← Back
Two family converted from one family
131-09 130 STREET
QUEENS · South Ozone Park · BIN 4255503
💬 Discuss this project
1950Year Built
2Stories
B3Building Class
R3-2Zoning
—Gross Floor Area
2Units
Two family converted from one family · 0.62 FAR built · Flood zone X500
Locations of Work
No floor-level scope or drawing coverage on file for this building.
Nothing on file for this building.
Nothing on file for this building.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
BISOTISSUEDPRO CUSTOM SOLAR LLC02/18/2020
BIS—ISSUEDGOLDSMITH CONST. CORP09/14/2006
2 projects · most recent 12/13/2023
General Wiring
FiledStatusContractorScope
12/13/2023CompleteRAY JAY & A ELECTRIC CORPGeneral Wiring
02/19/2020CompleteISLAND ELECTRIC CORP—
Nothing on file for this building.
▾Documents — 39 on file (BIS + DOB NOW)
▸Applications & Permits7
▸BISPLAN / WORK APPROVAL APPLICATION6
10/13/2021402451306Open ↗
06/17/2021402451306Open ↗
02/14/2020440585680Open ↗
Showing 3 of 6 on file for this type
▸BISWORK PERMIT APPLICATION1
02/14/2020440585680Open ↗
▸Zoning, Tax Lot & Property Records2
▸BISVERIFY TAX LOT1
12/07/2021402451306Open ↗
▸BISCO OBJ: VERIFY ADDRESS-TOPO STAMP1
12/07/2021402451306Open ↗
▸Seals & Professional Certifications4
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
02/14/2020440585680Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
02/14/2020440585680Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
06/14/2018402451306Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
02/14/2020440585680Open ↗
▸Safety & Tenant Protection1
▸BISTENANT PROTECTION PLAN AND NOTES1
02/14/2020440585680Open ↗
▸Environmental & Asbestos1
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
02/14/2020440585680Open ↗
▸Energy Compliance6
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
07/15/2020440585680Open ↗
02/14/2020440585680Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
07/15/2020440585680Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
02/14/2020440585680Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (FINAL)1
08/17/2020440585680Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
02/14/2020440585680Open ↗
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: RESPONSIBILITY3
12/08/2021402451306Open ↗
07/15/2020440585680Open ↗
02/14/2020440585680Open ↗
▸Approvals, Objections & Sign-offs5
▸BISUtility Company PV System Interconnection Acknowledgement Letter2
07/15/2020440585680Open ↗
07/15/2020440585680Open ↗
▸BISSCHEDULE A - OCCUPANCY / USE2
10/22/2021402451306Open ↗
10/13/2021402451306Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
07/15/2020440585680Open ↗
▸Cost, Insurance & Ownership3
▸BISCOST AFFIDAVIT2
07/15/2020440585680Open ↗
02/14/2020440585680Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
12/07/2021402451306Open ↗
▸Filing & Intake Forms6
▸BISADDITIONAL INFORMATION5
12/20/2021402451306Open ↗
10/22/2021402451306Open ↗
04/05/2019402451306Open ↗
Showing 3 of 5 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET1
02/14/2020440585680Open ↗
▸Other Documents1
▸BISPLOT DIAGRAM1
12/07/2021402451306Open ↗