← Back
Elevator co-op, conversion from loft/warehouse
130 WEST 24 STREET
MANHATTAN · Chelsea-Hudson Yards · BIN 1014962
💬 Discuss this project
1898Year Built
5Stories
D0Building Class
M1-8A/R11Zoning
33,514 sfGross Floor Area
13Units
LL97 CoveredRent Stabilized3 Open Violations ▸
Elevator co-op, conversion from loft/warehouse · Owner of record: ALLOFUS TENANTS INC · 7,455 sf lot · 4.5 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbing
Floor 520p · 1 filing · 20 docs
Floor 419p · 1 filing · 20 docs
Floor 319p · 1 filing · 20 docs
Floor 219p · 1 filing · 20 docs
Floor 132p · 2 filings · 20 docs
Cellar19p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
ROCK GROUP NY1707/08/2026
RELIABLE ENTERPRISES503/22/2026
ALLOFUS TENNANTS INC4403/22/2026
AGL INDUSTRIES103/22/2026
TRI-STAR EQUITIES203/21/2026
C O TRI-STAR EQUITIES103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SWA ARCHITECTURE1306/04/2025
ROBERT GERMAIN JR. PE210/29/2024
MJE PROFESSIONAL SERVICES103/07/2024
THOMAS ZAPOTICZNY203/01/2024
GC ENG & ASSOCIATES, PC102/08/2024
IDSR ARCHITECTURE106/30/2020
ASIF JAMIL, RA206/18/2020
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SWA ARCHITECTURE2803/21/2026
GREEN STUDIO403/21/2026
AGOUTI CONSTRUCTION CONSULTING203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ROCK GROUP NY CORPGeneral Contractor1203/21/2026
TUC-MEN CONTRACTING CORPGeneral Contractor1207/08/2026
PLATINUM SERVICES NY LLCGeneral Contractor407/08/2026
RELIABLE ENTERPRISES INCGeneral Contractor303/21/2026
ALL PRO PLBG & HTG INCPlumbing207/08/2026
FREDERICK LEEElectrical103/21/2026
FERNANDEZ HTG & MECH CORP.Plumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AUTOGRAPHIC CO1579606/04/2025
CATALPA SPECIAL INSPECTIO20041106/04/2025
ROBERT F. GERMAIN JR. PE5100210/29/2024
Building Lifecycle
All (138)Filed (22)Permit Issued (19)Signed Off (8)Violation (21)Inspection (12)Objection (26)Special Inspection (30)
06/18/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
ERIC BERLENT
06/18/2025
Special inspection requirement — Energy Code Compliance Inspections
ERIC BERLENT
06/18/2025
Special inspection requirement — Interior lighting power
ERIC BERLENT
06/18/2025
Special inspection requirement — Fire-Resistance Rated Construction
ERIC BERLENT
06/18/2025
Special inspection requirement — Lighting controls
ERIC BERLENT
06/18/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
asghar Ghodsi
06/04/2025
Filed — Alteration CO
FILING FOR CHANGE OF USE AT 1ST FLOOR TO USE GROUP SIX (6). WORK TO INCLUDE GEN. CONSTRUCTION, INSTALLATION OF HANDICAP RAMP, PLATFORM AND RAILINGS AT FRONT OF THE BUILDING. PLUMBING WORK TO BE FILED SEPERATELY. NO WORK AT CELLAR OR SUBSEQUENT FLOORS.
M00480376-P9
01/31/2025
Filed — Alteration CO
FILING FOR CHANGE OF USE AT 1ST FLOOR TO USE GROUP SIX (6). WORK TO INCLUDE GEN. CONSTRUCTION, INSTALLATION OF HANDICAP RAMP, PLATFORM AND RAILINGS AT FRONT OF THE BUILDING. PLUMBING WORK TO BE FILED SEPERATELY. NO WORK AT CELLAR OR SUBSEQUENT FLOORS.
M00480376-P8
01/30/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
asghar Ghodsi
01/30/2025
Special inspection requirement — Energy Code Compliance Inspections
ERIC BERLENT
01/30/2025
Special inspection requirement — Fire-Resistance Rated Construction
ERIC BERLENT
01/30/2025
Special inspection requirement — Lighting controls
ERIC BERLENT
01/30/2025
Special inspection requirement — Interior lighting power
ERIC BERLENT
01/30/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
ERIC BERLENT
01/28/2025
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
01/02/2025
Signed off — Alteration
M01027079-I1
11/15/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
11/12/2024
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
11/08/2024
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
10/31/2024
Special inspection requirement — Tenant Protection Plan Compliance
Robert Germain Jr.
10/31/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Robert Germain Jr.
10/31/2024
Special inspection requirement — HVAC-R and service water heating equipment
Robert Germain Jr.
10/31/2024
Special inspection requirement — HVAC-R and service water heating system controls
Robert Germain Jr.
10/31/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
Robert Germain Jr.
10/30/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
10/29/2024
Filed — Alteration
M01027079-P1
09/30/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Robert Germain Jr.
09/30/2024
Special inspection requirement — Tenant Protection Plan Compliance
09/30/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
Robert Germain Jr.
09/30/2024
Special inspection requirement — HVAC-R and service water heating system controls
Robert Germain Jr.
09/30/2024
Special inspection requirement — HVAC-R and service water heating equipment
Robert Germain Jr.
08/13/2024
Permit issued — Boiler Equipment
M01027079-I1-BE
07/31/2024
Signed off — Alteration
M00975070-I1
07/17/2024
Signed off — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
M01015857-I1
04/12/2024
Filed — Alteration
M01027079-I1
03/25/2024
Signed off — Alteration
Interior renovation of floor 2. No changes to structure or egress.
M00975351-I1
03/22/2024
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
03/19/2024
Special inspection requirement — Fire-Resistance Rated Construction
ERIC BERLENT
03/13/2024
Objection resolved — Addressed
03/11/2024
Objection raised — Accessibility
03/07/2024
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
M01015857-I1
03/07/2024
Permit issued — Supported Scaffold
M01015857-I1-SF
03/06/2024
Permit issued — General Construction
M00480376-I1-GC
03/01/2024
Filed — Alteration
Interior renovation of floor 2. No changes to structure or egress.
M00975351-P1
02/29/2024
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
02/29/2024
Special inspection requirement — Fire-Resistance Rated Construction
ERIC BERLENT
02/20/2024
Permit issued — Mechanical Systems
M00975070-I1-MS
02/08/2024
Filed — Alteration
M00975070-I1
01/22/2024
Permit issued — General Construction
M00975351-I1-GC
12/26/2023
Objection resolved — Addressed
12/26/2023
Objection resolved — Addressed
12/26/2023
Objection resolved — Addressed
12/26/2023
Objection resolved — Addressed
12/26/2023
Objection resolved — Addressed
12/26/2023
Objection resolved — Addressed
12/26/2023
Objection resolved — Addressed
12/22/2023
Objection raised — Other
12/22/2023
Objection raised — Inspections
12/22/2023
Objection raised — Structural
12/22/2023
Objection raised — Scope
Latest 60 of 138 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWBoiler EquipmentSigned-offC C CONTROLLED COMBUSTION08/13/2024
DOB NOWSupported ScaffoldSigned-offRELIABLE ENTERPRISES INC03/07/2024
DOB NOWGeneral ConstructionPermit IssuedTUC-MEN CONTRACTING CORP03/06/2024
DOB NOWMechanical SystemsSigned-offTUC-MEN CONTRACTING CORP02/20/2024
DOB NOWGeneral ConstructionSigned-offTUC-MEN CONTRACTING CORP01/22/2024
DOB NOWGeneral ConstructionPermit IssuedTUC-MEN CONTRACTING CORP10/26/2022
DOB NOWPlumbingSigned-offFERNANDEZ HTG & MECH CORP.12/16/2021
DOB NOWConstruction FenceSigned-offTUC-MEN CONTRACTING CORP11/01/2021
DOB NOWGeneral ConstructionPermit IssuedTUC-MEN CONTRACTING CORP10/29/2021
DOB NOWSupported ScaffoldSigned-offPLATINUM SERVICES NY LLC10/01/2021
DOB NOWSidewalk ShedSigned-offPLATINUM SERVICES NY LLC10/01/2021
DOB NOWGeneral ConstructionPermit IssuedTUC-MEN CONTRACTING CORP08/03/2021
DOB NOWPlumbingSigned-offALL PRO PLBG & HTG INC07/29/2021
DOB NOWConstruction FenceSigned-offTUC-MEN CONTRACTING CORP07/26/2021
DOB NOWPlumbingSigned-offALL PRO PLBG & HTG INC11/17/2020
DOB NOWSidewalk ShedSigned-offROCK GROUP NY CORP09/30/2020
DOB NOWSidewalk ShedSigned-offROCK GROUP NY CORP09/22/2020
DOB NOWSidewalk ShedSigned-offROCK GROUP NY CORP02/07/2020
DOB NOWSupported ScaffoldSigned-offROCK GROUP NY CORP02/07/2020
BISPLISSUEDJ. CAIAZZO PLBG & HTG COR05/01/2025
BISOTISSUEDDOWNTOWN INTERIORS INC04/28/2021
BISOTISSUEDDOWNTOWN INTERIORS INC04/28/2021
BISOTISSUEDDOWNTOWN INTERIORS INC10/20/2020
BISOTISSUEDDOWNTOWN INTERIORS INC10/20/2020
BISOTISSUEDHOBO CONSTRUCTION CO07/09/2020
BISPLISSUEDDELTA-SIGMA MECH CORP08/01/2018
BISOTISSUEDPRO TECH RENOVATIONS INC07/02/2018
BISPLISSUEDANGELO ANDREW INC06/07/2018
BISOTISSUEDARTISTIC DESIGN CORP04/26/2018
BISEQISSUEDGUL & G CONSTR. CORP08/06/2013
BISEQISSUEDGUL & G CONSTR. CORP08/06/2013
BISOTISSUEDDEWALT CONSTRUCTION CO IN03/23/2012
BISMHISSUEDEDGEHILL CONSTRUCTION INC07/13/2011
BISEQISSUEDSKYLINE RESTORATION INC04/15/2011
BISEQISSUEDSKYLINE RESTORATION INC04/14/2011
BISEQISSUEDSKYLINE RESTORATION INC02/17/2011
BISEQISSUEDSKYLINE RESTORATION INC02/16/2011
BISBLISSUEDC C CONTROLLED COMBUSTION04/07/2010
BISPLISSUEDENTERPRISE PLBG & HTG INC03/29/2010
BISOTISSUEDEDGEHILL CONSTRUCTION INC03/23/2010
+ 14 more permits on file
8 projects · most recent 02/21/2024
General Wiring
FiledStatusContractorScope
02/21/2024CompleteA.L. ELECTRICAL CORP.General Wiring
04/25/2023CompleteA.L. ELECTRICAL CORP.General Wiring
12/01/2022CompleteA.L. ELECTRICAL CORP.General Wiring
11/01/2022CompleteA.L. ELECTRICAL CORP.General Wiring
11/08/2020CompleteHIGH IMPACT ELECTRIC CORPGeneral Wiring
01/20/2020CompleteILLUMINOUS ELECTRIC CORP.—
02/25/2019CompleteDEMAND ELECTRIC INC—
06/07/2018CompleteSTELLMANN ELECTRICAL CORPGeneral Wiring
▾Field Inspections (DOB CAP) — 12
DateTypeResultReport
01/28/2025Fail-Final General Construction Non-Directive 14FailView ↗
11/15/2024Pass-Final CND-Occupancy InspectionPassView ↗
11/12/2024Pass-Final Boiler Equipment InspectionPassView ↗
11/08/2024Fail-Final CND-Occupancy InspectionFailView ↗
10/30/2024Pass-Final CND-Occupancy InspectionPassView ↗
03/22/2024Pass-Final General Construction Non-Directive 14PassView ↗
02/29/2024Fail-Final General Construction Non-Directive 14FailView ↗
05/25/2023Pass-Final CND-Occupancy InspectionPassView ↗
04/05/2022Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
03/30/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/25/2022Pass-Final Fence Non-Directive 14PassView ↗
03/07/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 56
DateRequirementInspectorRole
06/18/2025Fire-Resistant Penetrations and JointsERIC BERLENTspecial
06/18/2025Energy Code Compliance InspectionsERIC BERLENTprogress
06/18/2025Interior lighting powerERIC BERLENTenergy_progress
06/18/2025Fire-Resistance Rated ConstructionERIC BERLENTprogress
06/18/2025Lighting controlsERIC BERLENTenergy_progress
06/18/2025Structural Stability – Alterations of existing buildingsasghar Ghodsispecial
01/30/2025Structural Stability – Alterations of existing buildingsasghar Ghodsispecial
01/30/2025Energy Code Compliance InspectionsERIC BERLENTprogress
01/30/2025Fire-Resistance Rated ConstructionERIC BERLENTprogress
01/30/2025Lighting controlsERIC BERLENTenergy_progress
01/30/2025Interior lighting powerERIC BERLENTenergy_progress
01/30/2025Fire-Resistant Penetrations and JointsERIC BERLENTspecial
10/31/2024Tenant Protection Plan ComplianceRobert Germain Jr.special
10/31/2024Fire-Resistant Penetrations and JointsRobert Germain Jr.special
10/31/2024HVAC-R and service water heating equipmentRobert Germain Jr.energy_progress
10/31/2024HVAC-R and service water heating system controlsRobert Germain Jr.energy_progress
10/31/2024HVAC-R and service water piping design and insulationRobert Germain Jr.energy_progress
09/30/2024Fire-Resistant Penetrations and JointsRobert Germain Jr.special
09/30/2024Tenant Protection Plan Compliance—special
09/30/2024HVAC-R and service water piping design and insulationRobert Germain Jr.energy_progress
09/30/2024HVAC-R and service water heating system controlsRobert Germain Jr.energy_progress
09/30/2024HVAC-R and service water heating equipmentRobert Germain Jr.energy_progress
03/19/2024Fire-Resistance Rated ConstructionERIC BERLENTprogress
02/29/2024Fire-Resistance Rated ConstructionERIC BERLENTprogress
06/22/2023Fire-Resistance Rated ConstructionERIC BERLENTprogress
Latest 25 of 56.
▾Documents — 387 on file (BIS + DOB NOW)
▸Plans & Drawings24
▸DOB NOWPlans/Sketch19
09/03/2026M00481230-I1Request digital key ↗
09/03/2026M00480458-P1Request digital key ↗
09/03/2026M00480376-P7Request digital key ↗
Showing 3 of 19 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed2
09/04/2026M00299853-I1Request digital key ↗
08/15/2026M00299853-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Supported Scaffold2
09/04/2026M00299853-I1Request digital key ↗
08/15/2026M00299853-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing1
09/04/2026M00302187-I1Request digital key ↗
▸Applications & Permits72
▸BISPLAN / WORK APPROVAL APPLICATION47
04/29/2025102727391Open ↗
02/25/2025110073447Open ↗
08/14/2024104900608Open ↗
Showing 3 of 47 on file for this type
▸BISWORK PERMIT APPLICATION25
05/02/2025102727391Open ↗
10/20/2020123794974Open ↗
10/20/2020123794974Open ↗
Showing 3 of 25 on file for this type
▸Seals & Professional Certifications108
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION28
11/07/2019123784805Open ↗
05/28/2019123435611Open ↗
05/28/2019123435611Open ↗
Showing 3 of 28 on file for this type
▸DOB NOWProgress Inspector Seal & Signature24
09/01/2026M00480376-P2Open ↗
09/01/2026M00480376-P2Open ↗
09/01/2026M00480376-I1Open ↗
Showing 3 of 24 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature22
09/03/2026M00481230-I1Open ↗
09/03/2026M00480458-I1Open ↗
08/28/2026M00975351-P1Open ↗
Showing 3 of 22 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature15
09/01/2026M00480376-P2Open ↗
09/01/2026M00480376-I1Open ↗
09/01/2026M00480376-I1Open ↗
Showing 3 of 15 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST6
01/10/2018123177169Open ↗
02/22/2012120980670Open ↗
Showing 2 of 6 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM5
02/22/2012120980670Open ↗
Showing 1 of 5 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT3
01/10/2018123177169Open ↗
08/06/2013140100977Open ↗
08/06/2013140100968Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION2
08/06/2013140100977Open ↗
08/06/2013140100968Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
08/06/2013140100977Open ↗
08/06/2013140100968Open ↗
▸BISPC FULL REPORT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Trade Schedules & Equipment12
▸BISSCHEDULE B - PLUMBING7
05/17/2023102727391Open ↗
03/20/2023102727391Open ↗
Showing 2 of 7 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE2
04/19/2018123435611Open ↗
01/10/2018123177169Open ↗
▸Safety & Tenant Protection17
▸DOB NOWStreet Tree Checklist10
08/13/2026M00480376-P4Open ↗
08/13/2026M00480376-P8Open ↗
08/13/2026M00480376-P7Open ↗
Showing 3 of 10 on file for this type
▸BISTenant Protection Plan and Notes4
11/07/2019123784805Open ↗
04/19/2018123435611Open ↗
01/10/2018123177169Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWTenant Protection Plan3
08/13/2026M00299853-I1Open ↗
08/13/2026M00299853-P1Open ↗
08/13/2026M00302187-I1Open ↗
▸Environmental & Asbestos22
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'8
02/22/2012120980670Open ↗
06/27/2011120731501Open ↗
02/22/2012120980670Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report6
08/28/2026M00975351-I1Open ↗
08/28/2026M00975070-I1Open ↗
08/15/2026M00975351-P1Open ↗
Showing 3 of 6 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)5
06/12/2020123794974Open ↗
04/19/2018123435611Open ↗
01/10/2018123177169Open ↗
Showing 3 of 5 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
07/09/2020123784805Open ↗
▸Energy Compliance20
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS8
11/07/2019123784805Open ↗
05/22/2019123435611Open ↗
05/15/2019123435611Open ↗
Showing 3 of 8 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS3
05/15/2019123435611Open ↗
12/26/2018123177169Open ↗
04/09/2013120980670Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
07/24/2020123794974Open ↗
07/20/2020123794974Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)2
03/18/2022123794974Open ↗
02/04/2022123784805Open ↗
▸BISAIR SEALING AND INSULATION - VISUAL1
02/04/2022123784805Open ↗
▸BISLIGHTING IN DWELLING UNITS1
03/18/2022123794974Open ↗
▸BISTECHNICAL REPORT: ENERGY1
06/27/2011120731501Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
08/13/2026M01027079-I1Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026M00480376-I1Open ↗
▸Inspections & Test Reports21
▸BISTECHNICAL REPORT: RESPONSIBILITY16
05/30/2024110023126Open ↗
01/25/2024120293486Open ↗
12/26/2023110145316Open ↗
Showing 3 of 16 on file for this type
▸BIS* FINAL INSPECTION DIRECTIVE 14 OF 19754
05/24/2024110023126Open ↗
02/23/2024104786180Open ↗
12/26/2023110145316Open ↗
Showing 3 of 4 on file for this type
▸BIS* STRUCTURAL STABILITY 1 RCNY:16-011
02/23/2024104786180Open ↗
▸Approvals, Objections & Sign-offs37
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST23
05/12/2025102727391Open ↗
02/25/2025110073447Open ↗
10/01/2024104900608Open ↗
Showing 3 of 23 on file for this type
▸BISADMINISTRATIVE OBJECTIONS11
09/03/2024104900608Open ↗
09/03/2024104900608Open ↗
02/22/2012120980670Open ↗
Showing 3 of 11 on file for this type
▸BISSUPERSEDING LETTER1
05/02/2025102727391Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
04/09/2013120980670Open ↗
▸BISFINAL1
01/25/2024120293486Open ↗
▸Cost, Insurance & Ownership26
▸BISCOST AFFIDAVIT16
07/20/2023110073447Open ↗
11/23/2021123784805Open ↗
06/12/2020123794974Open ↗
Showing 3 of 16 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW310
09/27/2024104900608Open ↗
04/08/2024110023126Open ↗
02/23/2024104786180Open ↗
Showing 3 of 10 on file for this type
▸Filing & Intake Forms25
▸BISEFILING COVER SHEET9
06/01/2020123794974Open ↗
06/01/2020123794974Open ↗
11/07/2019123784805Open ↗
Showing 3 of 9 on file for this type
▸BISADDITIONAL INFORMATION8
09/25/2024104900608Open ↗
08/28/2024104900608Open ↗
06/08/2023102727391Open ↗
Showing 3 of 8 on file for this type
▸BISBOROUGH INTAKE FORM6
05/02/2025102727391Open ↗
04/28/2025102727391Open ↗
05/28/2019123435611Open ↗
Showing 3 of 6 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET2
08/06/2013140100977Open ↗
08/06/2013140100968Open ↗
▸Other Documents3
▸BIS* CHIMNEYS 27-8561
12/26/2023110145316Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
04/27/2018123177169Open ↗
▸BIS* VENT. SYS.-ENGINEER/INSTALLER 27-136,7791
02/23/2024104786180Open ↗