💬 Discuss this project
1930Year Built
5Stories
W5Building Class
R7-2Zoning
400,160 sfGross Floor Area
1Units
LL97 Covered6 Active Violations 1 unresolved · 5 paperwork only 11 likely answered 3 old, status unconfirmed ▸
City university · 477,375 sf lot · 0.84 FAR built · Flood zone X
Locations of Work
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Floor 1The City College of New York1 filing · 9 docs
MezzanineThe City College of New York1 filing · 9 docs
CellarThe City College of New York1 filing · 9 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYS Dormitory Authority1103/21/2026
CUNY510/06/2026
City403/21/2026
Dasny303/21/2026
NYC Department of Housing Preservation and Development103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
LERA Consulting Structural Engineering107/28/2026
Legacy Engineers302/13/2026
Martin H. Kapell112/15/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Outsource Consultants803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Fortini JohnElectrical103/21/2026
Zena ElectricElectrical103/21/2026
All-Star Electrical ServicesElectrical103/21/2026
Pro ElectricElectrical103/21/2026
Livia MichaelElectrical103/21/2026
Premier Electrical ContractorsElectrical103/21/2026
Tru-Val ElectricElectrical103/21/2026
Building Lifecycle
All (100)Filed (5)Violation (60)Objection (10)Special Inspection (25)
07/28/2026
Filed — Alteration CO
This Project was accepted into the HUB following consultation meeting with Damian Titus on 09/12/25. Herewith Filing Foundation work as outlined in plans and in connection with interior renovations at CCNY - Aaron Davis Hall.
M01322147-S5
07/10/2026
Special inspection requirement — HVAC-R and service water heating system controls
07/10/2026
Special inspection requirement — HVAC-R and service water heating equipment
07/10/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
07/08/2026
Objection resolved — Open
07/06/2026
Objection resolved — Open
07/06/2026
Objection resolved — Open
07/06/2026
Objection resolved — Open
02/25/2026
Objection raised — Other
02/25/2026
Objection raised — Other
02/25/2026
Objection raised — Other
02/16/2026
Objection raised — Other
02/13/2026
Filed — Alteration CO
This Project was accepted into the HUB following consultation meeting with Damian Titus on 09/12/25. Herewith Filing Foundation work as outlined in plans and in connection with interior renovations at CCNY - Aaron Davis Hall.
M01322147-S3
02/13/2026
Filed — Alteration CO
This Project was accepted into the HUB following consultation meeting with Damian Titus on 09/12/25. Herewith Filing Foundation work as outlined in plans and in connection with interior renovations at CCNY - Aaron Davis Hall.
M01322147-S2
02/13/2026
Filed — Alteration CO
This Project was accepted into the HUB following consultation meeting with Damian Titus on 09/12/25. Herewith Filing Foundation work as outlined in plans and in connection with interior renovations at CCNY - Aaron Davis Hall.
M01322147-S1
01/14/2026
Objection resolved — Addressed
12/26/2025
Objection raised — Other
12/15/2025
Filed — Alteration CO
This Project was accepted into the HUB following consultation meeting with Damian Titus on 09/12/25. Herewith Filing Foundation work as outlined in plans and in connection with interior renovations at CCNY - Aaron Davis Hall.
M01322147-I1
12/12/2025
Special inspection requirement — Preliminary
12/12/2025
Special inspection requirement — Energy Code Compliance Inspections
12/12/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
12/12/2025
Special inspection requirement — Fire-Resistance Rated Construction
12/04/2025
Special inspection requirement — Heating Systems
12/04/2025
Special inspection requirement — High Temperature Hot Water Piping (Welding)
12/04/2025
Special inspection requirement — High-Pressure Steam Piping (Welding)
12/04/2025
Special inspection requirement — Seismic Resistance of Plumbing, Mechanical, Fuel Gas, and Electrical Components
12/04/2025
Special inspection requirement — Smoke Control Systems Testing
12/04/2025
Special inspection requirement — Chimneys and vents
12/04/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
12/04/2025
Special inspection requirement — Seismic Isolation Systems
12/04/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
12/04/2025
Special inspection requirement — Seismic Resistance of Plumbing, Mechanical, Fuel Gas, and Electrical Components
12/04/2025
Special inspection requirement — Energy Code Compliance Inspections
12/04/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
12/04/2025
Special inspection requirement — Energy Code Compliance Inspections
12/04/2025
Special inspection requirement — Fire-Resistance Rated Construction
12/03/2025
Special inspection requirement — Standpipe Systems
12/03/2025
Special inspection requirement — Sprinkler Systems
12/03/2025
Special inspection requirement — Final
12/03/2025
Special inspection requirement — Mechanical Systems
12/17/2021
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/09/2019
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/09/2019
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/09/2019
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
09/06/2019
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
04/05/2019
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
04/05/2019
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
01/26/2018
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
09/15/2017
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
09/15/2017
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
01/03/2017
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
12/01/2016
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
12/01/2016
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/14/2016
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/01/2016
Violation issued (DOB, closed)
V-DOB VIOLATION - ACTIVE
06/10/2015
Violation issued (DOB, closed)
V-DOB VIOLATION - ACTIVE
06/10/2015
Violation issued (DOB, closed)
V-DOB VIOLATION - ACTIVE
10/31/2014
Violation issued (DOB, closed)
V-DOB VIOLATION - ACTIVE
10/31/2014
Violation issued (DOB, closed)
V-DOB VIOLATION - ACTIVE
05/30/2014
Violation issued (DOB, closed)
V-DOB VIOLATION - ACTIVE
Latest 60 of 100 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
BISOTISSUEDSBLM Architects03/01/2018
BISMHISSUEDVolmar Construction08/24/2017
BISOTISSUEDVolmar Construction08/24/2017
BISOTISSUEDVolmar Construction08/24/2017
BISMHISSUEDDynamic US04/02/2014
BISMHISSUEDR.maric Piping06/25/2009
BISPLISSUEDFresh Meadow Mechanical Plumbing01/13/2006
BISMHISSUEDFresh Meadow Mechanical01/13/2006
BISPLISSUEDFresh Meadow Mechanical Plumbing12/07/2004
BISMHISSUEDFresh Meadow Mechanical12/07/2004
BISEQISSUEDYork Scaffold Equipment02/15/2001
BISEQISSUEDColgate Scaffolding12/29/1999
BISEQISSUEDColgate Scaffolding01/04/1999
BISEQISSUEDColgate Scaffolding02/20/1998
1 project · most recent 07/28/2026
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
07/28/2026——Heating and Air Conditioning Systems
Heat / Cool
Cooper & Hunter CHV-24WTU 776 CFM · Split System ×2
CH-24LCUO 2,345 CFM · Condensing Unit ×1
CH-36LCDTUI 1,839 CFM · Split System ×1
CH-36LCU/O 2,530 CFM · Condensing Unit ×1
CH-48MES-230VO 2,235 CFM · Condensing Unit ×1
CH-M24DTU 776 CFM · Split System ×1
CHV-28WTU 1,839 CFM · Split System ×1
CHV6-072URB 2,530 CFM · Vrf Outdoor ×1
Mitsubishi Electric COOPER & HUNTER 719 CFM · Split System ×2
1 project · most recent 07/28/2026
Sprinkler System
FiledStatusContractorScope
07/28/2026——Sprinkler System
1 project · most recent 07/28/2026
Storm Water/Sanitary
FiledStatusContractorScope
07/28/2026——Storm, Water/Sanitary
2 projects · most recent 10/15/2019
FiledStatusContractorScope
10/15/2019Permit IssuedAll-Star Electrical Services—
05/02/2018CompleteZena Electric—
1 project · most recent 07/28/2026
Steel Concrete Masonry
FiledStatusContractorScope
07/28/2026——Steel, Concrete, Masonry
▾Special Inspection Requirements (DOB NOW) — 25
DateRequirementInspectorRole
07/10/2026HVAC-R and service water heating system controls—energy_progress
07/10/2026HVAC-R and service water heating equipment—energy_progress
07/10/2026HVAC-R and service water piping design and insulation—energy_progress
12/12/2025Preliminary—progress
12/12/2025Energy Code Compliance Inspections—progress
12/12/2025Fire-Resistant Penetrations and Joints—special
12/12/2025Fire-Resistance Rated Construction—progress
12/04/2025Heating Systems—special
12/04/2025High Temperature Hot Water Piping (Welding)—special
12/04/2025High-Pressure Steam Piping (Welding)—special
12/04/2025Seismic Resistance of Plumbing, Mechanical, Fuel Gas, and Electrical Components—special
12/04/2025Smoke Control Systems Testing—special
12/04/2025Chimneys and vents—special
12/04/2025Fire-Resistant Penetrations and Joints—special
12/04/2025Seismic Isolation Systems—special
12/04/2025Fire-Resistant Penetrations and Joints—special
12/04/2025Seismic Resistance of Plumbing, Mechanical, Fuel Gas, and Electrical Components—special
12/04/2025Energy Code Compliance Inspections—progress
12/04/2025Fire-Resistant Penetrations and Joints—special
12/04/2025Energy Code Compliance Inspections—progress
12/04/2025Fire-Resistance Rated Construction—progress
12/03/2025Standpipe Systems—special
12/03/2025Sprinkler Systems—special
12/03/2025Final—progress
12/03/2025Mechanical Systems—special
▾Tenants in the building
TenantSpaceFloorsRenovation projects
The City College of New YorkEducationCellar, Floor 1, Mezzanine
Project M01322147 Alteration CO · Plan Examiner Review · 12/15/2025
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 151 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/20/2026M01322147-S2Request digital key ↗
08/20/2026M01322147-S5Request digital key ↗
08/20/2026M01322147-S4Request digital key ↗
Showing 3 of 5 on file for this type
▸Applications & Permits34
▸BISPLAN / WORK APPROVAL APPLICATION27
02/15/2017123019081Open ↗
02/15/2017123019081Open ↗
02/15/2017123019081Open ↗
Showing 3 of 27 on file for this type
▸BISWORK PERMIT APPLICATION7
03/02/2018122810440Open ↗
08/25/2017123019081Open ↗
08/25/2017123019081Open ↗
Showing 3 of 7 on file for this type
▸Zoning, Tax Lot & Property Records1
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026M01322147-I1Open ↗
▸Seals & Professional Certifications48
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION33
08/24/2017123019081Open ↗
08/24/2017123019081Open ↗
03/02/2017123019081Open ↗
Showing 3 of 33 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM5
02/13/2014121464021Open ↗
02/13/2014121464021Open ↗
01/10/2013121464021Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST5
03/03/2014121932864Open ↗
02/13/2014121464021Open ↗
01/10/2013121464021Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/20/2026M01322147-S1Open ↗
08/20/2026M01322147-S5Open ↗
08/20/2026M01322147-S3Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
02/28/2014121932864Open ↗
▸Trade Schedules & Equipment6
▸BISSCHEDULE B - PLUMBING4
02/13/2014121464021Open ↗
01/10/2013121464021Open ↗
01/10/2013121464021Open ↗
Showing 3 of 4 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA2
01/02/2013120510599Open ↗
11/16/2012110353288Open ↗
▸Environmental & Asbestos7
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'5
12/17/2010120510599Open ↗
06/04/2010120314784Open ↗
08/18/2009120112573Open ↗
Showing 3 of 5 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
02/15/2017123019081Open ↗
02/28/2014121932864Open ↗
▸Energy Compliance7
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS7
08/24/2017123019081Open ↗
03/02/2017123019081Open ↗
02/15/2017123019081Open ↗
Showing 3 of 7 on file for this type
▸Approvals, Objections & Sign-offs14
▸BISADMINISTRATIVE OBJECTIONS5
12/20/2012121464021Open ↗
12/17/2010120510599Open ↗
08/18/2009120112573Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter5
08/20/2026M01322147-S5Open ↗
08/20/2026M01322147-S4Open ↗
08/20/2026M01322147-S3Open ↗
Showing 3 of 5 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST3
03/05/2018122810440Open ↗
02/26/2015121932864Open ↗
02/02/2011110449426Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
12/17/2010110449426Open ↗
▸Cost, Insurance & Ownership12
▸BISCOST AFFIDAVIT12
02/15/2017123019081Open ↗
02/26/2015121932864Open ↗
02/28/2014121932864Open ↗
Showing 3 of 12 on file for this type
▸Filing & Intake Forms11
▸BISEFILING COVER SHEET9
02/15/2017123019081Open ↗
02/15/2017123019081Open ↗
02/15/2017123019081Open ↗
Showing 3 of 9 on file for this type
▸BISBOROUGH INTAKE FORM1
03/05/2018122810440Open ↗
▸BISeFiling Job Application Cover Sheet1
03/05/2009110449426Open ↗
▸Other Documents6
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION5
02/14/2017123019081Open ↗
02/14/2017123019081Open ↗
07/08/2016122810440Open ↗
Showing 3 of 5 on file for this type
▸BISSupporting Document: Fee Deferment1
07/08/2016122810440Open ↗