| Owner | Filings | Most Recent |
|---|---|---|
| 130 ST. FELIX STREET LLC | 1 | 03/22/2026 |
| IPARK | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/11/2015 | $5.5M | — | — → — | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| ETTINGER ENGINEERING ASSOCIATES | 3 | 08/05/2026 |
| DESIMONE CONSULTING ENGINEERS | 2 | 07/28/2026 |
| LANGAN ENGINEERING | 1 | 07/14/2026 |
| FXCOLLABORATIVE ARCHITECTS LLP | 1 | 07/02/2026 |
| MB ARCHITECT PC | 1 | 10/15/2024 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| THOMAS MAINTENANCE INC | General Contractor | 1 | 07/08/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Permit Issued | THOMAS MAINTENANCE INC | 10/21/2024 |
| BIS | — | ISSUED | H.THOMAS O'HARA ARCHITECTS | 04/11/2007 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/05/2026 | — | — | Steel, Concrete, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/15/2024 | Permit Issued | THOMAS MAINTENANCE INC | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/31/2026 | Energy Code Compliance Inspections | — | progress |
| 07/31/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 07/31/2026 | Exhaust and Vent Systems in Plenums and Ducts | — | special |
| 07/31/2026 | Maintenance information | — | energy_progress |
| 07/31/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 07/31/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 07/31/2026 | Maintenance information | — | energy_progress |
| 07/31/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 07/31/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 07/31/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 07/31/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 07/31/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | — | special |
| 07/31/2026 | Energy Code Compliance Inspections | — | progress |
| 07/31/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 07/31/2026 | Post-installed Anchors | — | special |
| 07/31/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 07/31/2026 | Duct leakage testing, insulation and design | — | energy_progress |
| 07/16/2026 | Masonry | — | special |
| 07/16/2026 | Structural Cold-Formed Steel | — | special |
| 07/16/2026 | Structural Steel - Details | — | special |
| 07/16/2026 | Concrete - Cast-In-Place | — | special |
| 07/16/2026 | Post-installed Anchors | — | special |
| 07/16/2026 | Structural Steel - High Strength Bolting | — | special |
| 07/16/2026 | Structural Steel - Welding | — | special |
| 07/08/2026 | Structural Steel - Welding | — | special |