| Owner | Filings | Most Recent |
|---|---|---|
| DASNY | 49 | 07/08/2026 |
| DESIGN CONS MGMT -CUNY | 19 | 03/21/2026 |
| DORMITORY AUTHORITY OF THE STATE OF NEW YORK | 5 | 03/22/2026 |
| DORMITORY AUTHORITY STATE OF NY | 5 | 03/21/2026 |
| CUNY | 4 | 09/08/2026 |
| DASNY ONE PENN PLAZA 52ND FLOOR | 2 | 03/21/2026 |
| DASNY- 695 PARK AVE W BUILDING | 2 | 03/21/2026 |
| STATE | 2 | 03/21/2026 |
| STATE OF NY | 1 | 03/21/2026 |
| NYS DORMITORY AUTHORITY | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| KERI ENGINEERING, P.C. | 10 | 07/28/2026 |
| MARVEL ARCHITECTS | 3 | 07/24/2026 |
| LIZARDOS ENGINEERING | 4 | 05/08/2026 |
| POLISE CONSULTING ENGINEERS DPC | 2 | 04/30/2026 |
| SGVA | 1 | 03/26/2026 |
| SUPERSTRUCTURES ENG. + ARCH. | 3 | 07/16/2025 |
| P.A. COLLINS PE | 6 | 05/25/2023 |
| AK CONSULTING SERVICES, INC | 1 | 03/25/2021 |
| CALVERT WRIGHT ARCHITECTURE PC | 1 | 03/15/2021 |
| SYED ENGINEERING, P.C. | 1 | 03/02/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| JM ZONING, LLC. | 20 | 03/21/2026 |
| SUPERSTRUCTURES ENG + ARCH | 3 | 03/21/2026 |
| AK CONSULTING SERVICES | 2 | 03/21/2026 |
| NOEL BUILDING CONSULTING INC | 14 | 03/21/2026 |
| CONSTRUCTION PERMIT SERVICES | 6 | 03/21/2026 |
| ADVANCED BUILDERS SERVICES | 1 | 03/21/2026 |
| SKYLINE ACCESS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| VANGUARD CONSTRUCTION AND | General Contractor | 15 | 07/08/2026 |
| PAR FIRE PROTECTION LLC | Fire Protection | 4 | 07/08/2026 |
| PROJECT EYE CONSULTANTS I | General Contractor | 4 | 07/08/2026 |
| EVERLAST SCAFFOLDING INC | General Contractor | 4 | 03/21/2026 |
| B&B CONTRACTING GRP LLC | General Contractor | 3 | 04/09/2026 |
| SIRINA FIRE PROT CORP | Fire Protection | 2 | 07/08/2026 |
| SKH MECHANICAL CORP | Fire Protection | 2 | 07/08/2026 |
| RICHARDS P AND H CO, INC | Plumbing | 1 | 06/27/2026 |
| I.P. ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| SHIMON LEVITA | Electrical | 1 | 03/21/2026 |
| M.S.T GENERAL CONTRACTING | General Contractor | 1 | 07/08/2026 |
| MAC FELDER INC | Plumbing | 1 | 07/08/2026 |
| PAR PLUMBING CO., INC | Plumbing | 1 | 07/08/2026 |
| G ENERGY SOLTN AND SVCS I | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ALAN MARGOLIN & ASSOC | 423 | 8 | 07/28/2026 |
| QUALITY CONTROL LABORATOR | 406 | 5 | 10/16/2025 |
| TECTONIC ENGINEERING CONS | 106 | 3 | 07/29/2025 |
| FUTURE TECH CONSULTANTS O | 589 | 10 | 07/16/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | VANGUARD CONSTRUCTION AND | 06/30/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | VANGUARD CONSTRUCTION AND | 06/30/2026 |
| DOB NOW | General Construction | Permit Issued | B&B CONTRACTING GRP LLC | 12/11/2025 |
| DOB NOW | General Construction | Permit Issued | B&B CONTRACTING GRP LLC | 12/11/2025 |
| DOB NOW | Sprinklers | Signed-off | SKH MECHANICAL CORP | 09/19/2025 |
| DOB NOW | Plumbing | Permit Issued | RICHARDS P AND H CO, INC | 09/02/2025 |
| DOB NOW | General Construction | Permit Issued | B&B CONTRACTING GRP LLC | 08/13/2025 |
| DOB NOW | General Construction | Permit Issued | VANGUARD CONSTRUCTION AND | 06/18/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | VANGUARD CONSTRUCTION AND | 06/18/2025 |
| DOB NOW | Boiler Equipment | Permit Issued | OLYMPIAN FUEL OIL CORP | 06/04/2025 |
| DOB NOW | Sprinklers | Signed-off | MAC FELDER INC | 01/16/2025 |
| DOB NOW | Sprinklers | Signed-off | SKH MECHANICAL CORP | 01/15/2025 |
| DOB NOW | General Construction | Permit Issued | VANGUARD CONSTRUCTION AND | 01/10/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | VANGUARD CONSTRUCTION AND | 01/10/2025 |
| DOB NOW | Boiler Equipment | Permit Issued | MARATHON SOLUTIONS LLC | 09/12/2024 |
| DOB NOW | Suspended Scaffold | Permit Issued | SKYLINE RESTORATION INC | 07/30/2024 |
| DOB NOW | Mechanical Systems | Signed-off | PROJECT EYE CONSULTANTS I | 01/26/2024 |
| DOB NOW | Sprinklers | Signed-off | SIRINA FIRE PROT CORP | 01/18/2024 |
| DOB NOW | General Construction | Signed-off | PROJECT EYE CONSULTANTS I | 01/03/2024 |
| DOB NOW | Sprinklers | Permit Issued | SIRINA FIRE PROT CORP | 12/15/2023 |
| DOB NOW | General Construction | Signed-off | VANGUARD CONSTRUCTION AND | 08/18/2022 |
| DOB NOW | Sprinklers | Signed-off | LAWRENCE J. LEVINE | 07/23/2022 |
| DOB NOW | Sprinklers | Signed-off | LAWRENCE J. LEVINE | 07/23/2022 |
| DOB NOW | Sidewalk Shed | Permit Issued | EVERLAST SCAFFOLDING | 02/03/2022 |
| DOB NOW | General Construction | Signed-off | VANGUARD CONSTRUCTION AND | 08/19/2021 |
| DOB NOW | Mechanical Systems | Signed-off | VANGUARD CONSTRUCTION AND | 08/19/2021 |
| DOB NOW | Sprinklers | Signed-off | LAWRENCE J. LEVINE | 05/27/2021 |
| DOB NOW | General Construction | Signed-off | VANGUARD CONSTRUCTION AND | 05/13/2021 |
| DOB NOW | Sprinklers | Signed-off | LAWRENCE J. LEVINE | 05/11/2021 |
| DOB NOW | Plumbing | Signed-off | PAR PLUMBING CO., INC | 05/11/2021 |
| DOB NOW | Mechanical Systems | Signed-off | VANGUARD CONSTRUCTION AND | 05/10/2021 |
| DOB NOW | Construction Fence | Permit Issued | M.S.T GENERAL CONTRACTING | 03/26/2021 |
| DOB NOW | Sidewalk Shed | Permit Issued | EVERLAST SCAFFOLDING | 03/05/2021 |
| BIS | OT | ISSUED | R J GREEN CONSTRUCTI CORP | 12/29/2022 |
| BIS | OT | ISSUED | R J GREEN CONSTRUCTI CORP | 12/29/2022 |
| BIS | OT | ISSUED | R J GREEN CONSTRUCTI CORP | 11/22/2022 |
| BIS | OT | ISSUED | R J GREEN CONSTRUCTI CORP | 10/27/2022 |
| BIS | SP | ISSUED | SIRINA FIRE PROT CORP | 06/16/2022 |
| BIS | OT | ISSUED | R J GREEN CONSTRUCTI CORP | 12/28/2021 |
| BIS | OT | ISSUED | R J GREEN CONSTRUCTI CORP | 12/28/2021 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/28/2026 | Permit Issued | VANGUARD CONSTRUCTION AND | Air Conditioning Systems | Cooling York XT1-51X60 6,500 CFM ×1 |
| 04/30/2026 | — | — | Others | Other |
| 10/16/2025 | Signed-off | PROJECT EYE CONSULTANTS I | Others | Other N/A N/A |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/28/2026 | Signed-off | SKH MECHANICAL CORP | Sprinkler System |
| 10/16/2025 | Signed-off | SIRINA FIRE PROT CORP | 376 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/28/2026 | Signed-off | MAC FELDER INC | Water/Sanitary |
| 04/30/2026 | — | — | Water/Sanitary |
| 10/16/2025 | — | — | Water/Sanitary |
| 07/29/2025 | Permit Issued | RICHARDS P AND H CO, INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/29/2026 | Permit Issued | SCHLESINGER ELECT'L CONTR | General Wiring |
| 11/14/2025 | Complete | MAC FHIONNGHAILE & SONS | General Wiring |
| 10/31/2025 | Complete | SCHLESINGER ELECT'L CONTR | — |
| 02/01/2025 | Cancelled | I.P. ELECTRIC INC | General Wiring |
| 08/15/2024 | Complete | MILAD CONTRACTING CORP. | General Wiring |
| 11/17/2023 | Complete | GOTTLIEB ELECTRIC, LLC | — |
| 05/20/2021 | Permit Issued | G ENERGY SOLTN AND SVCS I | General Wiring |
| 03/08/2021 | Permit Issued | STANCO SYSTEM ELEC'L CONT | — |
| 03/23/2018 | Permit Issued | ELPO ELECTRICAL CONTG INC | General Wiring, Lighting |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/16/2025 | Permit Issued | B&B CONTRACTING GRP LLC | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/25/2021 | Permit Issued | M.S.T GENERAL CONTRACTING | Fence |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/23/2024 | Permit Issued | — | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/17/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/30/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/22/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/17/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/25/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/20/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 02/12/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/23/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/11/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/05/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/05/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/11/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 06/02/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 06/02/2023 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 06/02/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/02/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 10/04/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/19/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 08/12/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/03/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/29/2021 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/03/2026 | Sprinkler Systems | Young Suh | special |
| 08/03/2026 | Post-installed Anchors | Young Suh | special |
| 07/28/2026 | Fire-Resistant Penetrations and Joints | Young Suh | special |
| 07/28/2026 | Final | Young Suh | progress |
| 07/28/2026 | Fire-Resistance Rated Construction | Young Suh | progress |
| 07/28/2026 | Energy Code Compliance Inspections | Young Suh | progress |
| 07/28/2026 | Sprayed fire-resistant materials | Young Suh | special |
| 07/17/2026 | Fire-Resistance Rated Construction | Young Suh | progress |
| 07/17/2026 | Final | Young Suh | progress |
| 07/17/2026 | Energy Code Compliance Inspections | Young Suh | progress |
| 07/17/2026 | Sprayed fire-resistant materials | Young Suh | special |
| 07/17/2026 | Fire-Resistant Penetrations and Joints | Young Suh | special |
| 07/17/2026 | Sprinkler Systems | Young Suh | special |
| 07/17/2026 | Post-installed Anchors | Young Suh | special |
| 04/02/2026 | Interior lighting power | — | energy_progress |
| 03/30/2026 | Post-installed Anchors | Young Suh | special |
| 03/30/2026 | Sprinkler Systems | Young Suh | special |
| 02/06/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 02/06/2026 | Final | — | progress |
| 10/03/2025 | Fuel-Oil Storage and Fuel-Oil Piping Systems | — | special |
| 09/08/2025 | Sprinkler Systems | EDWIN DEGUZMAN | special |
| 08/11/2025 | Post-installed Anchors | GEORGE GHEBRYAL | special |
| 07/14/2025 | Structural Steel - Welding | MARISA HARTE | special |
| 07/14/2025 | Concrete - Cast-In-Place | MARISA HARTE | special |
| 07/14/2025 | Fire-Resistant Penetrations and Joints | MARISA HARTE | special |