← Back
Two family brick
13-04 33 AVENUE
QUEENS · Queensbridge-Ravenswood-Dutch Kills · BIN 4458146
💬 Discuss this project
1996Year Built
3Stories
B1Building Class
R6Zoning
—Gross Floor Area
2Units
Two family brick · 1.8 FAR built · Flood zone X500
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR208/14/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ISLAND ELECTRIC CORPElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281208/14/2025
Building Lifecycle
All (14)Filed (2)Permit Issued (1)Signed Off (1)Special Inspection (10)
08/28/2025
Signed off — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 7 Panels, 2.87 kW
Q01092891-I1
08/15/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
08/15/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
08/15/2025
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
08/15/2025
Special inspection requirement — Final
Mina Makar
08/15/2025
Special inspection requirement — Air barrier - visual inspection
Mina Makar
08/14/2025
Filed — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 7 Panels, 2.87 kW
Q01092891-P1
05/07/2025
Special inspection requirement — Air barrier - visual inspection
Mina Makar
05/07/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
05/07/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
05/07/2025
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
05/07/2025
Special inspection requirement — Final
Mina Makar
08/16/2024
Permit issued — Solar
Q01092891-I1-SL
08/07/2024
Filed — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 7 Panels, 2.87 kW
Q01092891-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offMOMENTUM SOLAR08/16/2024
BIS—ISSUEDHALLETS COVE CONST09/24/1996
BISPLISSUEDBLAU MECHANICAL CORP.10/16/1995
BIS—ISSUEDHALLETS COVE CONST04/07/1995
1 project · most recent 08/07/2024
FiledStatusContractorScope
08/07/2024CompleteISLAND ELECTRIC CORP—
▾Special Inspection Requirements (DOB NOW) — 10
DateRequirementInspectorRole
08/15/2025Structural Stability – Alterations of existing buildingsMina Makarspecial
08/15/2025Fire-Resistant Penetrations and JointsMina Makarspecial
08/15/2025Energy Code Compliance InspectionsMina Makarprogress
08/15/2025FinalMina Makarprogress
08/15/2025Air barrier - visual inspectionMina Makarenergy_progress
05/07/2025Air barrier - visual inspectionMina Makarenergy_progress
05/07/2025Fire-Resistant Penetrations and JointsMina Makarspecial
05/07/2025Structural Stability – Alterations of existing buildingsMina Makarspecial
05/07/2025Energy Code Compliance InspectionsMina Makarprogress
05/07/2025FinalMina Makarprogress
▾Documents — 11 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/21/2026Q01092891-I1Request digital key ↗
08/21/2026Q01092891-P1Request digital key ↗
▸Seals & Professional Certifications8
▸DOB NOWProgress Inspector Seal & Signature4
09/23/2026Q01092891-P1Open ↗
08/28/2026Q01092891-I1Open ↗
08/28/2026Q01092891-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/21/2026Q01092891-I1Open ↗
08/21/2026Q01092891-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/23/2026Q01092891-P1Open ↗
08/28/2026Q01092891-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01092891-I1Open ↗