RoofStructural work for new roof deckUnder Construction122p · 6 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Structural
STRUCTURAL WORK FOR NEW ROOF DECK (PATIO) AT 3RD FLOOR ROOF (4TH FLOOR LEVEL) AS PER PLANS. OBTAIN ST PERMIT. NO CHANGE IN USE, EGRESS OR OCCUPANCY. NOTE: AS PER NYC B.B. 2018-002, THE IMPOSED ROOF LOADS BY THIS PATIO IS ZERO. THE IMPOSED LOADS FROM THE
On file for this project
16 documents · 3 drawing sheets
INSTALL NEW HVAC UNITS AND NEW DUCTING AS PER ATTACHED PLANS. EXISTING COOLING, HEATING & VENTILATION SUPPLY SYSTEMS (COOLING TOWERS, HW BOILERS, HEAT EXCHANGER, MAKE-UP AIR UNITS) TO REMAIN. INSTALL PURGING SYSTEM AS PER PLAN, SEE SHEETS 11 THRU 17.
On file for this project
19 documents · 8 drawing sheets
INSTALL NEW PLUMBING SYSTEM AS PER PLANS. OBTAIN PL PERMIT. THIS APPLICATION IS FILED IN CONJUNCTION WITH THE ALT-CO B00935173-I1 BY EUGENE MEKHTIYEV, RA. (IMC ARCHITECTURE), AND A PREVIOUSLY FILED BIS# 301900110, ALT 1 SIGNED OFF:
On file for this project
49 documents · 21 drawing sheets
Latest 3 of 6 filings on this floor.
Floor 6Hkf INC126p · 5 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
INSTALL NEW HVAC UNITS AND NEW DUCTING AS PER ATTACHED PLANS. EXISTING COOLING, HEATING & VENTILATION SUPPLY SYSTEMS (COOLING TOWERS, HW BOILERS, HEAT EXCHANGER, MAKE-UP AIR UNITS) TO REMAIN. INSTALL PURGING SYSTEM AS PER PLAN, SEE SHEETS 11 THRU 17.
On file for this project
19 documents
INSTALL NEW PLUMBING SYSTEM AS PER PLANS. OBTAIN PL PERMIT. THIS APPLICATION IS FILED IN CONJUNCTION WITH THE ALT-CO B00935173-I1 BY EUGENE MEKHTIYEV, RA. (IMC ARCHITECTURE), AND A PREVIOUSLY FILED BIS# 301900110, ALT 1 SIGNED OFF:
On file for this project
49 documents · 1 drawing sheet
APPLICATION IS FILED TO CONVERT EXISTING COMMERCIAL BUILDING INTO A TRANSIENT LODGING HOUSE WITH 16 SLEEPING ROOM ACCOMODATIONS FOR A TOTAL OF 400 BEDS AND ACCESSORY OFFICES AS SHOWN ON PLANS.
On file for this project
24 documents
Latest 3 of 5 filings on this floor.
Floor 5Hkf INC122p · 5 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
INSTALL NEW HVAC UNITS AND NEW DUCTING AS PER ATTACHED PLANS. EXISTING COOLING, HEATING & VENTILATION SUPPLY SYSTEMS (COOLING TOWERS, HW BOILERS, HEAT EXCHANGER, MAKE-UP AIR UNITS) TO REMAIN. INSTALL PURGING SYSTEM AS PER PLAN, SEE SHEETS 11 THRU 17.
On file for this project
19 documents
INSTALL NEW PLUMBING SYSTEM AS PER PLANS. OBTAIN PL PERMIT. THIS APPLICATION IS FILED IN CONJUNCTION WITH THE ALT-CO B00935173-I1 BY EUGENE MEKHTIYEV, RA. (IMC ARCHITECTURE), AND A PREVIOUSLY FILED BIS# 301900110, ALT 1 SIGNED OFF:
On file for this project
49 documents
APPLICATION IS FILED TO CONVERT EXISTING COMMERCIAL BUILDING INTO A TRANSIENT LODGING HOUSE WITH 16 SLEEPING ROOM ACCOMODATIONS FOR A TOTAL OF 400 BEDS AND ACCESSORY OFFICES AS SHOWN ON PLANS.
On file for this project
24 documents · 2 drawing sheets
Latest 3 of 5 filings on this floor.
Floor 4Hkf INCUnder Construction138p · 6 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
APPLICATION FILED FOR STORAGE ROOMS IN THE CELLAR AS WELL AS ROOFTOP OCCUPANCY PURSUANT TO BUILDING BULLETIN 2018-002. NO CHANGE IN USE, EGRESS OROCCUPANCY UNDER THIS APPLICATION.
On file for this project
3 documents · 3 drawing sheets
INSTALL NEW HVAC UNITS AND NEW DUCTING AS PER ATTACHED PLANS. EXISTING COOLING, HEATING & VENTILATION SUPPLY SYSTEMS (COOLING TOWERS, HW BOILERS, HEAT EXCHANGER, MAKE-UP AIR UNITS) TO REMAIN. INSTALL PURGING SYSTEM AS PER PLAN, SEE SHEETS 11 THRU 17.
On file for this project
19 documents · 3 drawing sheets
INSTALL NEW PLUMBING SYSTEM AS PER PLANS. OBTAIN PL PERMIT. THIS APPLICATION IS FILED IN CONJUNCTION WITH THE ALT-CO B00935173-I1 BY EUGENE MEKHTIYEV, RA. (IMC ARCHITECTURE), AND A PREVIOUSLY FILED BIS# 301900110, ALT 1 SIGNED OFF:
On file for this project
49 documents · 3 drawing sheets
Latest 3 of 6 filings on this floor.
Floor 3Hkf INC135p · 5 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
INSTALL NEW HVAC UNITS AND NEW DUCTING AS PER ATTACHED PLANS. EXISTING COOLING, HEATING & VENTILATION SUPPLY SYSTEMS (COOLING TOWERS, HW BOILERS, HEAT EXCHANGER, MAKE-UP AIR UNITS) TO REMAIN. INSTALL PURGING SYSTEM AS PER PLAN, SEE SHEETS 11 THRU 17.
On file for this project
19 documents · 1 drawing sheet
INSTALL NEW PLUMBING SYSTEM AS PER PLANS. OBTAIN PL PERMIT. THIS APPLICATION IS FILED IN CONJUNCTION WITH THE ALT-CO B00935173-I1 BY EUGENE MEKHTIYEV, RA. (IMC ARCHITECTURE), AND A PREVIOUSLY FILED BIS# 301900110, ALT 1 SIGNED OFF:
On file for this project
49 documents · 6 drawing sheets
APPLICATION IS FILED TO CONVERT EXISTING COMMERCIAL BUILDING INTO A TRANSIENT LODGING HOUSE WITH 16 SLEEPING ROOM ACCOMODATIONS FOR A TOTAL OF 400 BEDS AND ACCESSORY OFFICES AS SHOWN ON PLANS.
On file for this project
24 documents · 2 drawing sheets
Latest 3 of 5 filings on this floor.
Floor 2Hkf INC150p · 8 filings · 20 docs
ArchitectureCivilFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
INSTALL NEW HVAC UNITS AND NEW DUCTING AS PER ATTACHED PLANS. EXISTING COOLING, HEATING & VENTILATION SUPPLY SYSTEMS (COOLING TOWERS, HW BOILERS, HEAT EXCHANGER, MAKE-UP AIR UNITS) TO REMAIN. INSTALL PURGING SYSTEM AS PER PLAN, SEE SHEETS 11 THRU 17.
On file for this project
19 documents · 1 drawing sheet
INSTALL NEW PLUMBING SYSTEM AS PER PLANS. OBTAIN PL PERMIT. THIS APPLICATION IS FILED IN CONJUNCTION WITH THE ALT-CO B00935173-I1 BY EUGENE MEKHTIYEV, RA. (IMC ARCHITECTURE), AND A PREVIOUSLY FILED BIS# 301900110, ALT 1 SIGNED OFF:
On file for this project
49 documents · 12 drawing sheets
APPLICATION IS FILED TO CONVERT EXISTING COMMERCIAL BUILDING INTO A TRANSIENT LODGING HOUSE WITH 16 SLEEPING ROOM ACCOMODATIONS FOR A TOTAL OF 400 BEDS AND ACCESSORY OFFICES AS SHOWN ON PLANS.
On file for this project
24 documents · 3 drawing sheets
Latest 3 of 8 filings on this floor.
Floor 1Hkf INC141p · 7 filings · 20 docs
ArchitectureCivilFire ProtectionGeneralMechanicalPlumbingStructuralOther
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
INSTALL NEW HVAC UNITS AND NEW DUCTING AS PER ATTACHED PLANS. EXISTING COOLING, HEATING & VENTILATION SUPPLY SYSTEMS (COOLING TOWERS, HW BOILERS, HEAT EXCHANGER, MAKE-UP AIR UNITS) TO REMAIN. INSTALL PURGING SYSTEM AS PER PLAN, SEE SHEETS 11 THRU 17.
On file for this project
19 documents · 2 drawing sheets
INSTALL NEW PLUMBING SYSTEM AS PER PLANS. OBTAIN PL PERMIT. THIS APPLICATION IS FILED IN CONJUNCTION WITH THE ALT-CO B00935173-I1 BY EUGENE MEKHTIYEV, RA. (IMC ARCHITECTURE), AND A PREVIOUSLY FILED BIS# 301900110, ALT 1 SIGNED OFF:
On file for this project
49 documents · 8 drawing sheets
APPLICATION IS FILED TO CONVERT EXISTING COMMERCIAL BUILDING INTO A TRANSIENT LODGING HOUSE WITH 16 SLEEPING ROOM ACCOMODATIONS FOR A TOTAL OF 400 BEDS AND ACCESSORY OFFICES AS SHOWN ON PLANS.
On file for this project
24 documents · 3 drawing sheets
Latest 3 of 7 filings on this floor.
CellarHkf INCUnder Construction60p · 7 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing
APPLICATION FILED FOR STORAGE ROOMS IN THE CELLAR AS WELL AS ROOFTOP OCCUPANCY PURSUANT TO BUILDING BULLETIN 2018-002. NO CHANGE IN USE, EGRESS OROCCUPANCY UNDER THIS APPLICATION.
On file for this project
3 documents · 1 drawing sheet
INSTALL NEW HVAC UNITS AND NEW DUCTING AS PER ATTACHED PLANS. EXISTING COOLING, HEATING & VENTILATION SUPPLY SYSTEMS (COOLING TOWERS, HW BOILERS, HEAT EXCHANGER, MAKE-UP AIR UNITS) TO REMAIN. INSTALL PURGING SYSTEM AS PER PLAN, SEE SHEETS 11 THRU 17.
On file for this project
19 documents · 4 drawing sheets
INSTALL NEW PLUMBING SYSTEM AS PER PLANS. OBTAIN PL PERMIT. THIS APPLICATION IS FILED IN CONJUNCTION WITH THE ALT-CO B00935173-I1 BY EUGENE MEKHTIYEV, RA. (IMC ARCHITECTURE), AND A PREVIOUSLY FILED BIS# 301900110, ALT 1 SIGNED OFF:
On file for this project
49 documents · 8 drawing sheets
Latest 3 of 7 filings on this floor.
Site & exteriorHkf INC5p · 3 filings · 20 docs
ArchitectureMechanical
Issued Permit Scope
Boiler Equipment · General Construction · Mechanical Systems
APPLICATION IS FILED TO CONVERT EXISTING COMMERCIAL BUILDING INTO A TRANSIENT LODGING HOUSE WITH 16 SLEEPING ROOM ACCOMODATIONS FOR A TOTAL OF 400 BEDS AND ACCESSORY OFFICES AS SHOWN ON PLANS.
On file for this project
24 documents · 12 drawing sheets
FUEL OIL STORAGE FOR DIESEL GENERATOR. NO CHANGE OF USE,EGRESS AND OCCUPANCY
On file for this project
3 documents · 3 drawing sheets
INSTALL POST SMOKE PURGE AND EMERGENCY GENERATOR. NO CHANGE IN OCCUPANCY, USE OR EGRESS.
On file for this project
3 documents · 11 drawing sheets