0Year Built
—Stories
D6Building Class
C4-2Zoning
0 sfGross Floor Area
163Units
2 Active Violations 1 unresolved · 1 paperwork only ▸
Elevator apt, fireproof with stores · Owner of record: Flushing Point Property · 44,307 sf lot · 0 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentCivilGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
Whole building & multi-floor projectsFlushing Point Holding, LLCUnder Construction13 filings
RoofDoria INC1 filing
Floor 20Unit PH
Floor 19
Floor 18
Floor 17
Floor 16
Floor 15
Floor 14
Floor 13
Floor 12
Floor 11
Floor 10
Floor 9
Floor 8
Floor 7
Floor 6
Floor 5
Floor 4Unit 460
Floor 3
Floor 2Proposed partitionsUnder Construction1 filing · 2 docs
Floor 1Flushing Point Property, LLCUnder Construction4 filings · 2 docs
CellarFlushing PointUnder Construction3p · 9 filings
Site & exteriorFlushing Point Property. LLCUnder Construction6 filings · 2 docs
Filed — no permit issuedSite-specific enclosure for property protection1 filing · 2 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Flushing Point Holding15307/01/2026
Jade Century Properties304/09/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
10/21/2025$32.0M—— → —— not available
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
KZ Engineering509/24/2026
MEP Green Design & Builders507/08/2026
Lombardo Professional Engineering206/16/2026
Nexus Engineer206/16/2026
Patuxent Engineering206/02/2026
Key Civil Engineering1112/06/2023
087007108/27/2023
Skyline Rigging206/28/2023
Ashraf303/06/2023
Tohfaz Uddin PE506/01/2022
CNY Engineering509/11/2020
HRM Engineering Services307/06/2018
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JMT Expediting403/21/2026
Synergy Building Consultants303/21/2026
KD Designs503/21/2026
Platinum Services NY403/21/2026
BMB Building Consulting203/21/2026
Nexus-NYC Construction103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MPS Plumbing & HeatingFire Protection1708/25/2026
Platinum Services NYScaffold907/01/2026
Efin ManagementScaffold609/18/2026
MPS Plumbing & HeatingPlumbing407/01/2026
Milestone ConstructionGeneral Contractor407/01/2026
Republic Scaffold & HoistScaffold406/28/2026
LG Elite PlumbingPlumbing207/01/2026
Efin ManagementGeneral Contractor209/02/2026
Mes ConstructionPlumbing207/01/2026
DoriaScaffold204/09/2026
Rightway ElectricalElectrical103/22/2026
CL ElectricalElectrical103/21/2026
Nash Electric ServicesElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Times Buildings Engineering710907/08/2026
Skyline Rigging7880206/28/2023
Twin Peaks317104/11/2022
Quality Control Laborator406112/04/2017
Building Lifecycle
All (234)Filed (46)Permit Issued (50)Signed Off (5)Violation (35)Inspection (20)Objection (48)Special Inspection (30)
09/24/2026
Filed — Alteration
PROPOSED SITE-SPECIFIC ENGINEERED ENCLOSURE SYSTEM (SSEES) AT EAST-FACING BALCONIES OF ADJACENT NORTH & SOUTH RESIDENTIALTOWERS DURING NEW BUILDING CONSTRUCTION ALTERNATE ADJOINING PROPERTY PROTECTION PURSUANT TO BC 3309.15.
Q01457916-I1
09/23/2026
Special inspection requirement — Post-installed Anchors
09/17/2026
Permit issued — Protection and Mechanical Methods
Q01442660-I1-PMM
09/01/2026
Permit issued — Mechanical Systems
Q00279548-I1-MS
08/24/2026
Permit issued — Standpipe
Q01394823-I1-EW-SD
08/24/2026
Permit issued — Standpipe
Q01394823-I1-EW-SP
08/20/2026
Filed — Alteration
Proposed temporary installation of contractor sheds/ shanties at 1st & 2nd floor as per BC 3303.16 to be used as temporary offices during construction of New Building filed under 421405642. No change in use, egress and/or occupancy with this application.
Q01442660-I1
08/18/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
08/03/2026
Violation issued (ECB, closed)
Unknown
08/03/2026
Inspection — Certified StandPipe - SD - Alarm Sys 64/09 - Finish
Certified
View inspection ↗
08/03/2026
Inspection — Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet)
Certified
View inspection ↗
07/31/2026
Permit issued — Standpipe
Q01380117-I1-EW-SD
07/30/2026
Violation issued (ECB, closed)
Unknown
07/30/2026
Violation issued (ECB, open)
Construction
07/30/2026
Violation issued (ECB, closed)
Construction
07/30/2026
Violation issued (ECB, open)
Construction
07/22/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
ZHUANG MIAO
07/22/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
ZHUANG MIAO
07/15/2026
Objection resolved — Addressed
07/14/2026
Objection resolved — Addressed
07/14/2026
Objection resolved — Addressed
07/14/2026
Objection resolved — Addressed
07/14/2026
Objection resolved — Addressed
07/14/2026
Objection resolved — Addressed
07/14/2026
Objection resolved — Addressed
07/14/2026
Objection resolved — Addressed
07/14/2026
Special inspection requirement — Post-installed Anchors
RUCI LIN
07/14/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
RUCI LIN
07/08/2026
Filed — Alteration
INSTALL NEW PLUMBING SYSTEM FOR NEW COMMERCIAL HOTEL BUILDING IN CONJUNTION WITH NB #421405642.
Q00218052-P2
06/30/2026
Objection raised — Other
06/29/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
ZHUANG MIAO
06/29/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
ZHUANG MIAO
06/29/2026
Special inspection requirement — Lowest Floor Elevation
06/23/2026
Permit issued — Plumbing
Q00218052-I1-PL
06/17/2026
Permit issued — Protection and Mechanical Methods
Q01417882-I1-PMM
06/16/2026
Filed — Alteration
Application for the installation and use of mini-crane as per plans filed herein. No change in egress, use, or occupancy.
Q01417882-I1
06/16/2026
Filed — Alteration
Application for the installation and use of mini-crane as per plans filed herein. No change in egress, use, or occupancy.
Q01412197-I1
06/16/2026
Filed — Alteration
Temporary installation of construction office shanty. No change in use, egress and/or occupancy.
Q01416345-I1
06/16/2026
Permit issued — Protection and Mechanical Methods
Q01412197-I1-PMM
06/08/2026
Objection raised — Fire_Protection
06/08/2026
Objection raised — Inspections
06/08/2026
Objection raised — Admin
06/08/2026
Objection raised — Admin
06/08/2026
Objection raised — Inspections
06/08/2026
Objection raised — Structural
06/08/2026
Objection raised — Structural
06/08/2026
Objection raised — Fire_Protection
06/08/2026
Objection raised — Structural
06/08/2026
Objection resolved — Addressed
06/02/2026
Filed — Alteration
INSTALLATION OF SINGLE PERSONNEL MATERIAL HOIST IN ACCORDANCE WITH NYCC 2022 CHAPTER 33 BUILDING CODE. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
Q01382858-P1
05/29/2026
Violation issued (ECB, closed)
Construction
05/20/2026
Filed — Alteration
Q01394823-I1
05/15/2026
Objection raised — Other
04/29/2026
Special inspection requirement — Standpipe Systems
RUCI LIN
04/29/2026
Special inspection requirement — Sprinkler Systems
RUCI LIN
04/15/2026
Filed — Alteration
INSTALLATION OF SINGLE PERSONNEL MATERIAL HOIST IN ACCORDANCE WITH NYCC 2022 CHAPTER 33 BUILDING CODE. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
Q01382858-I1
04/15/2026
Permit issued — Protection and Mechanical Methods
Q01382858-I1-PMM
04/01/2026
Filed — Alteration
HEREBY FILING FOR NEW TEMPORARY STANDPIPE ALARM SYSTEM AS PER LOCAL LAW 63&64 OF 2009. THIS APPLICATION IS FILED IN CONJUNCTION WITH NB APPLICATION# 421405642
Q01380117-I1
03/30/2026
Special inspection requirement — Standpipe Systems
RUCI LIN
03/17/2026
Violation issued (ECB, closed)
Construction
Latest 60 of 234 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWProtection and Mechanical MethodsPermit IssuedEfin Management09/17/2026
DOB NOWMechanical SystemsPermit IssuedEfin Management09/01/2026
DOB NOWStandpipePermit IssuedMPS Plumbing & Heating08/24/2026
DOB NOWSprinklersPermit IssuedMPS Plumbing & Heating08/24/2026
DOB NOWStandpipePermit IssuedMPS Plumbing & Heating07/31/2026
DOB NOWPlumbingPermit IssuedMPS Plumbing & Heating06/23/2026
DOB NOWProtection and Mechanical MethodsPermit IssuedEfin Management06/17/2026
DOB NOWProtection and Mechanical MethodsPermit IssuedEfin Management06/16/2026
DOB NOWProtection and Mechanical MethodsPermit IssuedRepublic Scaffold & Hoist04/15/2026
DOB NOWConstruction FencePermit IssuedEfin Management02/09/2026
DOB NOWGeneral ConstructionSigned-offEfin Management01/07/2026
DOB NOWConstruction FencePermit IssuedEfin Management01/07/2026
DOB NOWStandpipePermit IssuedMPS Plumbing & Heating12/08/2025
DOB NOWConstruction FencePermit IssuedEfin Management11/21/2025
DOB NOWSidewalk ShedPermit IssuedRepublic Scaffold & Hoist11/05/2025
DOB NOWStandpipePermit IssuedMPS Plumbing & Heating12/10/2024
DOB NOWPlumbingPermit IssuedMes Construction07/18/2024
DOB NOWStructuralSigned-offAgostin Preni04/05/2024
DOB NOWGeneral ConstructionSigned-offAgostin Preni12/21/2023
DOB NOWCurb CutSigned-offAgostin Preni12/14/2023
DOB NOWStandpipePermit IssuedMPS Plumbing & Heating12/04/2023
DOB NOWStandpipeSigned-offMPS Plumbing & Heating12/04/2023
DOB NOWStandpipeSigned-offMPS Plumbing & Heating12/04/2023
DOB NOWPlumbingPermit IssuedLG Elite Plumbing11/15/2023
DOB NOWSidewalk ShedPermit IssuedPlatinum Services NY09/28/2023
DOB NOWProtection and Mechanical MethodsPermit IssuedDoria08/04/2023
DOB NOWPlumbingPermit IssuedMes Construction07/17/2023
DOB NOWStructuralSigned-offAgostin Preni03/20/2023
DOB NOWStandpipeSigned-offMPS Plumbing & Heating12/08/2022
DOB NOWStandpipeSigned-offMPS Plumbing & Heating12/08/2022
DOB NOWStandpipePermit IssuedMPS Plumbing & Heating12/07/2022
DOB NOWProtection and Mechanical MethodsSigned-offPlatinum Services NY11/09/2022
DOB NOWProtection and Mechanical MethodsSigned-offPlatinum Services NY11/09/2022
DOB NOWProtection and Mechanical MethodsSigned-offPlatinum Services NY10/03/2022
DOB NOWProtection and Mechanical MethodsSigned-offPlatinum Services NY10/03/2022
DOB NOWSidewalk ShedPermit IssuedPlatinum Services NY10/03/2022
DOB NOWProtection and Mechanical MethodsPermit IssuedDoria08/30/2022
DOB NOWPlumbingPermit IssuedLG Elite Plumbing07/05/2022
DOB NOWPlumbingSigned-offMPS Plumbing & Heating02/03/2022
DOB NOWPlumbingSigned-offMPS Plumbing & Heating02/03/2022
+ 38 more permits on file
2 projects · most recent 01/20/2020
Air Conditioning Systems Heating Systems Cooling Towers Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
01/20/2020——Air Conditioning Systems, Heating Systems—
01/07/2020Permit IssuedEfin ManagementAir Conditioning Systems, Cooling Towers, Ventilation Systems
Cooling
Daikin ×38
Cooling Tower
1 project · most recent 04/01/2026
FiledStatusContractorScope
04/01/2026Permit IssuedMPS Plumbing & Heating1 outlets
4 projects · most recent 07/08/2026
Water/Sanitary Gas Storm
FiledStatusContractorScope
07/08/2026Permit IssuedMPS Plumbing & HeatingGas, Storm, Water/Sanitary
04/01/2026———
08/11/2023Permit IssuedLG Elite PlumbingGas, Storm, Water/Sanitary
09/15/2022Permit IssuedMes ConstructionWater/Sanitary
17 projects · most recent 09/03/2026
General Wiring
FiledStatusContractorScope
09/03/2026Permit IssuedIntelogic ElectricGeneral Wiring
06/24/2026Permit IssuedAL-Lectric Elect'l ContractingGeneral Wiring
06/24/2026Permit IssuedAL-Lectric Elect'l ContractingGeneral Wiring
05/26/2026Permit IssuedNash Electric Services—
03/15/2026Permit IssuedCL Electrical—
12/04/2025Permit IssuedNash Electric Services—
09/05/2024CompleteRightway Electrical5 meters, 5 new_meters
11/06/2023CancelledRightway Electrical5 meters, 5 new_meters
10/27/2021CompleteIlluminous Electric—
10/27/2021CompleteIlluminous Electric—
10/26/2021CompleteRightway ElectricalGeneral Wiring
10/26/2021CompleteRightway ElectricalGeneral Wiring
10/06/2021CompleteIlluminous Electric—
04/29/2020Permit IssuedIlluminous Electric—
10/03/2018CompleteNash Electric Services—
3 projects · most recent 11/19/2025
Sidewalk Shed Fence
FiledStatusContractorScope
11/19/2025Permit IssuedEfin ManagementFence
11/19/2025Permit IssuedRepublic Scaffold & HoistSidewalk Shed
03/06/2023Permit IssuedPlatinum Services NYSidewalk Shed
▾Field Inspections (DOB CAP) — 20
DateTypeResultReport
08/18/2026Pass-Final CND-Occupancy InspectionPassView ↗
08/03/2026Certified StandPipe - SD - Alarm Sys 64/09 - FinishCertifiedView ↗
08/03/2026Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet)CertifiedView ↗
09/16/2024Pass-Final PL - Up to 9 Requested FloorsPassView ↗
09/06/2024Pass-Final PL - More than 10 Requested FloorsPassView ↗
08/02/2024Pass-Final Curb Cut Non-Directive 14PassView ↗
07/12/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
02/02/2024Pass-Final PL - Up to 9 Requested FloorsPassView ↗
11/24/2023Pass-Final PL - Up to 9 Requested FloorsPassView ↗
08/02/2023Pass-Final PL - More than 10 Requested FloorsPassView ↗
05/18/2023Pass-Final PL - Up to 9 Requested FloorsPassView ↗
04/06/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/17/2023Fail-Final PL - UndergroundFailView ↗
11/30/2022Pass-Final PL - Up to 9 Requested FloorsPassView ↗
11/04/2022Pass-Final PL - Up to 9 Requested FloorsPassView ↗
09/27/2022Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
09/20/2022Pass-Final PL - Up to 9 Requested FloorsPassView ↗
09/12/2022Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
08/31/2022Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
08/19/2022Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 70
DateRequirementInspectorRole
09/23/2026Post-installed Anchors—special
07/22/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationZHUANG MIAOspecial
07/22/2026Fire-Resistant Penetrations and JointsZHUANG MIAOspecial
07/14/2026Fire-Resistant Penetrations and JointsRUCI LINspecial
07/14/2026Post-installed AnchorsRUCI LINspecial
06/29/2026Fire-Resistant Penetrations and JointsZHUANG MIAOspecial
06/29/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationZHUANG MIAOspecial
06/29/2026Lowest Floor Elevation—progress
04/29/2026Standpipe SystemsRUCI LINspecial
04/29/2026Sprinkler SystemsRUCI LINspecial
03/30/2026Standpipe SystemsRUCI LINspecial
12/17/2025FinalJunda Qiuprogress
12/12/2025Lowest Floor ElevationRUCI LINprogress
12/12/2023FinalJaclyn Peranteauprogress
12/12/2023Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)RUCI LINspecial
12/06/2023Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)RUCI LINspecial
12/06/2023FinalRUCI LINprogress
08/11/2023Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationRUCI LINspecial
08/04/2023Final—progress
08/04/2023Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)—special
08/04/2023Structural Stability – Alterations of existing buildings—special
07/06/2023Post-installed AnchorsZELJKO STEVANOVICspecial
06/27/2023Post-installed AnchorsZELJKO STEVANOVICspecial
09/16/2022Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationRUCI LINspecial
03/23/2022FinalRUCI LINprogress
Latest 25 of 70.
▾Documents — 480 on file (BIS + DOB NOW)
▸Plans & Drawings49
▸DOB NOWPlans/Sketch34
10/04/2026Q01457916-I1Request digital key ↗
08/29/2026Q00003132-I1Request digital key ↗
08/28/2026Q00044724-I1Request digital key ↗
Showing 3 of 34 on file for this type
▸DOB NOWPlans/Sketch - Plumbing8
08/28/2026Q00218052-I1Request digital key ↗
08/28/2026Q00218052-P2Request digital key ↗
08/28/2026Q00270559-I1Request digital key ↗
Showing 3 of 8 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems3
08/28/2026Q00279548-I1Request digital key ↗
08/28/2026Q00279558-I1Request digital key ↗
08/15/2026Q00279566-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Standpipe2
08/28/2026Q00270559-I1Request digital key ↗
08/15/2026Q00216172-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sprinkler2
08/28/2026Q00270559-I1Request digital key ↗
08/15/2026Q00216172-I1Request digital key ↗
▸Applications & Permits101
▸BISPLAN / WORK APPROVAL APPLICATION84
02/19/2026421405642Open ↗
01/27/2026421405642Open ↗
12/18/2025421405642Open ↗
Showing 3 of 84 on file for this type
▸BISWORK PERMIT APPLICATION13
01/03/2024421405642Open ↗
06/26/2020440591352Open ↗
03/31/2020440591352Open ↗
Showing 3 of 13 on file for this type
▸BISBPP-5 - Authorization to the Department of Transportation3
12/20/2023421490755Open ↗
10/06/2023421490755Open ↗
Showing 2 of 3 on file for this type
▸BISBPP-DOT: SIDEWALK/CURB/ROAD WORK PERMITS1
08/15/2024421490755Open ↗
▸Zoning, Tax Lot & Property Records16
▸BISZONING DIAGRAM7
02/02/2022421405642Open ↗
06/04/2021421405642Open ↗
11/08/2019421405642Open ↗
Showing 3 of 7 on file for this type
▸BISTAX LOT: FINAL LOT NUMBER ISSUED2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWFlood Zone Design Certification2
08/28/2026Q00044745-I1Open ↗
08/13/2026Q00044724-I1Open ↗
▸BISZONING RESOLUTION DETERMINATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED1
05/19/2023421816057Open ↗
▸BISRESTRICTION: RESTRICTIVE DECLARATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISADDRESS: NEW HOUSE NUMBER APPROVED1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISEASEMENT AND RESTRICTIVE DECLARATIONS - SUPPPORTING DOCUMENTATION1
12/28/2017421405642Open ↗
▸Seals & Professional Certifications103
▸DOB NOWDPL-1: Design Professional Seal & Signature47
10/04/2026Q01457916-I1Open ↗
08/28/2026Q00044745-I1Open ↗
08/28/2026Q00216172-I1Open ↗
Showing 3 of 47 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature17
09/01/2026Q01394823-I1Open ↗
09/01/2026Q07994079-P1Open ↗
09/01/2026Q01380117-I1Open ↗
Showing 3 of 17 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION12
03/26/2020421405642Open ↗
03/04/2020421757254Open ↗
11/08/2019421405642Open ↗
Showing 3 of 12 on file for this type
▸BISAPPLICANT OWNER SIGNATURE7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸DOB NOWProgress Inspector Seal & Signature7
09/25/2026Q01336164-I1Open ↗
08/29/2026Q00705020-I1Open ↗
08/29/2026Q00044745-I1Open ↗
Showing 3 of 7 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT5
03/31/2020440591352Open ↗
10/10/2018440514864Open ↗
10/10/2018440514855Open ↗
Showing 3 of 5 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY3
03/31/2020440591352Open ↗
10/10/2018440514864Open ↗
10/10/2018440514855Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION3
03/31/2020440591352Open ↗
10/10/2018440514864Open ↗
10/10/2018440514855Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST2
07/02/2018421649880Open ↗
Showing 1 of 2 on file for this type
▸Trade Schedules & Equipment14
▸BISSCHEDULE B - PLUMBING8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
07/02/2018421649880Open ↗
▸BISSEWER CONNECTION: DEP SD1 & SD21
01/30/2018421405642Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
10/16/2019421405642Open ↗
▸DOB NOWStandpipe Alarms Drawings1
08/13/2026Q00705020-I1—
▸Safety & Tenant Protection9
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE3
01/31/2018421405642Open ↗
01/31/2018421405642Open ↗
01/31/2018421405642Open ↗
▸BISSTREET TREE CHECKLIST3
05/06/2022421490755Open ↗
Showing 1 of 3 on file for this type
▸BISSTREET TREES SITE PLAN2
10/06/2023421490755Open ↗
07/21/2023421405642Open ↗
▸BISSTREET TREE SUPPORTING DOCUMENT1
01/18/2018421405642Open ↗
▸Energy Compliance9
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS5
11/08/2019421405642Open ↗
09/09/2019421405642Open ↗
05/07/2018421405642Open ↗
Showing 3 of 5 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
08/31/2020421757254Open ↗
Showing 1 of 3 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Inspections & Test Reports23
▸BISTECHNICAL REPORT: RESPONSIBILITY13
07/10/2023421405642Open ↗
08/31/2020421757254Open ↗
03/31/2020440591352Open ↗
Showing 3 of 13 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX4
11/10/2018421405642Open ↗
11/10/2018421405642Open ↗
11/10/2018421405642Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: PILE DRIVING2
08/09/2023421405642Open ↗
03/26/2020421405642Open ↗
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
01/31/2018421405642Open ↗
▸BISTECHNICAL REPORT: SOIL INSPECTION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISBPP: FIELD INSPECTION1
08/15/2024421490755Open ↗
▸DOB NOWHydrant Flow Test Letter1
08/15/2026Q00216172-I1Open ↗
▸Approvals, Objections & Sign-offs67
▸BISSCHEDULE A - OCCUPANCY / USE31
08/07/2023421405642Open ↗
02/02/2022421405642Open ↗
11/16/2021421405642Open ↗
Showing 3 of 31 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION28
08/15/2024421490755Open ↗
12/11/2023421490755Open ↗
05/22/2023421816057Open ↗
Showing 3 of 28 on file for this type
▸BISSUPERSEDING LETTER2
01/03/2024421405642Open ↗
05/24/2018421405642Open ↗
▸BISCONSTRUCTION CODE DETERMINATION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISDOB APPROVAL FOR NEW CC2
08/15/2024421490755Open ↗
12/11/2023421490755Open ↗
▸BISBPP-8 - Request Items for Builders Pavement Plan Signoff1
08/15/2024421490755Open ↗
▸BISCURB CUT (CC) SIGNOFF1
08/07/2024421490755Open ↗
▸Cost, Insurance & Ownership13
▸BISCOST AFFIDAVIT6
08/31/2020421757254Open ↗
07/02/2018421649880Open ↗
07/02/2018421649880Open ↗
Showing 3 of 6 on file for this type
▸BISPROJECT-SPECIFIC GL INSURANCE4
01/03/2024421405642Open ↗
11/14/2019421405642Open ↗
11/12/2019421405642Open ↗
Showing 3 of 4 on file for this type
▸BISDEPT OF FINANCE VERIFICATION2
05/19/2023421816057Open ↗
Showing 1 of 2 on file for this type
▸DOB NOWPW3: Cost Affidavit (Before Sign Off)1
08/13/2026Q00003132-I1Open ↗
▸Filing & Intake Forms53
▸BISADDITIONAL INFORMATION19
01/14/2026421405642Open ↗
05/22/2023421816057Open ↗
02/02/2022421405642Open ↗
Showing 3 of 19 on file for this type
▸BISEFILING COVER SHEET18
07/27/2023421816057Open ↗
03/04/2020421757254Open ↗
07/03/2018421649880Open ↗
Showing 3 of 18 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET10
03/31/2020440591352Open ↗
10/10/2018440514864Open ↗
10/10/2018440514855Open ↗
Showing 3 of 10 on file for this type
▸BISBOROUGH INTAKE FORM4
01/03/2024421405642Open ↗
07/27/2023421816057Open ↗
04/27/2020421405642Open ↗
Showing 3 of 4 on file for this type
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT32
10/06/2023421490755Open ↗
Showing 1 of 2 on file for this type
▸Other Documents18
▸BISPLOT DIAGRAM2
05/19/2023421816057Open ↗
Showing 1 of 2 on file for this type
▸BISRECORDS MGMT FEE PAYMENT RECEIPT2
05/19/2023421816057Open ↗
05/06/2022421490755Open ↗
▸DOB NOWLowest Floor Elevation Plan2
08/28/2026Q00218052-I1Open ↗
08/25/2026Q00235544-I1Open ↗
▸DOB NOWFlood Hazard Area Substantial Improvement Calculation2
08/28/2026Q00044745-I1Open ↗
08/13/2026Q00044724-I1Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
05/06/2022421490755Open ↗
▸BISCURB CUT: PROVIDE EXISTING NUMBER1
12/11/2023421490755Open ↗
▸BISBPP: TOPOGRAPHIC SURVEY1
12/11/2023421490755Open ↗
▸BISBPP-PARKS: PLANT NEW TREE1
08/15/2024421490755Open ↗
▸BISNYS DEC TIDAL WETLANDS MAP1
05/06/2022421490755Open ↗
▸BISBPP: FINAL AS-BUILT PHOTOGRAPHS1
08/15/2024421490755Open ↗
▸BISBPP: PHOTOS-SIGNED/SEALED BY APPLICANT1
12/11/2023421490755Open ↗
▸BISBPP: AS-BUILT SIDEWALK SURVEY1
08/15/2024421490755Open ↗
▸DOB NOWFEMA Elevation Certificate (086-0-33)/Flood Proofing Certificate (086-0-34)1
08/13/2026Q00235544-I1Open ↗
▸DOB NOWHydraulic Calculations1
08/15/2026Q00216172-I1Open ↗