| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/02/2023 | $600K | — | Private party → 131-22 111TH AVENUE LLC | $340/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| BAYSIDE ENGINEERING PC | 6 | 02/10/2025 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ANNMARIE KHAN & ANDRE KHA | General Contractor | 2 | 07/08/2026 |
| HORBRIDGE PLUMBING & HEATING | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SD TESTING & INSPECTION S | 7010 | 5 | 02/10/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | HORBRIDGE PLUMBING & HEAT | 12/02/2024 |
| DOB NOW | General Construction | Permit Issued | ANNMARIE KHAN & ANDRE KHA | 09/12/2024 |
| DOB NOW | Construction Fence | Permit Issued | ANNMARIE KHAN & ANDRE KHA | 08/27/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/27/2024 | Permit Issued | TRINCITY ELECTRIC, INC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/10/2026 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 08/10/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/27/2026 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 03/09/2026 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 07/21/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/20/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/14/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/19/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/19/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 11/12/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/25/2025 | High Temperature Hot Water Piping (Welding) | XIUCHENG LI | special |
| 02/25/2025 | Fire-Resistant Penetrations and Joints | XIUCHENG LI | special |
| 02/25/2025 | Seismic Resistance of Plumbing, Mechanical, Fuel Gas, and Electrical Components | XIUCHENG LI | special |
| 02/25/2025 | High-Pressure Fuel-Gas Piping (Welding) | XIUCHENG LI | special |
| 02/25/2025 | Energy Code Compliance Inspections | XIUCHENG LI | progress |
| 02/25/2025 | Permanent certificate | XIUCHENG LI | energy_progress |
| 02/25/2025 | Maintenance information | XIUCHENG LI | energy_progress |
| 02/25/2025 | HVAC-R and service water heating equipment | XIUCHENG LI | energy_progress |
| 02/25/2025 | HVAC-R and service water piping design and insulation | XIUCHENG LI | energy_progress |
| 02/25/2025 | HVAC-R and service water heating system controls | XIUCHENG LI | energy_progress |
| 01/22/2025 | HVAC-R and service water heating system controls | XIUCHENG LI | energy_progress |
| 01/22/2025 | High Temperature Hot Water Piping (Welding) | XIUCHENG LI | special |
| 01/22/2025 | High-Pressure Fuel-Gas Piping (Welding) | XIUCHENG LI | special |
| 01/22/2025 | Seismic Resistance of Plumbing, Mechanical, Fuel Gas, and Electrical Components | XIUCHENG LI | special |
| 01/22/2025 | Energy Code Compliance Inspections | XIUCHENG LI | progress |
| 01/22/2025 | Fire-Resistant Penetrations and Joints | XIUCHENG LI | special |
| 01/22/2025 | HVAC-R and service water piping design and insulation | XIUCHENG LI | energy_progress |
| 01/22/2025 | Maintenance information | XIUCHENG LI | energy_progress |
| 01/22/2025 | HVAC-R and service water heating equipment | XIUCHENG LI | energy_progress |
| 01/22/2025 | Permanent certificate | XIUCHENG LI | energy_progress |
| 01/22/2025 | Insulation placement and R values | XIUCHENG LI | energy_progress |
| 01/22/2025 | Electric vehicle service equipment requirements | XIUCHENG LI | energy_progress |
| 01/22/2025 | Interior lighting power | XIUCHENG LI | energy_progress |
| 01/22/2025 | Fenestration and door U-factor and product ratings | XIUCHENG LI | energy_progress |
| 01/22/2025 | Air barrier - visual inspection | XIUCHENG LI | energy_progress |