| Owner | Filings | Most Recent |
|---|---|---|
| SEVA PROPERTY DEVELOPMENT | 4 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 03/01/2021 | $679K | — | — → — | $224/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| TOM PETERSEN ARCHITECT, LLC | 1 | 03/21/2025 |
| METRO STRUCTURES | 7 | 11/20/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| PINNACLE BUILDING CON | 7 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SEVA PROPERTY DEVLOPMENT | General Contractor | 2 | 07/08/2026 |
| ALL PRO PLBG & HTG INC | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| THOMAS PETERSEN ARCHITECT | 7854 | 1 | 03/21/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | TOM PETERSEN ARCHITECT, LLC | 04/08/2025 |
| DOB NOW | Plumbing | Permit Issued | ALL PRO PLBG & HTG INC | 07/31/2023 |
| DOB NOW | General Construction | Permit Issued | SEVA PROPERTY DEVLOPMENT | 10/05/2022 |
| DOB NOW | Construction Fence | Signed-off | SEVA PROPERTY DEVLOPMENT | 07/09/2022 |
| DOB NOW | Plumbing | Permit Issued | ALL PRO PLBG & HTG INC | 06/09/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/20/2023 | Permit Issued | ALL PRO PLBG & HTG INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/06/2025 | Complete | VENTURE HOME SOLAR LLC | — |
| 03/27/2023 | Permit Issued | AYYUB ELECTRIC CORP | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/25/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/22/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/03/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 10/30/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 10/18/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 08/10/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/21/2025 | Air barrier - visual inspection | TOM PETERSEN | energy_progress |
| 03/21/2025 | Fire-Resistant Penetrations and Joints | TOM PETERSEN | special |
| 03/21/2025 | Structural Stability – Alterations of existing buildings | TOM PETERSEN | special |
| 03/21/2025 | Energy Code Compliance Inspections | TOM PETERSEN | progress |
| 03/21/2025 | Final | TOM PETERSEN | progress |
| 06/14/2023 | HVAC-R and service water heating equipment | Augustine Angba | energy_progress |
| 06/14/2023 | HVAC-R and service water heating system controls | Augustine Angba | energy_progress |
| 06/14/2023 | Energy Code Compliance Inspections | Augustine Angba | progress |
| 06/14/2023 | HVAC-R and service water piping design and insulation | Augustine Angba | energy_progress |
| 01/26/2023 | Energy Code Compliance Inspections | Augustine Angba | progress |
| 01/26/2023 | HVAC-R and service water heating equipment | Augustine Angba | energy_progress |
| 01/26/2023 | HVAC-R and service water piping design and insulation | Augustine Angba | energy_progress |
| 01/26/2023 | HVAC-R and service water heating system controls | Augustine Angba | energy_progress |
| 01/06/2023 | Fenestration areas | Augustine Angba | energy_progress |
| 01/06/2023 | Lighting controls | Augustine Angba | energy_progress |
| 01/06/2023 | Air barrier - visual inspection | Augustine Angba | energy_progress |
| 01/06/2023 | Lighting in dwelling units | Augustine Angba | energy_progress |
| 01/06/2023 | Insulation placement and R values | Augustine Angba | energy_progress |
| 01/06/2023 | Fenestration air leakage | Augustine Angba | energy_progress |
| 01/06/2023 | Fenestration and door U-factor and product ratings | Augustine Angba | energy_progress |
| 01/06/2023 | Fire-Resistance Rated Construction | Augustine Angba | progress |
| 01/06/2023 | Energy Code Compliance Inspections | Augustine Angba | progress |