (6)Special Inspection (30)
08/03/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
07/30/2026
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
07/24/2026
Permit issued — Plumbing
M01341204-I1-PL
07/15/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
06/25/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
06/25/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
06/17/2026
Permit issued — Sprinklers
M01362986-S1-EW-SP
05/26/2026
Permit issued — General Construction
M01362986-I1-GC
04/02/2026
Permit issued — Sprinklers
M01283295-S2-PL
03/23/2026
Objection raised — Scope
03/20/2026
Filed — Alteration
DHK 18: Modification to interior partitions and finishes to accommodate the On Call Room Renovation in the existing hospital building. No change to use, egress, occupancy.
M01362986-S1
03/20/2026
Filed — Alteration
DHK 18: Modification to interior partitions and finishes to accommodate the On Call Room Renovation in the existing hospital building. No change to use, egress, occupancy.
M01362986-I1
03/19/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
AILANTO DANIEL MINAWI
03/19/2026
Special inspection requirement — Lighting controls
AILANTO DANIEL MINAWI
03/19/2026
Special inspection requirement — Interior lighting power
AILANTO DANIEL MINAWI
03/19/2026
Special inspection requirement — Energy Code Compliance Inspections
AILANTO DANIEL MINAWI
02/20/2026
Special inspection requirement — Final
AILANTO DANIEL MINAWI
02/04/2026
Filed — Alteration
M01341204-I1
02/04/2026
Special inspection requirement — Energy Code Compliance Inspections
Young Suh
02/04/2026
Special inspection requirement — Post-installed Anchors
Young Suh
02/04/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Young Suh
12/12/2025
Objection resolved — Resolved
11/06/2025
Permit issued — Sprinklers
M01283295-S2-EW-SP
11/05/2025
Permit issued — General Construction
M01283295-I1-GC
11/05/2025
Permit issued — Mechanical Systems
M01283295-S1-MS
10/20/2025
Signed off — Alteration
Plumbing and sprinkler modifications in floor 4 Mammography Suite and Locker Room in the DHK Building as per plans filed.
M00347434-I1
10/16/2025
Objection raised — Admin
10/16/2025
Objection raised — Structural
09/30/2025
Filed — Alteration
Remove and replace existing air outlets and supply / return ductwork within the new CT scan room. Replace existing CAV-7-42 with new including hot water reheat piping trip. Run new supply/return chilled water from existing as per plans filed herewith only
M01283295-S1
09/26/2025
Filed — Alteration
Remove and replace existing air outlets and supply / return ductwork within the new CT scan room. Replace existing CAV-7-42 with new including hot water reheat piping trip. Run new supply/return chilled water from existing as per plans filed herewith only
M01283295-S3
09/24/2025
Filed — Alteration
Remove and replace existing air outlets and supply / return ductwork within the new CT scan room. Replace existing CAV-7-42 with new including hot water reheat piping trip. Run new supply/return chilled water from existing as per plans filed herewith only
M01283295-S2
09/22/2025
Filed — Alteration
Remove and replace existing air outlets and supply / return ductwork within the new CT scan room. Replace existing CAV-7-42 with new including hot water reheat piping trip. Run new supply/return chilled water from existing as per plans filed herewith only
M01283295-I1
09/18/2025
Special inspection requirement — Post-installed Anchors
AILANTO DANIEL MINAWI
09/16/2025
Special inspection requirement — Duct leakage testing, insulation and design
AILANTO DANIEL MINAWI
09/16/2025
Special inspection requirement — Maintenance information
AILANTO DANIEL MINAWI
09/16/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
AILANTO DANIEL MINAWI
09/16/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
AILANTO DANIEL MINAWI
09/16/2025
Special inspection requirement — Post-installed Anchors
AILANTO DANIEL MINAWI
09/16/2025
Special inspection requirement — Post-installed Anchors
AILANTO DANIEL MINAWI
09/16/2025
Special inspection requirement — Designated Seismic System
AILANTO DANIEL MINAWI
09/08/2025
Special inspection requirement — Sprinkler Systems
AILANTO DANIEL MINAWI
09/08/2025
Special inspection requirement — Final
AILANTO DANIEL MINAWI
09/08/2025
Special inspection requirement — Final
AILANTO DANIEL MINAWI
09/08/2025
Special inspection requirement — Final
AILANTO DANIEL MINAWI
09/08/2025
Special inspection requirement — Mechanical Systems
AILANTO DANIEL MINAWI
09/08/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
AILANTO DANIEL MINAWI
11/08/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
06/02/2024
Violation issued (FDNY_NOV, closed)
05/19/2024
Violation issued (FDNY_NOV, closed)
05/08/2024
Signed off — Alteration
HVAC MODIFICATIONS TO ACCOMMODATE THE CONVERSION OF ENDOSCOPY SUITES TO ORs IN THE EXISTING HOSPITAL BUILDING.
M00929819-S1
05/06/2024
Signed off — Alteration
HVAC MODIFICATIONS TO ACCOMMODATE THE CONVERSION OF ENDOSCOPY SUITES TO ORs IN THE EXISTING HOSPITAL BUILDING.
M00929819-I1
05/06/2024
Signed off — Alteration
M00929810-I1
05/02/2024
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
02/16/2024
Violation issued (FDNY_NOV, closed)
12/27/2023
Permit issued — Plumbing
M00929819-S1-PL
12/19/2023
Permit issued — General Construction
M00929810-I1-GC
12/19/2023
Permit issued — Mechanical Systems
M00929819-I1-MS
11/18/2023
Violation issued (FDNY_ORDER, closed)
11/18/2023
Violation issued (FDNY_ORDER, closed)
11/18/2023
Violation issued (FDNY_ORDER, closed)
Latest 60 of 203 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offRiehm Plumbing07/24/2026
DOB NOWSprinklersPermit IssuedRiehm Plumbing06/17/2026
DOB NOWGeneral ConstructionPermit IssuedEmpire General Contracting05/26/2026
DOB NOWPlumbingPermit IssuedRiehm Plumbing04/02/2026
DOB NOWSprinklersPermit IssuedSirina Fire Protection11/06/2025
DOB NOWGeneral ConstructionPermit IssuedEmpire General Contracting11/05/2025
DOB NOWMechanical SystemsPermit IssuedEmpire General Contracting11/05/2025
DOB NOWPlumbingSigned-offCardoza Plumbing Wmbe12/27/2023
DOB NOWGeneral ConstructionSigned-offJames E Fitzgerald12/19/2023
DOB NOWMechanical SystemsSigned-offJames E Fitzgerald12/19/2023
DOB NOWSprinklersSigned-offRiehm Plumbing03/22/2023
DOB NOWGeneral ConstructionSigned-offHM Hughes Co03/21/2023
DOB NOWPlumbingSigned-offRiehm Plumbing02/16/2023
DOB NOWPlumbingSigned-offRiehm Plumbing07/14/2022
DOB NOWGeneral ConstructionSigned-offHM Hughes Co05/09/2022
DOB NOWMechanical SystemsSigned-offCauldwell Wingate Co12/01/2021
DOB NOWGeneral ConstructionSigned-offCauldwell Wingate Co12/01/2021
DOB NOWPlumbingSigned-offRiehm Plumbing10/20/2021
DOB NOWSprinklersSigned-offSirina Fire Protection07/07/2021
DOB NOWSprinklersSigned-offCurrent Fire Protection I06/17/2021
DOB NOWSprinklersSigned-offCurrent Fire Protection I06/30/2020
DOB NOWSidewalk ShedSigned-offSafway Atlantic12/17/2019
DOB NOWSupported ScaffoldSigned-offSafway Atlantic12/14/2019
DOB NOWConstruction FenceSigned-offSafway Atlantic12/14/2019
DOB NOWSupported ScaffoldSigned-offSafway Atlantic09/17/2019
DOB NOWSidewalk ShedSigned-offSafway Atlantic09/17/2019
DOB NOWConstruction FenceSigned-offSafway Atlantic09/17/2019
DOB NOWConstruction FenceSigned-offSafway Atlantic12/13/2018
DOB NOWSupported ScaffoldSigned-offSafway Atlantic12/12/2018
DOB NOWSidewalk ShedSigned-offSafway Atlantic12/12/2018
DOB NOWSupported ScaffoldSigned-offSafway Atlantic09/24/2018
DOB NOWSidewalk ShedSigned-offSafway Atlantic09/24/2018
DOB NOWConstruction FenceSigned-offSafway Atlantic09/24/2018
DOB NOWSidewalk ShedSigned-offSafway Atlantic12/26/2017
DOB NOWConstruction FenceSigned-offSafway Atlantic12/22/2017
DOB NOWSupported ScaffoldSigned-offSafway Atlantic12/22/2017
DOB NOWSidewalk ShedSigned-offSafway Atlantic12/14/2017
DOB NOWConstruction FenceSigned-offSafway Atlantic12/08/2017
BISSDISSUEDRael Automatic Sprinkler Co06/12/2024
BISSDISSUEDRael Automatic Sprinkler Co06/08/2023
+ 48 more permits on file
2 projects · most recent 03/20/2026
FiledStatusContractorScope
03/20/2026Permit IssuedRiehm Plumbing—
09/30/2025Permit IssuedSirina Fire Protection4 heads
1 project · most recent 09/30/2025
Water/Sanitary
FiledStatusContractorScope
09/30/2025Permit IssuedRiehm PlumbingWater/Sanitary
25 projects · most recent 07/23/2026
General Wiring
FiledStatusContractorScope
07/23/2026Permit IssuedAllan Briteway ElectricalGeneral Wiring
07/03/2026Permit IssuedJam ElectricalGeneral Wiring
07/03/2026Permit IssuedJam ElectricalGeneral Wiring
07/03/2026Permit IssuedJam ElectricalGeneral Wiring
07/03/2026Permit IssuedJam ElectricalGeneral Wiring
07/01/2026CompleteJam Electrical—
05/26/2026CompleteArcadia Elect'l CoGeneral Wiring
05/06/2025CompleteE-J Electric Installation CoGeneral Wiring
07/26/2024CompleteE-J Electric Installation CoGeneral Wiring
05/13/2024CompleteNead ElectricGeneral Wiring
03/31/2022CompleteLowy & DonnathGeneral Wiring
02/15/2022CompleteLowy & DonnathGeneral Wiring
09/02/2021CompleteHarley Electric CoGeneral Wiring
09/23/2020CancelledLowy & DonnathGeneral Wiring
07/16/2020Permit IssuedDooley Electric CoGeneral Wiring
1 project · most recent 09/30/2025
FiledStatusContractorScope
09/30/2025Permit IssuedRiehm Plumbing2 scope_items
▾Field Inspections (DOB CAP) — 15
DateTypeResultReport
08/03/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
07/30/2026Fail-Final General Construction Non-Directive 14FailView ↗
07/15/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
06/25/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
06/25/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
11/08/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
05/02/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
09/15/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
08/28/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
02/27/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
02/24/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
02/10/2022Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
02/04/2022Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
02/04/2022Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
10/25/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 38
DateRequirementInspectorRole
03/19/2026Fire-Resistant Penetrations and JointsAILANTO DANIEL MINAWIspecial
03/19/2026Lighting controlsAILANTO DANIEL MINAWIenergy_progress
03/19/2026Interior lighting powerAILANTO DANIEL MINAWIenergy_progress
03/19/2026Energy Code Compliance InspectionsAILANTO DANIEL MINAWIprogress
02/20/2026FinalAILANTO DANIEL MINAWIprogress
02/04/2026Energy Code Compliance InspectionsYoung Suhprogress
02/04/2026Post-installed AnchorsYoung Suhspecial
02/04/2026HVAC-R and service water piping design and insulationYoung Suhenergy_progress
09/18/2025Post-installed AnchorsAILANTO DANIEL MINAWIspecial
09/16/2025Duct leakage testing, insulation and designAILANTO DANIEL MINAWIenergy_progress
09/16/2025Maintenance informationAILANTO DANIEL MINAWIenergy_progress
09/16/2025Fire-Resistant Penetrations and JointsAILANTO DANIEL MINAWIspecial
09/16/2025HVAC-R and service water piping design and insulationAILANTO DANIEL MINAWIenergy_progress
09/16/2025Post-installed AnchorsAILANTO DANIEL MINAWIspecial
09/16/2025Post-installed AnchorsAILANTO DANIEL MINAWIspecial
09/16/2025Designated Seismic SystemAILANTO DANIEL MINAWIspecial
09/08/2025Sprinkler SystemsAILANTO DANIEL MINAWIspecial
09/08/2025FinalAILANTO DANIEL MINAWIprogress
09/08/2025FinalAILANTO DANIEL MINAWIprogress
09/08/2025FinalAILANTO DANIEL MINAWIprogress
09/08/2025Mechanical SystemsAILANTO DANIEL MINAWIspecial
09/08/2025Fire-Resistant Penetrations and JointsAILANTO DANIEL MINAWIspecial
09/06/2023FinalGEORGE GHEBRYALprogress
09/06/2023Mechanical SystemsGEORGE GHEBRYALspecial
10/26/2022FinalGEORGE GHEBRYALprogress
Latest 25 of 38.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
NewYork-PresbyterianMedical / HealthcareEntire building
Project M01362986 Alteration · Permit Entire · 03/20/2026
Project M01341204 Alteration · Permit Entire · 02/04/2026
Project M01283295 Alteration · Permit Entire · 09/22/2025
Project M00929819 Alteration · LOC Issued · 09/28/2023
Project M00929810 Alteration · LOC Issued · 09/27/2023
Project M08022405 Alteration · LOC Issued · 11/04/2022
Project M08022382 Alteration · LOC Issued · 11/03/2022
Project M00713993 Alteration · LOC Issued · 04/11/2022
Project M00714048 Alteration · LOC Issued · 04/11/2022
Project M00605501 Alteration · LOC Issued · 10/13/2021
Project M00605513 Alteration · LOC Issued · 10/06/2021
Project M00357210 Alteration · LOC Issued · 06/24/2020
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 2,063 on file (BIS + DOB NOW)
▸Plans & Drawings25
▸DOB NOWPlans/Sketch21
09/06/2026M00003503-I1Request digital key ↗
09/06/2026M00003499-I1Request digital key ↗
09/06/2026M00007340-I1Request digital key ↗
Showing 3 of 21 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler3
09/04/2026M00347434-I1Request digital key ↗
09/04/2026M00357210-I1Request digital key ↗
08/15/2026M00357210-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing1
09/04/2026M00347434-I1Request digital key ↗
▸Applications & Permits442
▸BISPLAN / WORK APPROVAL APPLICATION288
05/04/2021140172079Open ↗
08/25/2020121325137Open ↗
07/24/2020140911280Open ↗
Showing 3 of 288 on file for this type
▸BISWORK PERMIT APPLICATION149
07/29/2021140901923Open ↗
07/06/2021140902012Open ↗
07/28/2020140911280Open ↗
Showing 3 of 149 on file for this type
▸BISPLACE OF ASSEMBLY5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸Zoning, Tax Lot & Property Records4
▸BISZONING RESOLUTION DETERMINATION4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸Seals & Professional Certifications331
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION155
05/01/2020140673359Open ↗
04/06/2020140660988Open ↗
04/06/2020140660988Open ↗
Showing 3 of 155 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT36
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 36 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST31
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 31 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature24
09/06/2026M00003503-I1Open ↗
09/06/2026M00003499-I1Open ↗
09/06/2026M00007340-I1Open ↗
Showing 3 of 24 on file for this type
▸BISAPPLICANT OWNER SIGNATURE22
07/06/2020140911280Open ↗
05/19/2020140902012Open ↗
05/14/2020140902290Open ↗
Showing 3 of 22 on file for this type
▸DOB NOWProgress Inspector Seal & Signature22
09/02/2026M00929819-I1Open ↗
09/01/2026M01283295-I1Open ↗
08/30/2026M01283295-S3Open ↗
Showing 3 of 22 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature15
09/02/2026M00929819-I1Open ↗
08/30/2026M01283295-S3Open ↗
08/30/2026M01283295-S3Open ↗
Showing 3 of 15 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸Trade Schedules & Equipment120
▸BISSELF-CERT PLUMBING NOTICE36
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 36 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE27
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 27 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA24
08/14/2020123299055Open ↗
04/10/2020122275796Open ↗
Showing 2 of 24 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT13
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 13 on file for this type
▸BISSCHEDULE B - PLUMBING12
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 12 on file for this type
▸BISEQUIPMENT USE PERMITS8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸Safety & Tenant Protection8
▸BISSTREET TREE SUPPORTING DOCUMENT5
08/04/2021140172079Open ↗
Showing 1 of 5 on file for this type
▸BISSTREET TREE CHECKLIST3
08/04/2021140172079Open ↗
Showing 1 of 3 on file for this type
▸Environmental & Asbestos68
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE TO PROCEED16
07/06/2020140911280Open ↗
06/23/2020140902290Open ↗
Showing 2 of 16 on file for this type
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE OF SATISFACTION15
01/07/2025140875275Open ↗
10/31/2024140901923Open ↗
01/10/2023140911280Open ↗
Showing 3 of 15 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸DOB NOWOER: Notice to Proceed6
09/06/2026M00003503-I1Open ↗
09/06/2026M00003499-I1Open ↗
09/06/2026M00007340-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWOER: Notice of Satisfaction4
09/06/2026M00003503-I1Open ↗
09/06/2026M00003499-I1Open ↗
09/06/2026M00007340-I1Open ↗
Showing 3 of 4 on file for this type
▸BISASBESTOS-EXEMPTION (ASB4)3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸Energy Compliance69
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY26
07/02/2021140902012Open ↗
07/02/2021140901923Open ↗
07/24/2020140911280Open ↗
Showing 3 of 26 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS21
05/01/2020140673359Open ↗
Showing 1 of 21 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS7
07/08/2020140886361Open ↗
05/01/2020140673359Open ↗
03/30/2020140658893Open ↗
Showing 3 of 7 on file for this type
▸BISTR8: Energy Code Progress Inspections4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISINTERIOR LIGHTING POWER3
01/07/2025140875275Open ↗
10/31/2024140901923Open ↗
01/10/2023140911280Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)3
10/31/2024140902012Open ↗
10/31/2024140901923Open ↗
01/10/2023140911280Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS3
01/07/2025140875275Open ↗
10/31/2024140902012Open ↗
10/31/2024140901923Open ↗
▸DOB NOWEN2: As Built Energy Analysis.2
08/13/2026M00605513-I1Open ↗
08/13/2026M00713993-I1Open ↗
▸Inspections & Test Reports110
▸BISTECHNICAL REPORT: RESPONSIBILITY74
07/29/2021140901923Open ↗
07/02/2021140902012Open ↗
07/24/2020140911280Open ↗
Showing 3 of 74 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX17
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 17 on file for this type
▸BISINSPECTION REPORT - SUPPORTING DOCUMENTATION9
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 9 on file for this type
▸BISFIRE-RESISTIVE RATED CONSTRUCTION4
01/07/2025140875275Open ↗
10/31/2024140902012Open ↗
10/31/2024140901923Open ↗
Showing 3 of 4 on file for this type
▸BISHYDRAULIC FLOW CALCULATIONS3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISTECHNICAL REPORT: PILE DRIVING3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸Approvals, Objections & Sign-offs203
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST90
04/14/2025140875275Open ↗
01/08/2025140902012Open ↗
01/08/2025140901923Open ↗
Showing 3 of 90 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION42
04/10/2020123299055Open ↗
Showing 1 of 42 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter24
09/06/2026M00003503-I1Open ↗
09/06/2026M00003499-I1Open ↗
09/06/2026M00007340-I1Open ↗
Showing 3 of 24 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE14
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 14 on file for this type
▸BISADMINISTRATIVE OBJECTIONS14
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 14 on file for this type
▸BISCONSTRUCTION CODE DETERMINATION13
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 13 on file for this type
▸BISFINAL6
01/07/2025140875275Open ↗
10/31/2024140902012Open ↗
10/31/2024140901923Open ↗
Showing 3 of 6 on file for this type
▸Cost, Insurance & Ownership118
▸BISCOST AFFIDAVIT102
11/23/2021140170231Open ↗
12/17/2020140170231Open ↗
11/05/2020123522170Open ↗
Showing 3 of 102 on file for this type
▸BISPROJECT-SPECIFIC GL INSURANCE9
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 9 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW37
01/07/2025140875275Open ↗
10/31/2024140902012Open ↗
10/31/2024140901923Open ↗
Showing 3 of 7 on file for this type
▸Filing & Intake Forms371
▸BISADDITIONAL INFORMATION174
08/04/2021140172079Open ↗
06/30/2021140172079Open ↗
06/30/2021140172079Open ↗
Showing 3 of 174 on file for this type
▸BISBOROUGH INTAKE FORM111
05/01/2020140673359Open ↗
04/10/2020121325137Open ↗
04/06/2020140170231Open ↗
Showing 3 of 111 on file for this type
▸BISEFILING COVER SHEET53
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 53 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET33
07/06/2020140911280Open ↗
05/19/2020140902012Open ↗
05/14/2020140902290Open ↗
Showing 3 of 33 on file for this type
▸Other Documents79
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION48
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 48 on file for this type
▸BISSupporting Document: Fee Exempt16
07/06/2020140911280Open ↗
05/19/2020140902012Open ↗
05/13/2020140901923Open ↗
Showing 3 of 16 on file for this type
▸BISBPP - SUPPORTING DOCUMENTATION5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION4
11/18/2021140208665Open ↗
11/18/2021140262445Open ↗
11/18/2021140208674Open ↗
Showing 3 of 4 on file for this type
▸BISSupporting Document: Fee Deferment3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISFIRE SUPP ANSUL APPROVL: FD-FSS3
11/18/2021121325137Open ↗