Over six families without stores
1309 FINDLAY AVENUE
BRONX · Mount Eden-Claremont (West) · BIN 2007212
💬 Discuss this project
1920Year Built
2Stories
C1Building Class
R7-1Zoning
12,335 sfGross Floor Area
25Units
Rent Stabilized0 Open ViolationsFDNY Report ↗
Over six families without stores · Owner of record: 1309 FINDLAY AVE LLC · 3,742 sf lot · 3.3 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionCivilGeneralOther
Roof80p · 2 filings · 20 docs
Penthouse90p · 1 filing · 20 docs
Floor 489p · 1 filing · 20 docs
Floor 385p · 1 filing · 20 docs
Floor 288p · 1 filing · 20 docs
Floor 186p · 1 filing · 20 docs
Cellar97p · 2 filings · 20 docs
Site & exterior121p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NY CREATIVE DEVELOPERS5307/08/2026
OWNERS REP903/22/2026
1309 FINDLAY AVE LLC103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/13/2022$1.3M—Private party → 1309 FINDLAY AVE LLC$107/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ADB ASSOCIATES502/26/2024
VASILIOS ARTEMIOU PE611/15/2023
FL&M ENGINEERING DESIGN &INSPECTION206/05/2023
R & O ENGINEERING605/08/2023
AR ARCHITECT P.C101/03/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NYC DESIGN FILE1703/21/2026
GREEN STUDIO403/21/2026
ADAC CONSTRUCTION203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MJH CONSTRUCTION CORPGeneral Contractor1607/08/2026
GWT ENTERPRISES INCGeneral Contractor303/21/2026
MANHATTAN D ENTERPRISESGeneral Contractor303/21/2026
PRIME PIPING & HEATING INFire Protection107/08/2026
AQUA PLUMBING & HTNG CORPPlumbing107/08/2026
PRIME PIPING & HEATING INPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP56161302/26/2024
REGIONAL TESTING CORP.394512/19/2022
Building Lifecycle
All (190)Filed (20)Permit Issued (16)Signed Off (8)Violation (23)Inspection (13)Objection (80)Special Inspection (30)
07/18/2026
Violation issued (HPD, closed)
B
03/22/2026
Violation issued (HPD, closed)
C
11/17/2025
Violation issued (HPD, closed)
I
04/18/2024
Violation issued (HPD, closed)
A
02/29/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
FAHAD FATEH
02/29/2024
Special inspection requirement — Lighting in dwelling units
FAHAD FATEH
02/29/2024
Special inspection requirement — Lighting controls
FAHAD FATEH
02/29/2024
Special inspection requirement — Electric vehicle service equipment requirements
FAHAD FATEH
02/29/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
FAHAD FATEH
02/29/2024
Special inspection requirement — Protection of exposed foundation insulation
FAHAD FATEH
02/29/2024
Special inspection requirement — Air barrier - visual inspection
FAHAD FATEH
02/29/2024
Special inspection requirement — Fenestration areas
FAHAD FATEH
02/29/2024
Special inspection requirement — Maintenance information
FAHAD FATEH
02/29/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
FAHAD FATEH
02/29/2024
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
FAHAD FATEH
02/29/2024
Special inspection requirement — Subgrade Inspections
FAHAD FATEH
02/29/2024
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
FAHAD FATEH
02/29/2024
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
FAHAD FATEH
02/29/2024
Special inspection requirement — Masonry
FAHAD FATEH
02/29/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
02/29/2024
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
02/29/2024
Special inspection requirement — Fire-Resistance Rated Construction
FAHAD FATEH
02/29/2024
Special inspection requirement — Interior lighting power
FAHAD FATEH
02/29/2024
Special inspection requirement — Exterior lighting power
FAHAD FATEH
02/29/2024
Special inspection requirement — Fenestration air leakage
FAHAD FATEH
02/29/2024
Special inspection requirement — Insulation placement and R values
FAHAD FATEH
02/26/2024
Filed — ALT-CO - New Building with Existing Elements to Remain
PROPOSED VERTICAL AND HORIZONTAL ENLARGEMENT CONVERTING EXISTING 2 STORY & CELLAR, 2 UNIT,INTO A 4 STORY + PENTHOUSE, 25 UNIT, RESIDENTIAL BUILDING.
X00685306-A2
12/20/2023
Signed off — ALT-CO - New Building with Existing Elements to Remain
PROPOSED VERTICAL AND HORIZONTAL ENLARGEMENT CONVERTING EXISTING 2 STORY & CELLAR, 2 UNIT,INTO A 4 STORY + PENTHOUSE, 25 UNIT, RESIDENTIAL BUILDING.
X00685306-S3
12/19/2023
Inspection — Pass-Final PL Permit Withdrawal
Pass
View inspection ↗
12/18/2023
Special inspection requirement — HVAC-R and service water heating equipment
FAHAD FATEH
12/18/2023
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
12/18/2023
Special inspection requirement — HVAC-R and service water heating system controls
FAHAD FATEH
12/18/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
12/18/2023
Special inspection requirement — Mechanical Systems
FAHAD FATEH
12/18/2023
Special inspection requirement — Heating Systems
FAHAD FATEH
12/18/2023
Special inspection requirement — Final
FAHAD FATEH
12/18/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
FAHAD FATEH
12/14/2023
Objection resolved — Addressed
12/11/2023
Signed off — ALT-CO - New Building with Existing Elements to Remain
PROPOSED VERTICAL AND HORIZONTAL ENLARGEMENT CONVERTING EXISTING 2 STORY & CELLAR, 2 UNIT,INTO A 4 STORY + PENTHOUSE, 25 UNIT, RESIDENTIAL BUILDING.
X00685306-S4
12/11/2023
Inspection — Fail-Final PL Permit Withdrawal
Fail
View inspection ↗
11/17/2023
Objection raised — Admin
11/15/2023
Filed — ALT-CO - New Building with Existing Elements to Remain
PROPOSED VERTICAL AND HORIZONTAL ENLARGEMENT CONVERTING EXISTING 2 STORY & CELLAR, 2 UNIT,INTO A 4 STORY + PENTHOUSE, 25 UNIT, RESIDENTIAL BUILDING.
X00685306-A1
11/14/2023
Signed off — ALT-CO - New Building with Existing Elements to Remain
PROPOSED VERTICAL AND HORIZONTAL ENLARGEMENT CONVERTING EXISTING 2 STORY & CELLAR, 2 UNIT,INTO A 4 STORY + PENTHOUSE, 25 UNIT, RESIDENTIAL BUILDING.
X00685306-S1
11/14/2023
Filed — ALT-CO - New Building with Existing Elements to Remain
PROPOSED VERTICAL AND HORIZONTAL ENLARGEMENT CONVERTING EXISTING 2 STORY & CELLAR, 2 UNIT,INTO A 4 STORY + PENTHOUSE, 25 UNIT, RESIDENTIAL BUILDING.
X00685306-P9
11/14/2023
Permit issued — Foundation
X00685306-S1-FO
11/03/2023
Signed off — ALT-CO - New Building with Existing Elements to Remain
PROPOSED VERTICAL AND HORIZONTAL ENLARGEMENT CONVERTING EXISTING 2 STORY & CELLAR, 2 UNIT,INTO A 4 STORY + PENTHOUSE, 25 UNIT, RESIDENTIAL BUILDING.
X00685306-S2
10/30/2023
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
10/26/2023
Signed off — ALT-CO - New Building with Existing Elements to Remain
PROPOSED VERTICAL AND HORIZONTAL ENLARGEMENT CONVERTING EXISTING 2 STORY & CELLAR, 2 UNIT,INTO A 4 STORY + PENTHOUSE, 25 UNIT, RESIDENTIAL BUILDING.
X00685306-S5
10/26/2023
Signed off — ALT-CO - New Building with Existing Elements to Remain
PROPOSED VERTICAL AND HORIZONTAL ENLARGEMENT CONVERTING EXISTING 2 STORY & CELLAR, 2 UNIT,INTO A 4 STORY + PENTHOUSE, 25 UNIT, RESIDENTIAL BUILDING.
X00685306-S6
10/26/2023
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
10/25/2023
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
10/12/2023
Signed off — Alteration
X00861130-I1
10/12/2023
Signed off — Alteration
INSTALLATION OF ROOF PROTECTION AS PER PLANS. ROOF PROTECTION SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
X00882272-I1
08/17/2023
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
08/15/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
06/08/2023
Permit issued — General Construction
X00685306-I1-GC
06/06/2023
Permit issued — Protection and Mechanical Methods
X00882272-I1-PMM
06/05/2023
Filed — Alteration
INSTALLATION OF ROOF PROTECTION AS PER PLANS. ROOF PROTECTION SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
X00882272-I1
05/25/2023
Permit issued — Construction Fence
X00685306-S5-FN
05/08/2023
Filed — ALT-CO - New Building with Existing Elements to Remain
PROPOSED VERTICAL AND HORIZONTAL ENLARGEMENT CONVERTING EXISTING 2 STORY & CELLAR, 2 UNIT,INTO A 4 STORY + PENTHOUSE, 25 UNIT, RESIDENTIAL BUILDING.
X00685306-P8
Latest 60 of 190 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWFoundationPermit IssuedMJH CONSTRUCTION CORP11/14/2023
DOB NOWGeneral ConstructionPermit IssuedMJH CONSTRUCTION CORP06/08/2023
DOB NOWProtection and Mechanical MethodsSigned-offGWT ENTERPRISES INC06/06/2023
DOB NOWConstruction FenceSigned-offMJH CONSTRUCTION CORP05/25/2023
DOB NOWSidewalk ShedSigned-offMANHATTAN D ENTERPRISES04/21/2023
DOB NOWPlumbingSigned-offPRIME PIPING & HEATING IN03/28/2023
DOB NOWPlumbingSigned-offA M B MECHANICAL INC03/28/2023
DOB NOWSupport of ExcavationSigned-offMJH CONSTRUCTION CORP03/20/2023
DOB NOWGeneral ConstructionPermit IssuedMJH CONSTRUCTION CORP01/31/2023
DOB NOWStructuralSigned-offMJH CONSTRUCTION CORP01/30/2023
DOB NOWGeneral ConstructionPermit IssuedMJH CONSTRUCTION CORP01/25/2023
DOB NOWMechanical SystemsSigned-offMJH CONSTRUCTION CORP01/19/2023
DOB NOWGeneral ConstructionPermit IssuedMJH CONSTRUCTION CORP06/08/2022
DOB NOWConstruction FenceSigned-offMJH CONSTRUCTION CORP05/27/2022
DOB NOWFoundationPermit IssuedMJH CONSTRUCTION CORP05/27/2022
DOB NOWPlumbingPermit IssuedAQUA PLUMBING & HTNG CORP04/09/2022
1 project · most recent 02/26/2024
Air Conditioning Systems Associated Ducts and Piping Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
02/26/2024Permit IssuedMJH CONSTRUCTION CORPAir Conditioning Systems, Associated Ducts and Piping, Heating Systems, Ventilation Systems
Cooling
Amana DHP093 7,000 BTU · Ptac ×28
DHP153 14,100 BTU · Ptac ×26
Heating
Amana DHP093 6,200 BTU · Ptac ×28
DHP153 13,400 BTU · Ptac ×26
Ventilation
Nutone AEN110 50 CFM · Exhaust Fan ×38
QTXEN150 100 CFM · Exhaust Fan ×38
Ducts & Piping
Masterflow ducts Ductwork
1 project · most recent 02/26/2024
Sprinkler System
FiledStatusContractorScope
02/26/2024Signed-offPRIME PIPING & HEATING INSprinkler System
1 project · most recent 02/26/2024
Gas Storm Water/Sanitary
FiledStatusContractorScope
02/26/2024Signed-offA M B MECHANICAL INCGas, Storm, Water/Sanitary
3 projects · most recent 11/16/2023
General Wiring
FiledStatusContractorScope
11/16/2023CompleteS&R ELECTRICAL & MECHANICGeneral Wiring
05/03/2023CompleteS&R ELECTRICAL & MECHANIC—
04/24/2023CompleteSOLAS ELECTRICAL CORP—
1 project · most recent 02/26/2024
Concrete
FiledStatusContractorScope
02/26/2024Permit IssuedMJH CONSTRUCTION CORPConcrete
1 project · most recent 02/26/2024
Fence
FiledStatusContractorScope
02/26/2024Permit IssuedMJH CONSTRUCTION CORPFence
▾Field Inspections (DOB CAP) — 13
DateTypeResultReport
12/19/2023Pass-Final PL Permit WithdrawalPassView ↗
12/11/2023Fail-Final PL Permit WithdrawalFailView ↗
10/30/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
10/26/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
10/25/2023Pass-Final CND-Occupancy InspectionPassView ↗
08/17/2023Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
08/15/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/26/2023Pass-Final House ConnectionPassView ↗
04/03/2023Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
04/03/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
08/12/2022Certified Gas-Gas-Piping-RoughingCertifiedView ↗
08/12/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/12/2022Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 145
DateRequirementInspectorRole
02/29/2024Insulation placement and R valuesFAHAD FATEHenergy_progress
02/29/2024Lighting in dwelling unitsFAHAD FATEHenergy_progress
02/29/2024Protection of exposed foundation insulationFAHAD FATEHenergy_progress
02/29/2024HVAC-R and service water piping design and insulationFAHAD FATEHenergy_progress
02/29/2024Fenestration and door U-factor and product ratingsFAHAD FATEHenergy_progress
02/29/2024Electric vehicle service equipment requirementsFAHAD FATEHenergy_progress
02/29/2024Maintenance informationFAHAD FATEHenergy_progress
02/29/2024Fenestration areasFAHAD FATEHenergy_progress
02/29/2024Air barrier - visual inspectionFAHAD FATEHenergy_progress
02/29/2024Lighting controlsFAHAD FATEHenergy_progress
02/29/2024Structural Stability – Alterations of existing buildingsFAHAD FATEHspecial
02/29/2024Subsurface Investigations (Borings/Test Pits)FAHAD FATEHspecial
02/29/2024Subgrade InspectionsFAHAD FATEHspecial
02/29/2024Excavations - Sheeting, Shoring, and BracingFAHAD FATEHspecial
02/29/2024Exterior Insulation and Finish Systems (EIFS)FAHAD FATEHspecial
02/29/2024MasonryFAHAD FATEHspecial
02/29/2024Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
02/29/2024Energy Code Compliance InspectionsFAHAD FATEHprogress
02/29/2024Fire-Resistance Rated ConstructionFAHAD FATEHprogress
02/29/2024Interior lighting powerFAHAD FATEHenergy_progress
02/29/2024Exterior lighting powerFAHAD FATEHenergy_progress
02/29/2024Fenestration air leakageFAHAD FATEHenergy_progress
12/18/2023HVAC-R and service water piping design and insulationFAHAD FATEHenergy_progress
12/18/2023HVAC-R and service water heating equipmentFAHAD FATEHenergy_progress
12/18/2023Energy Code Compliance InspectionsFAHAD FATEHprogress
Latest 25 of 145.
▾Documents — 217 on file (BIS + DOB NOW)
▸Plans & Drawings20
▸DOB NOWPlans/Sketch20
08/24/2026X00655600-I1Request digital key ↗
08/23/2026X00685306-P5Request digital key ↗
08/23/2026X00685306-P3Request digital key ↗
Showing 3 of 20 on file for this type
▸Zoning, Tax Lot & Property Records9
▸DOB NOWZD1: DOB Zoning Diagram4
08/13/2026X00685306-P2Open ↗
08/13/2026X00685306-I1Open ↗
08/13/2026X00685306-P1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWZoning Exhibit form (1-5)4
08/13/2026X00685306-P2Open ↗
08/13/2026X00685306-I1Open ↗
08/13/2026X00685306-P1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026X00685306-I1Open ↗
▸Seals & Professional Certifications128
▸DOB NOWProgress Inspector Seal & Signature66
09/01/2026X00685306-A1Open ↗
09/01/2026X00685306-A1Open ↗
09/01/2026X00685306-P2Open ↗
Showing 3 of 66 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature42
09/01/2026X00685306-A1Open ↗
09/01/2026X00685306-I1Open ↗
09/01/2026X00685306-I1Open ↗
Showing 3 of 42 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature20
08/24/2026X00655600-I1Open ↗
08/23/2026X00685306-P2Open ↗
08/23/2026X00685306-S2Open ↗
Showing 3 of 20 on file for this type
▸Trade Schedules & Equipment4
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸Safety & Tenant Protection6
▸DOB NOWStreet Tree Checklist4
08/13/2026X00685306-P2Open ↗
08/13/2026X00685306-A2Open ↗
08/13/2026X00685306-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWStreet Trees Site Plan1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWStreet Tree Sign Off1
08/13/2026X00685306-I1Open ↗
▸Environmental & Asbestos14
▸DOB NOWDEP ACP-5: Asbestos Assessment Report14
08/24/2026X00655600-I1Open ↗
08/23/2026X00685306-P1Open ↗
08/23/2026X00685306-P8Open ↗
Showing 3 of 14 on file for this type
▸Energy Compliance3
▸DOB NOWPreliminary Commissioning Report Certification2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWEN2: As Built Energy Analysis1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Inspections & Test Reports12
▸DOB NOWSOIL REPORT7
08/13/2026X00685306-A2Open ↗
08/13/2026X00685306-P1Open ↗
08/13/2026X00685306-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWTR4 Test Report and Plot Diagram3
08/13/2026X00685306-S6Open ↗
08/13/2026X00685306-I1Open ↗
08/13/2026X00685306-S1Open ↗
▸DOB NOWTR4 Plot Diagram2
08/13/2026X00685306-I1Open ↗
08/13/2026X00685306-S1Open ↗
▸Other Documents21
▸DOB NOWPlot Diagram6
08/13/2026X00685306-A2Open ↗
08/13/2026X00685306-P2Open ↗
08/13/2026X00685306-P3Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸DOB NOWSite Survey: Initial4
08/13/2026X00685306-P2Open ↗
08/13/2026X00685306-P1Open ↗
08/13/2026X00685306-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProperty Ownership Certification4
08/23/2026X00685306-P1Open ↗
08/23/2026X00685306-A2Open ↗
08/15/2026X00685306-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProject Specific General Liability (PGL1)1
08/13/2026X00685306-I1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026X00685306-S6Open ↗
▸DOB NOWFinal Survey1
08/13/2026X00685306-I1Open ↗