General warehouse
1285 OAK POINT AVENUE
BRONX · Hunts Point · BIN 2006826
💬 Discuss this project
1957Year Built
1Stories
E1Building Class
M1-2Zoning
24,500 sfGross Floor Area
1Units
3 Open Violations 1 unresolved · 2 paperwork only ▸
General warehouse · Owner of record: OAK POINT HUB LLC · 20,000 sf lot · 1.23 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbing
Roof2p · 1 filing · 20 docs
Floor 71p · 1 filing · 20 docs
Floor 6
Floor 5
Floor 4
Floor 3
Floor 2
Floor 1
Mezzanine5p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
TURNER MANAGEMENT CONSULTING1607/08/2026
ACE GROUP NY607/08/2026
NY SKYHIGH CONSTRUCTION404/09/2026
OWNER OF 1285 OAK POINT A103/22/2026
MARJERRY REALTY503/21/2026
NY COMMON PANTRY703/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
10/19/2022$9.0M—MARJERRY REALTY CORP. → OAK POINT HUB LLC$367/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
FAZAL BANGASH108/27/2025
MOHAMMAD HAQUE108/15/2025
ICOR ASSOCIATES904/21/2023
METHOD DESIGN ARCHITECTURE + URBANI212/07/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
PROJECT TACTICAL SOLUTIONS1103/21/2026
GREEN STUDIO203/21/2026
NY SKYHIGH CONSTRUCTION203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ACE GROUP NY CORPGeneral Contractor407/08/2026
ARROW MECHANICAL CORPGeneral Contractor303/21/2026
FLINT MECHANICAL CORPFire Protection107/08/2026
ETRICITY ELECTRICAL CO INElectrical103/22/2026
NYC HIGH SKILLED BUILDERGeneral Contractor107/08/2026
NY SKYHIGH CONSTRUCTIONGeneral Contractor104/09/2026
ETHOS PLUMBING CORPPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BANGASH ASSOCIATES INC8488108/27/2025
H & O ENGINEERING, DPC5595704/21/2023
METHOD DESIGN ARCHITECTUR5713212/07/2022
Building Lifecycle
All (57)Filed (13)Permit Issued (7)Signed Off (2)Violation (5)Inspection (7)Special Inspection (23)
08/29/2025
Permit issued — General Construction
X01278237-I1-GC
08/27/2025
Filed — Alteration
X01278237-I1
08/15/2025
Filed — Alteration
X01272087-I1
08/15/2025
Permit issued — Sidewalk Shed
X01272087-I1-SF
08/15/2025
Permit issued — Sidewalk Shed
X01272087-I1-SH
04/24/2023
Special inspection requirement — Final
SANTIAGO HELMAN
04/24/2023
Special inspection requirement — Mechanical Systems
SANTIAGO HELMAN
04/24/2023
Special inspection requirement — Energy Code Compliance Inspections
SANTIAGO HELMAN
04/24/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
SANTIAGO HELMAN
04/21/2023
Filed — Alteration
MECHANICAL WORK IN CONJUNCTION WITH INTERIOR RENOVATION OF WAREHOUSE ON THE 1ST FLOOR AND MEZZ AS PER PLANS FILED HEREWITH AND TO OBTAIN EUP FOR EXISTING ROOFTOP UNITS PREVIOUSLY FILED UNDER DOB#220168556. NO CHANGE IN USE, EGRESS, OR OCCUPANCY
X00653261-P2
04/17/2023
Signed off — Alteration
PLUMBING WORK IN CONJUNCTION WITH INTERIOR RENOVATION OF WAREHOUSE ON THE 1ST FLOOR AND MEZZ AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
X00653262-I1
04/17/2023
Signed off — Alteration
SPRINKLER WORK IN CONJUNCTION WITH INTERIOR RENOVATION OF WAREHOUSE ON THE 1ST FLOOR AND MEZZ AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
X00653264-I1
01/05/2023
Inspection — Certified Sprinkler-Dry Pipe Valve (SP)-Dry Pipe Valve Test
Certified
View inspection ↗
12/28/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/23/2022
Filed — Alteration
PLUMBING WORK IN CONJUNCTION WITH INTERIOR RENOVATION OF WAREHOUSE ON THE 1ST FLOOR AND MEZZ AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
X00653262-P3
12/22/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/15/2022
Filed — Alteration
PLUMBING WORK IN CONJUNCTION WITH INTERIOR RENOVATION OF WAREHOUSE ON THE 1ST FLOOR AND MEZZ AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
X00653262-P2
12/14/2022
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
12/07/2022
Filed — Alteration
MECHANICAL WORK IN CONJUNCTION WITH INTERIOR RENOVATION OF WAREHOUSE ON THE 1ST FLOOR AND MEZZ AS PER PLANS FILED HEREWITH AND TO OBTAIN EUP FOR EXISTING ROOFTOP UNITS PREVIOUSLY FILED UNDER DOB#220168556. NO CHANGE IN USE, EGRESS, OR OCCUPANCY
X00653261-P1
12/07/2022
Filed — Alteration
SPRINKLER WORK IN CONJUNCTION WITH INTERIOR RENOVATION OF WAREHOUSE ON THE 1ST FLOOR AND MEZZ AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
X00653264-P1
12/07/2022
Filed — Alteration
PLUMBING WORK IN CONJUNCTION WITH INTERIOR RENOVATION OF WAREHOUSE ON THE 1ST FLOOR AND MEZZ AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
X00653262-P1
12/07/2022
Filed — Alteration
INTERIOR RENOVATION OF WAREHOUSE ON THE 1ST FLOOR AND MEZZ AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
X00653260-P1
12/07/2022
Special inspection requirement — Interior lighting power
Demetrios Comodromos
12/07/2022
Special inspection requirement — Sprinkler Systems
SANTIAGO HELMAN
12/07/2022
Special inspection requirement — Concrete - Cast-In-Place
SANTIAGO HELMAN
12/07/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Demetrios Comodromos
12/07/2022
Special inspection requirement — Energy Code Compliance Inspections
Demetrios Comodromos
12/07/2022
Special inspection requirement — Final
Demetrios Comodromos
12/07/2022
Special inspection requirement — Fire-Resistance Rated Construction
Demetrios Comodromos
12/07/2022
Special inspection requirement — Lighting controls
Demetrios Comodromos
11/18/2022
Special inspection requirement — Mechanical Systems
SANTIAGO HELMAN
11/18/2022
Special inspection requirement — Energy Code Compliance Inspections
SANTIAGO HELMAN
11/18/2022
Special inspection requirement — Final
SANTIAGO HELMAN
11/18/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
SANTIAGO HELMAN
11/18/2022
Special inspection requirement — Concrete - Cast-In-Place
SANTIAGO HELMAN
11/18/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Demetrios Comodromos
11/18/2022
Special inspection requirement — Energy Code Compliance Inspections
Demetrios Comodromos
11/18/2022
Special inspection requirement — Final
Demetrios Comodromos
11/18/2022
Special inspection requirement — Fire-Resistance Rated Construction
Demetrios Comodromos
11/18/2022
Special inspection requirement — Lighting controls
Demetrios Comodromos
11/18/2022
Special inspection requirement — Interior lighting power
Demetrios Comodromos
11/07/2022
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
11/02/2022
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
08/12/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
07/19/2022
Permit issued — Mechanical Systems
X00653261-I1-MS
07/01/2022
Permit issued — Sprinklers
X00653264-I1-EW-SP
06/16/2022
Permit issued — Plumbing
X00653262-I1-PL
05/18/2022
Filed — Alteration
MECHANICAL WORK IN CONJUNCTION WITH INTERIOR RENOVATION OF WAREHOUSE ON THE 1ST FLOOR AND MEZZ AS PER PLANS FILED HEREWITH AND TO OBTAIN EUP FOR EXISTING ROOFTOP UNITS PREVIOUSLY FILED UNDER DOB#220168556. NO CHANGE IN USE, EGRESS, OR OCCUPANCY
X00653261-I1
05/12/2022
Filed — Alteration
PLUMBING WORK IN CONJUNCTION WITH INTERIOR RENOVATION OF WAREHOUSE ON THE 1ST FLOOR AND MEZZ AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
X00653262-I1
05/12/2022
Filed — Alteration
SPRINKLER WORK IN CONJUNCTION WITH INTERIOR RENOVATION OF WAREHOUSE ON THE 1ST FLOOR AND MEZZ AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
X00653264-I1
04/08/2022
Permit issued — General Construction
X00653260-I1-GC
02/05/2022
Filed — Alteration
INTERIOR RENOVATION OF WAREHOUSE ON THE 1ST FLOOR AND MEZZ AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
X00653260-I1
06/11/1992
Violation issued (ECB, closed)
Construction
02/06/1991
Violation issued (DOB, closed)
VP*-VIOLATION UNSERVED ECB- DISMISSED
02/06/1991
Violation issued (ECB, open)
Construction
03/19/1990
Violation issued (ECB, open)
Construction
09/13/1989
Violation issued (DOB, open)
VP-VIOLATION UNSERVED ECB-ACTIVE
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedNY SKYHIGH CONSTRUCTION08/29/2025
DOB NOWSidewalk ShedPermit IssuedACE GROUP NY CORP08/15/2025
DOB NOWSidewalk ShedPermit IssuedACE GROUP NY CORP08/15/2025
DOB NOWMechanical SystemsSigned-offARROW MECHANICAL CORP07/19/2022
DOB NOWSprinklersSigned-offBLETSAS P&H CORP07/01/2022
DOB NOWPlumbingSigned-offETHOS PLUMBING CORP06/16/2022
DOB NOWGeneral ConstructionSigned-offNYC HIGH SKILLED BUILDER04/08/2022
BISMHISSUEDCOTTAM HEATING & AIR CONDIT.04/30/2012
BISOTISSUEDJOHN COFFEY & SON INC05/13/1999
BISMHISSUEDPORT MORRIS TILE & MARBLE CORP01/31/1997
BISMHISSUEDNELSON AIR DEVICE03/22/1990
1 project · most recent 04/21/2023
Heating and Air Conditioning Systems Heating Systems Refrigeration Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
04/21/2023Signed-offARROW MECHANICAL CORPHeating and Air Conditioning Systems, Heating Systems, Refrigeration Systems, Ventilation Systems
Heat / Cool
Trane YSC048E3EHA1A0 4 tons · Condensing Unit ×1
YSC060E3RHA1N 5 tons · Condensing Unit ×1
YSC090F3RHAGB 8 tons · Condensing Unit ×1
YSC120F3RHA0B 10 tons · Chiller ×1
Heating
Reznor UBX-100 87,150 BTU · Unit Heater ×18
UBX-75 615,000 BTU · Unit Heater ×4
N/A N/A 13,652 BTU · Unit Heater ×2
Ventilation
N/A N/A 92,300 CFM · Exhaust Fan ×18
Refrigeration
Turbo Air TS055XR404A3A (EFFICIENCY UNITS MEASURED IN AWEF ONLY) 14,086 BTU · Condensing Unit ×2
TS040MR404A3-T (EFFICIENCY UNITS MEASURED IN AWEF ONLY) 27,846 BTU · Condensing Unit ×1
TS050MR404A3A-T (EFFICIENCY UNITS MEASURED IN AWEF ONLY) 34,325 BTU · Condensing Unit ×1
1 project · most recent 05/18/2022
General Wiring
FiledStatusContractorScope
05/18/2022CompleteETRICITY ELECTRICAL CO INGeneral Wiring
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
01/05/2023Certified Sprinkler-Dry Pipe Valve (SP)-Dry Pipe Valve TestCertifiedView ↗
12/28/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/22/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/14/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
11/07/2022Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
11/02/2022Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
08/12/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 23
DateRequirementInspectorRole
04/24/2023FinalSANTIAGO HELMANprogress
04/24/2023Mechanical SystemsSANTIAGO HELMANspecial
04/24/2023Energy Code Compliance InspectionsSANTIAGO HELMANprogress
04/24/2023HVAC-R and service water piping design and insulationSANTIAGO HELMANenergy_progress
12/07/2022Interior lighting powerDemetrios Comodromosenergy_progress
12/07/2022Sprinkler SystemsSANTIAGO HELMANspecial
12/07/2022Concrete - Cast-In-PlaceSANTIAGO HELMANspecial
12/07/2022Fire-Resistant Penetrations and JointsDemetrios Comodromosspecial
12/07/2022Energy Code Compliance InspectionsDemetrios Comodromosprogress
12/07/2022FinalDemetrios Comodromosprogress
12/07/2022Fire-Resistance Rated ConstructionDemetrios Comodromosprogress
12/07/2022Lighting controlsDemetrios Comodromosenergy_progress
11/18/2022Mechanical SystemsSANTIAGO HELMANspecial
11/18/2022Energy Code Compliance InspectionsSANTIAGO HELMANprogress
11/18/2022FinalSANTIAGO HELMANprogress
11/18/2022HVAC-R and service water piping design and insulationSANTIAGO HELMANenergy_progress
11/18/2022Concrete - Cast-In-PlaceSANTIAGO HELMANspecial
11/18/2022Fire-Resistant Penetrations and JointsDemetrios Comodromosspecial
11/18/2022Energy Code Compliance InspectionsDemetrios Comodromosprogress
11/18/2022FinalDemetrios Comodromosprogress
11/18/2022Fire-Resistance Rated ConstructionDemetrios Comodromosprogress
11/18/2022Lighting controlsDemetrios Comodromosenergy_progress
11/18/2022Interior lighting powerDemetrios Comodromosenergy_progress
▾Documents — 93 on file (BIS + DOB NOW)
▸Plans & Drawings13
▸DOB NOWPlans/Sketch13
08/24/2026X00653260-P1Request digital key ↗
08/24/2026X00653260-I1Request digital key ↗
08/24/2026X00653264-P1Request digital key ↗
Showing 3 of 13 on file for this type
▸Applications & Permits5
▸BISPLAN / WORK APPROVAL APPLICATION4
04/04/2012220168556Open ↗
04/04/2012220168547Open ↗
02/09/2012220168547Open ↗
Showing 3 of 4 on file for this type
▸BISWORK PERMIT APPLICATION1
05/04/2012220168556Open ↗
▸Seals & Professional Certifications39
▸DOB NOWProgress Inspector Seal & Signature16
08/30/2026X00653260-I1Open ↗
08/30/2026X00653260-I1Open ↗
08/30/2026X00653260-I1Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature13
08/24/2026X00653262-I1Open ↗
08/24/2026X00653262-P3Open ↗
08/24/2026X00653262-P2Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature7
08/30/2026X00653260-I1Open ↗
08/30/2026X00653260-I1Open ↗
08/28/2026X00653261-P1Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION3
05/04/2012220168556Open ↗
02/09/2012220168547Open ↗
02/09/2012220168556Open ↗
▸Environmental & Asbestos13
▸DOB NOWDEP ACP-5: Asbestos Assessment Report12
08/24/2026X00653262-P2Open ↗
08/24/2026X00653262-P1Open ↗
08/24/2026X00653262-I1Open ↗
Showing 3 of 12 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
02/09/2012220168556Open ↗
▸Energy Compliance4
▸BISTECHNICAL REPORT: ENERGY2
02/09/2012220168547Open ↗
02/09/2012220168556Open ↗
▸DOB NOWEN2: As Built Energy Analysis2
08/13/2026X00653260-I1Open ↗
08/13/2026X00653261-I1Open ↗
▸Approvals, Objections & Sign-offs13
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter11
08/24/2026X00653262-P3Open ↗
08/24/2026X00653262-P2Open ↗
08/24/2026X00653262-P1Open ↗
Showing 3 of 11 on file for this type
▸BISADMINISTRATIVE OBJECTIONS2
02/09/2012220168547Open ↗
02/09/2012220168556Open ↗
▸Cost, Insurance & Ownership4
▸BISCOST AFFIDAVIT4
04/04/2012220168556Open ↗
04/04/2012220168547Open ↗
02/09/2012220168547Open ↗
Showing 3 of 4 on file for this type
▸Filing & Intake Forms2
▸BISEFILING COVER SHEET2
02/09/2012220168547Open ↗
02/09/2012220168556Open ↗