DOB11/14/2025VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION
DOB12/01/2024FAILURE TO DISPLAY ENERGY EFFICIENCY SCORE AND ENERGY EFFICIENCY GRADE AS PER ADCODE SEC. 28-309.12.3
ECB07/03/2024A. C. 27-929.1, FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS AND FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL IN AN OFFICE BUILDING 100 FEET OR MOR$10K due
ECB04/14/202327-929.1 FAILURE TO COMPLETE INSTALLATION OF FULL SYSTEM OF AUTOMATIC SPRINKLERS & FILE FINAL SPRINKLER REPORT PREPARED BY REGISTERED DESIGNPROFESSIONAL IN OFFICE BLDG 100 FT OR MORE IN HEIGHT IN EXISTENCE ON$6K due
ECB12/22/2022FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 9A REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#901864.REMEDY:SUBMIT ACCEPTABLE REQUIRE$6K due
DOB02/22/2022FAILED TO FILE FISP CYCLE 9A TECHNICAL REPORT BY 02/21/2022
ECB12/17/202127-929.1 FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS AND FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL IN AN OFFICE BUILDING 100 FEET OR MORE IN HE$3K due
DOB12/01/2021FAILURE TO DISPLAY ENERGY EFFICIENCY SCORE AND ENERGY EFFICIENCY GRADE AS PER ADCODE SEC. 28-309.12.3
DOB04/29/2021FAILURE TO DISPLAY ENERGY EFFICIENCY SCORE AND ENERGY EFFICIENCY GRADE AS PER ADCODE SEC. 28-309.12.3
ECB11/24/202027-929.1,FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS AND FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL IN AN OFFICE BUILDING 100 FEET OR MORE IN$6K due
ECB11/25/2019FAILURE TO MAINTAIN BUILDING EXTERIOR WALLS FACADE AND APPURTENANCES.AT THE TIME OF INSPECTION EXPOSURE 1 PILLING OF PAINT AT 12 FLOOR LINTEL.EXPOSURE 2:DEMAGED MORTAR JOINTS.EXPOSURE 3:MISSING BRICKS AT ENTRAN$6K due
DOB11/12/2019FAILED TO FILE FINAL SPRINKLER REPORT BY JULY 1, 2019
DOB09/06/2019VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST
DOB09/06/2019VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST
DOB05/02/2019FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4
DOB01/26/2018VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2016 CAT 1 INSP/TST
DOB01/26/2018VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2016 CAT 1 INSP/TST
DOB01/03/2017VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2015 CAT 1 INSP/TST
DOB01/03/2017VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2015 CAT 1 INSP/TST
ECB04/16/202127-929.1 FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS AND FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL IN AN OFFICE BUILDING 100 FEET OR MORE IN HENothing owed — awaiting certificate of correction
ECB04/18/201121M07,22L10. FAILURE TO COMPLY W/THE COMMISSIONER'S ORDER TO FILE A C/C W/THE DOB. RESPONDENT FILED TO COMPLY W/THE COMMISSIONER'S ORDER TO CORRECT THE VIOLATING CONDITIONS AND FILED A C/C PURSUANT TO SECTIONNothing owed — awaiting certificate of correction
ECB04/18/201121-M-07/22-L-10-RESPONDENT FILE A COFC ON JAN 25-2011 FOR NOV#38214290H.AN INSPECTION MADE ON APRIL 18, 2011RESULTED IN THE ISSUANCE OF NOV#38216079L.THIS INSPECTION FOUND CONDITIONS W/THE RESPONDENT DESCRIBEDNothing owed — awaiting certificate of correction