| Owner | Filings | Most Recent |
|---|---|---|
| S W MANAGEMENT | 7 | 07/08/2026 |
| NEW AMERICAN CONSTRUCTION INC | 5 | 03/22/2026 |
| 13-15 SHERIDAN SQUARE | 12 | 03/22/2026 |
| MNR GROUP | 2 | 03/22/2026 |
| GEORGE BAUER INC | 1 | 03/22/2026 |
| AT&T MOBILITY | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| LEDER-LUIS ARCHITECTURAL DESIGN, PL | 2 | 01/22/2021 |
| GREEN DESIGN | 2 | 07/02/2019 |
| SCALAR ARCHITECTURE PC | 1 | 12/29/2017 |
| Representative | Filings | Most Recent |
|---|---|---|
| XPDITE GROUP LLC (104) | 2 | 03/21/2026 |
| AE DESIGN SOLUTION | 2 | 03/21/2026 |
| ATLANTIC BUILDING SUPPLY INC. | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MNR GROUP INC | General Contractor | 12 | 07/08/2026 |
| NEW AMERICAN CONSTRUCTION INC | General Contractor | 4 | 07/08/2026 |
| HARLEY PLUMB & HEAT INC | Plumbing | 2 | 07/08/2026 |
| PETER MILEVSKI | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| LEDER-LUIS ARCHITECTURAL | 1553 | 2 | 01/22/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Supported Scaffold | Signed-off | MNR GROUP INC | 12/04/2020 |
| DOB NOW | Plumbing | Signed-off | HARLEY PLUMB & HEAT INC | 04/21/2020 |
| DOB NOW | Supported Scaffold | Signed-off | MNR GROUP INC | 11/18/2019 |
| DOB NOW | Supported Scaffold | Signed-off | MNR GROUP INC | 11/13/2019 |
| DOB NOW | Plumbing | Signed-off | HARLEY PLUMB & HEAT INC | 10/23/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | NEW AMERICAN CONSTRUCTION | 07/03/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | NEW AMERICAN CONSTRUCTION | 06/17/2019 |
| DOB NOW | Supported Scaffold | Signed-off | MNR GROUP INC | 03/29/2019 |
| DOB NOW | Supported Scaffold | Signed-off | MNR GROUP INC | 11/19/2018 |
| DOB NOW | Supported Scaffold | Signed-off | MNR GROUP INC | 08/20/2018 |
| DOB NOW | Supported Scaffold | Signed-off | MNR GROUP INC | 05/29/2018 |
| DOB NOW | Supported Scaffold | Signed-off | MNR GROUP INC | 01/03/2018 |
| BIS | OT | ISSUED | MNR GROUP INC | 05/11/2020 |
| BIS | EQ | ISSUED | RENNON CONSTRUCTION CORP | 03/17/2020 |
| BIS | OT | ISSUED | MNR GROUP INC | 06/05/2019 |
| BIS | EQ | RE-ISSUED | RENNON CONSTRUCTION CORP | 03/08/2019 |
| BIS | OT | ISSUED | MNR GROUP INC | 08/27/2018 |
| BIS | OT | ISSUED | ZAIN CONTRACTING INC | 06/28/2018 |
| BIS | EQ | ISSUED | RENNON CONSTRUCTION CORP | 03/01/2018 |
| BIS | EQ | ISSUED | RENNON CONSTRUCTION CORP | 03/03/2017 |
| BIS | OT | ISSUED | MNR GROUP INC | 06/27/2014 |
| BIS | OT | ISSUED | MNR GROUP INC | 05/09/2014 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/16/2019 | Complete | COUNTY ELECL CONTRACTOR I | Boiler Controls |
| 06/26/2019 | Permit Issued | A WILCO ELECTRIC LLC | General Wiring |
| 06/14/2019 | Complete | RICHARD NEU | — |
| 05/01/2019 | Permit Issued | A WILCO ELECTRIC LLC | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/02/2021 | Fire-Resistant Penetrations and Joints | Julio Leder-Luis | special |
| 01/19/2021 | Fire-Resistant Penetrations and Joints | Julio Leder-Luis | special |
| 07/01/2019 | Final | BRIAN T. O'CONNOR | progress |
| 10/23/2017 | Final | JULIO SALCEDO-FERNANDEZ | progress |