Elevator co-op, conversion from loft/warehouse
130 WEST 26TH STREET
MANHATTAN · BIN 1015023
💬 Discuss this project
1912Year Built
7Stories
D0Building Class
M1-8A/R11Zoning
16,100 sfGross Floor Area
7Units
Rent Stabilized0 Active ViolationsFISP: SAFE
Elevator co-op, conversion from loft/warehouse · Owner of record: 130 W 26th St Housing Development Fu · 2,469 sf lot · 6.52 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingEquipmentGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Floor 7Temporary pipe scaffold installation4p · 1 filing · 3 docs
Floor 6Temporary pipe scaffold installation4p · 1 filing · 3 docs
Floor 5Temporary pipe scaffold installation4p · 1 filing · 3 docs
Floor 4Temporary pipe scaffold installation4p · 1 filing · 3 docs
Floor 3Temporary pipe scaffold installation6p · 3 filings · 12 docs
Floor 2Non-loadbearing partition removal and installation, mechanic31p · 2 filings · 20 docs
Floor 1Temporary pipe scaffold installation8p · 3 filings · 9 docs
CellarReplacement boiler and oil burner11p · 1 filing · 10 docs
Site & exteriorTemporary sidewalk shed installation6p · 2 filings · 6 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
130W26TH St Artists Housing203/21/2026
130 West 2203/21/2026
130 W 26 St Ahdfc203/21/2026
130 W 26th St Housing Development Fu103/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Municipal Building Consultants203/21/2026
Richard Wainer Architect603/21/2026
New York & Company403/21/2026
AE Design Solution403/21/2026
SNR Expediting Design403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Kings Group NYScaffold807/08/2026
Powers Bridging & ScaffoldingScaffold507/08/2026
NY Signature BuildersGeneral Contractor407/08/2026
Regency Heating & Air Conspecialty_contractor303/21/2026
R.C.M. ElectricElectrical103/21/2026
HI-Tech Plumbing & HeatingPlumbing107/08/2026
NY Electric Maintenance & DataElectrical103/21/2026
Up Rite ConstructionGeneral Contractor107/08/2026
Ganic Plumbing & HeatingPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Gregory V. Perotto, P.E947204/05/2023
New York Engineering Associates851201/21/2022
Building Lifecycle
All (163)Filed (11)Permit Issued (15)Signed Off (5)Facade (FISP) (16)Violation (60)Inspection (6)Objection (20)Special Inspection (30)
03/21/2025
Signed off — Alteration
PLUMBING MODIFICATIONS FOR APT. 3 AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
M01037944-I1
03/05/2025
Signed off — Alteration
INTERIOR RENOVATIONS FOR EXISTING BATHROOM AND KITCHEN IN JOINT LIVING-WORK QUARTER APT. 3 ON 3RD FLOOR INCLUDING PARTITIONS AND FINISHES AS PER PLANS FILED HEREWITH. NO CHANGE TO THE UNIT LAYOUT, USE, EGRESS OR OCCUPANCY.
M01037927-I1
02/27/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
11/27/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
11/25/2024
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
10/22/2024
Permit issued — General Construction
M01037927-I1-GC
10/18/2024
Permit issued — Plumbing
M01037944-I1-PL
10/07/2024
Objection resolved — Addressed
06/20/2024
Objection raised — Other
06/20/2024
Objection resolved — Addressed
05/21/2024
Objection raised — Scope
05/21/2024
Objection resolved — Addressed
05/21/2024
Objection raised — Inspections
05/21/2024
Objection resolved — Addressed
05/21/2024
Objection raised — Scope
05/21/2024
Objection resolved — Addressed
05/21/2024
Objection raised — Other
05/21/2024
Objection resolved — Addressed
05/21/2024
Objection raised — Scope
05/21/2024
Objection resolved — Addressed
05/21/2024
Objection raised — Scope
05/21/2024
Objection resolved — Addressed
05/10/2024
Objection raised — Scope
05/07/2024
Filed — Alteration
PLUMBING MODIFICATIONS FOR APT. 3 AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
M01037944-I1
05/07/2024
Filed — Alteration
INTERIOR RENOVATIONS FOR EXISTING BATHROOM AND KITCHEN IN JOINT LIVING-WORK QUARTER APT. 3 ON 3RD FLOOR INCLUDING PARTITIONS AND FINISHES AS PER PLANS FILED HEREWITH. NO CHANGE TO THE UNIT LAYOUT, USE, EGRESS OR OCCUPANCY.
M01037927-I1
04/18/2024
Special inspection requirement — Lighting in dwelling units
Altagracia Martinez
04/18/2024
Special inspection requirement — Final
Altagracia Martinez
04/18/2024
Special inspection requirement — Energy Code Compliance Inspections
Altagracia Martinez
04/24/2023
Signed off — Alteration
MINOR REMOVAL OF NON-LOADBEARING PARTITIONS & INSTALLATION OF NEW NON-LOADBEARING PARTITIONS. ALSO, SOME MECHANICAL WORK IN THIS FILING. PLUMBING WORK TO BE FILED AS A SUBSEQUENT FILING. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00579151-I1
04/20/2023
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
04/17/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
Gregory Perotto
04/17/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Gregory Perotto
04/17/2023
Special inspection requirement — Mechanical Systems
Gregory Perotto
04/17/2023
Special inspection requirement — Heating Systems
Gregory Perotto
04/17/2023
Special inspection requirement — Energy Code Compliance Inspections
Gregory Perotto
04/17/2023
Special inspection requirement — Final
Gregory Perotto
04/17/2023
Special inspection requirement — Fire-Resistance Rated Construction
Gregory Perotto
04/17/2023
Special inspection requirement — Fenestration and door U-factor and product ratings
Gregory Perotto
04/17/2023
Special inspection requirement — Interior lighting power
Gregory Perotto
04/17/2023
Special inspection requirement — Fenestration air leakage
Gregory Perotto
04/17/2023
Special inspection requirement — Lighting controls
Gregory Perotto
04/17/2023
Special inspection requirement — Air barrier - visual inspection
Gregory Perotto
04/05/2023
Filed — Alteration
MINOR REMOVAL OF NON-LOADBEARING PARTITIONS & INSTALLATION OF NEW NON-LOADBEARING PARTITIONS. ALSO, SOME MECHANICAL WORK IN THIS FILING. PLUMBING WORK TO BE FILED AS A SUBSEQUENT FILING. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00579151-P1
04/04/2023
Violation issued (HPD, closed)
C
04/02/2023
Violation issued (HPD, closed)
C
03/26/2023
Special inspection requirement — Heating Systems
Gregory Perotto
03/26/2023
Special inspection requirement — Fire-Resistance Rated Construction
Gregory Perotto
03/26/2023
Special inspection requirement — Final
Gregory Perotto
03/26/2023
Special inspection requirement — Energy Code Compliance Inspections
Gregory Perotto
03/26/2023
Special inspection requirement — Interior lighting power
Gregory Perotto
03/26/2023
Special inspection requirement — Air barrier - visual inspection
Gregory Perotto
03/26/2023
Special inspection requirement — Fenestration air leakage
Gregory Perotto
03/26/2023
Special inspection requirement — Lighting controls
Gregory Perotto
03/26/2023
Special inspection requirement — Fenestration and door U-factor and product ratings
Gregory Perotto
03/26/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
Gregory Perotto
03/26/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Gregory Perotto
03/26/2023
Special inspection requirement — Mechanical Systems
Gregory Perotto
02/28/2023
Signed off — Alteration
MINOR REMOVAL OF NON-LOADBEARING PARTITIONS & INSTALLATION OF NEW NON-LOADBEARING PARTITIONS. ALSO, SOME MECHANICAL WORK IN THIS FILING. PLUMBING WORK TO BE FILED AS A SUBSEQUENT FILING. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00579151-S1
10/10/2022
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
06/28/2022
Permit issued — General Construction
M00579151-I1-GC
Latest 60 of 163 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offUp Rite Construction10/22/2024
DOB NOWPlumbingSigned-offHI-Tech Plumbing & Heating10/18/2024
DOB NOWGeneral ConstructionSigned-offNY Signature Builders06/28/2022
DOB NOWSidewalk ShedPermit IssuedPowers Bridging & Scaffol05/17/2022
DOB NOWPlumbingSigned-offGanic Plumbing & Heating11/08/2021
DOB NOWGeneral ConstructionSigned-offRegency Heating & Air Con10/25/2021
DOB NOWMechanical SystemsSigned-offNY Signature Builders10/18/2021
DOB NOWBoiler EquipmentSigned-offRockway Fuel Oil10/07/2021
DOB NOWSupported ScaffoldPermit IssuedPowers Bridging & Scaffol03/30/2021
DOB NOWSidewalk ShedPermit IssuedKings Group NY10/14/2020
DOB NOWSupported ScaffoldPermit IssuedKings Group NY10/14/2020
DOB NOWSupported ScaffoldPermit IssuedPowers Bridging & Scaffol08/12/2020
DOB NOWSidewalk ShedPermit IssuedPowers Bridging & Scaffol08/12/2020
DOB NOWSupported ScaffoldPermit IssuedKings Group NY12/31/2019
DOB NOWSidewalk ShedPermit IssuedKings Group NY12/30/2019
BISOTISSUEDBulado General Contractor08/13/2020
BISOTISSUEDTishon Contracting Co05/13/2019
BISOTISSUEDMark Contracting NY05/09/2018
BISOTISSUEDHayward Baker08/30/2016
BISOTISSUEDHayward Baker08/23/2016
BISEQISSUEDNew Force Construction02/15/2013
BISEQISSUEDNew Force Construction09/17/2012
BISBLISSUEDFred M. Shcildwachter & Sons08/22/2007
BISOTISSUEDSTJ Contracting03/13/2006
BISOTISSUEDGS Precision Maintenance10/07/2005
BISPLISSUEDA Installation05/27/2005
BISOTISSUEDSquare Foot Solutions07/06/2004
BISPLISSUEDPrime Piping & Heating07/02/2004
BISOTISSUEDRoadhouse Renovatiors05/18/2004
BISOTISSUEDUrban D.C01/26/2001
BISEQISSUEDRockledge Scaffold03/30/2000
BISEQISSUEDRockledge Scaffold12/02/1999
6 projects · most recent 10/22/2024
General Wiring
FiledStatusContractorScope
10/22/2024CompleteCoachmen SolutionsGeneral Wiring
10/28/2022CompleteCresco ElectricalGeneral Wiring
04/21/2022CompleteGemini Electric CoGeneral Wiring
04/21/2022CompleteGemini Electric CoGeneral Wiring
07/28/2020CompleteOptimal Electric—
12/30/2019Permit IssuedWCK Electric—
3 projects · most recent 08/12/2020
Sidewalk Shed Scaffold
FiledStatusContractorScope
08/12/2020Permit IssuedPowers Bridging & ScaffolSidewalk Shed
08/12/2020Permit IssuedPowers Bridging & ScaffolScaffold
12/30/2019Permit IssuedKings Group NYSidewalk Shed
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
02/27/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
11/27/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
11/25/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
04/20/2023Pass-Final General Construction Non-Directive 14PassView ↗
10/10/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/10/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 35
DateRequirementInspectorRole
04/18/2024Lighting in dwelling unitsAltagracia Martinezenergy_progress
04/18/2024FinalAltagracia Martinezprogress
04/18/2024Energy Code Compliance InspectionsAltagracia Martinezprogress
04/17/2023HVAC-R and service water piping design and insulationGregory Perottoenergy_progress
04/17/2023Fire-Resistant Penetrations and JointsGregory Perottospecial
04/17/2023Mechanical SystemsGregory Perottospecial
04/17/2023Heating SystemsGregory Perottospecial
04/17/2023Energy Code Compliance InspectionsGregory Perottoprogress
04/17/2023FinalGregory Perottoprogress
04/17/2023Fire-Resistance Rated ConstructionGregory Perottoprogress
04/17/2023Fenestration and door U-factor and product ratingsGregory Perottoenergy_progress
04/17/2023Interior lighting powerGregory Perottoenergy_progress
04/17/2023Fenestration air leakageGregory Perottoenergy_progress
04/17/2023Lighting controlsGregory Perottoenergy_progress
04/17/2023Air barrier - visual inspectionGregory Perottoenergy_progress
03/26/2023Heating SystemsGregory Perottospecial
03/26/2023Fire-Resistance Rated ConstructionGregory Perottoprogress
03/26/2023FinalGregory Perottoprogress
03/26/2023Energy Code Compliance InspectionsGregory Perottoprogress
03/26/2023Interior lighting powerGregory Perottoenergy_progress
03/26/2023Air barrier - visual inspectionGregory Perottoenergy_progress
03/26/2023Fenestration air leakageGregory Perottoenergy_progress
03/26/2023Lighting controlsGregory Perottoenergy_progress
03/26/2023Fenestration and door U-factor and product ratingsGregory Perottoenergy_progress
03/26/2023HVAC-R and service water piping design and insulationGregory Perottoenergy_progress
Latest 25 of 35.
▾Documents — 132 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch7
09/03/2026M00579151-P1Request digital key ↗
09/03/2026M00585890-I1Request digital key ↗
09/03/2026M00585890-P1Request digital key ↗
Showing 3 of 7 on file for this type
▸DOB NOWPlans/Sketch - Supported Scaffold2
09/05/2026M00288354-I1Request digital key ↗
08/15/2026M00376981-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed2
09/05/2026M00288876-I1Request digital key ↗
09/04/2026M00376980-I1Request digital key ↗
▸Applications & Permits17
▸BISPLAN / WORK APPROVAL APPLICATION10
05/14/2021123902553Open ↗
04/30/2021123902553Open ↗
06/20/2019123902553Open ↗
Showing 3 of 10 on file for this type
▸BISWORK PERMIT APPLICATION7
08/13/2020123902553Open ↗
05/13/2019123862560Open ↗
05/10/2018123444282Open ↗
Showing 3 of 7 on file for this type
▸Seals & Professional Certifications46
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION11
11/12/2019123862560Open ↗
06/17/2019123902553Open ↗
05/16/2019123902553Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature11
09/05/2026M00288354-I1Open ↗
09/04/2026M00376981-I1Open ↗
09/03/2026M00585890-I1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWProgress Inspector Seal & Signature11
09/23/2026M00585890-I1Open ↗
08/28/2026M00579151-I1Open ↗
08/28/2026M00579151-I1Open ↗
Showing 3 of 11 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST5
04/19/2019123862560Open ↗
03/09/2018123444282Open ↗
08/01/2016122838750Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/23/2026M00585890-I1Open ↗
08/28/2026M00579151-I1Open ↗
08/26/2026M00579151-P1Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT3
04/19/2019123862560Open ↗
03/09/2018123444282Open ↗
07/25/2016122838750Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
09/18/2012121378838Open ↗
▸Safety & Tenant Protection8
▸BISTenant Protection Plan and Notes4
05/16/2019123902553Open ↗
04/19/2019123862560Open ↗
03/09/2018123444282Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWTenant Protection Plan4
08/13/2026M00288876-I1Open ↗
08/13/2026M00376980-I1Open ↗
08/13/2026M00288354-I1Open ↗
Showing 3 of 4 on file for this type
▸Environmental & Asbestos9
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
08/27/2026M01037944-I1Open ↗
08/14/2026M01037927-I1Open ↗
08/13/2026M00579151-P1Open ↗
Showing 3 of 5 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)3
04/19/2019123862560Open ↗
03/09/2018123444282Open ↗
04/01/2015122349397Open ↗
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
06/02/2021123902553Open ↗
▸Energy Compliance10
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS5
11/12/2019123862560Open ↗
05/16/2019123902553Open ↗
04/24/2019123862560Open ↗
Showing 3 of 5 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS2
06/02/2021123902553Open ↗
11/12/2019123862560Open ↗
▸DOB NOWEN2: As Built Energy Analysis.2
08/13/2026M00579151-I1Open ↗
08/13/2026M00585890-I1Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
08/13/2026M00585890-I1Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
06/02/2021123902553Open ↗
09/17/2020104081128Open ↗
▸Approvals, Objections & Sign-offs8
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST5
06/02/2021123902553Open ↗
09/17/2020104081128Open ↗
11/12/2019123862560Open ↗
Showing 3 of 5 on file for this type
▸BISADMINISTRATIVE OBJECTIONS1
09/18/2012121378838Open ↗
▸BISSHED LETTER1
02/21/2013121378838Open ↗
▸BISCONSTRUCTION CODE DETERMINATION1
03/06/2017122838750Open ↗
▸Cost, Insurance & Ownership10
▸BISCOST AFFIDAVIT10
06/02/2021123902553Open ↗
09/17/2020104081128Open ↗
11/12/2019123862560Open ↗
Showing 3 of 10 on file for this type
▸Filing & Intake Forms10
▸BISEFILING COVER SHEET6
05/16/2019123902553Open ↗
04/19/2019123862560Open ↗
03/09/2018123444282Open ↗
Showing 3 of 6 on file for this type
▸BISBOROUGH INTAKE FORM3
11/12/2019123862560Open ↗
09/27/2018104221263Open ↗
03/15/2018122838750Open ↗
▸BISADDITIONAL INFORMATION1
05/17/2021123902553Open ↗
▸Other Documents1
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
08/13/2020123902553Open ↗