← Back
Elevator apt, miscellaneous
131 WEST 129 STREET
MANHATTAN · Harlem (North) · BIN 1057980
💬 Discuss this project
1905Year Built
6Stories
D9Building Class
R7-2Zoning
27,339 sfGross Floor Area
13Units
LL97 CoveredRent Stabilized52 Open Violations 50 unresolved · 2 paperwork only ▸
Elevator apt, miscellaneous · Owner of record: NYC HOUSING PRESERVATION AND DEVELOPMENT · 7,494 sf lot · 3.65 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionCivilGeneral
Filed — no permit issued92p · 4 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
HPD403/21/2026
BLESSED TRINITY CHURCH203/21/2026
CITY OF NEW YORK (NYCDDC)203/21/2026
NYC HOUSING PRESERVATION AND DEVELOPMENT103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
P. M. ARCHITECTURE, PC704/13/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
PM ARCHITECTURE PC1203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
FRANK MERESHENSKYElectrical203/21/2026
JANKUC, JONELElectrical103/21/2026
DONOHUE, MICHAELElectrical103/21/2026
KEITH ECHEVARRIAElectrical103/21/2026
MCCLARIN, LEROYElectrical103/21/2026
NUNEZ, JOSEElectrical103/21/2026
JOSE NUNEZElectrical103/21/2026
Building Lifecycle
All (157)Filed (7)Violation (60)Objection (60)Special Inspection (30)
09/03/2026
Objection resolved — Addressed
09/03/2026
Objection resolved — Addressed
07/15/2026
Objection resolved — Addressed
07/15/2026
Objection resolved — Addressed
07/15/2026
Objection resolved — Addressed
05/19/2026
Special inspection requirement — Insulation placement and R values
05/15/2026
Objection raised — Other
05/15/2026
Objection raised — Other
05/07/2026
Objection raised — Other
05/07/2026
Objection raised — Other
04/20/2026
Objection raised — Other
04/20/2026
Objection raised — Other
04/20/2026
Objection resolved — Addressed
04/13/2026
Filed — Alteration CO
SUBSTANTIAL RENOVATION OF 6 STORY+ CELLAR APT. BUILDING. FIRE AND OTHER SEPARATE TRADES TO BE UNDER SEPARATE FILING. TO SUPERSEDE EXPIRED JOB 121208950
M01370797-I1
03/13/2026
Special inspection requirement — Maintenance information
03/13/2026
Special inspection requirement — Exterior lighting power
03/13/2026
Special inspection requirement — Metering
03/13/2026
Special inspection requirement — Fenestration air leakage
03/13/2026
Special inspection requirement — Interior lighting power
03/13/2026
Special inspection requirement — Subgrade Inspections
03/13/2026
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
03/13/2026
Special inspection requirement — Air barrier - visual inspection
03/13/2026
Special inspection requirement — Lighting controls
03/13/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
03/13/2026
Special inspection requirement — Lighting in dwelling units
03/13/2026
Special inspection requirement — Electrical motors and elevators
03/13/2026
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
03/11/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
03/11/2026
Special inspection requirement — Fire-Resistance Rated Construction
03/11/2026
Special inspection requirement — Concrete - Cast-In-Place
03/11/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
03/11/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
03/11/2026
Special inspection requirement — Masonry
03/11/2026
Special inspection requirement — Energy Code Compliance Inspections
01/12/2026
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/18/2024
Special inspection requirement — Heating Systems
06/18/2024
Special inspection requirement — HVAC-R and service water heating equipment
06/18/2024
Special inspection requirement — HVAC-R and service water heating system controls
06/18/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
06/12/2024
Objection resolved — Addressed
06/12/2024
Special inspection requirement — HVAC-R and service water heating equipment
06/12/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
06/12/2024
Special inspection requirement — HVAC-R and service water heating system controls
04/23/2024
Objection resolved — Addressed
04/22/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
04/22/2024
Special inspection requirement — Sprinkler Systems
04/15/2024
Objection resolved — Addressed
04/01/2024
Objection raised — Other
03/29/2024
Objection raised — Other
03/28/2024
Objection raised — Other
03/22/2024
Filed — Alteration
Install of (2) new boilers, expansion tank, pumps, and piping in conjunction with alt 1 filing . Decommission existing boilers at 131 West 129th Street
M00648040-P2
03/22/2024
Filed — Alteration
New mechanical work for new kit./bath exhausts, convectors, supply and return piping. All work in conjunction with Alt 1 filing 121208950 and plumbing/sprinkler filing M00516962-I1 . Work on floors includes cellar,001-006 and roof.
M00449135-P1
03/22/2024
Filed — Alteration
Provide all new plumbing fixtures,sprinkler riser,sprinkler heads, with new stacks, risers, and piping in a 6 story+ cellar apartment building. In conjunction to Alt 1 filing 121208950, and mechanical filing M00449135-I1.
M00516962-P1
02/06/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
03/16/2023
Violation issued (HPD, closed)
A
03/16/2022
Objection raised — Other
03/16/2022
Objection resolved — Addressed
02/16/2022
Violation issued (HPD, closed)
A
02/15/2022
Objection raised — Energy
02/15/2022
Objection resolved — Addressed
Latest 60 of 157 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
BISOTISSUEDRESHPAL SINGH08/01/2011
BISOTISSUEDPATTI CONSTRUCTION CORP09/03/2003
BISOTISSUEDSEAMAN M. CONST. CORP03/28/2001
BISOTISSUEDB & C CONSTRUCTION04/13/2000
BISOTISSUEDLAKHI GENERAL CONTRACTOR06/01/1998
BISPLISSUEDEDWARD ESBIN & SONS03/05/1996
1 project · most recent 03/22/2024
Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
03/22/2024——Heating Systems, Ventilation Systems
Heating
A.O. Smith BTH 250 240,000 BTU · Water Heater ×4
Ventilation
Panasonic FV-10NLF1 105 CFM · Kitchen Exhaust ×38
FV-10NLFI 30 CFM · Exhaust Fan ×2
Greenheck LFC-15L-FC 450 CFM · Kitchen Exhaust ×2
Pennbarry MODEL DX-11R 430 CFM · Exhaust Fan ×2
1 project · most recent 03/22/2024
FiledStatusContractorScope
03/22/2024——670 heads
1 project · most recent 03/22/2024
Gas Storm Water/Sanitary
FiledStatusContractorScope
03/22/2024——Gas, Storm, Water/Sanitary
▾Special Inspection Requirements (DOB NOW) — 33
DateRequirementInspectorRole
05/19/2026Insulation placement and R values—energy_progress
03/13/2026Maintenance information—energy_progress
03/13/2026Exterior lighting power—energy_progress
03/13/2026Metering—energy_progress
03/13/2026Fenestration air leakage—energy_progress
03/13/2026Interior lighting power—energy_progress
03/13/2026Subgrade Inspections—special
03/13/2026Subsurface Investigations (Borings/Test Pits)—special
03/13/2026Air barrier - visual inspection—energy_progress
03/13/2026Lighting controls—energy_progress
03/13/2026Fenestration and door U-factor and product ratings—energy_progress
03/13/2026Lighting in dwelling units—energy_progress
03/13/2026Electrical motors and elevators—energy_progress
03/13/2026Excavations - Sheeting, Shoring, and Bracing—special
03/11/2026Structural Stability – Alterations of existing buildings—special
03/11/2026Fire-Resistance Rated Construction—progress
03/11/2026Concrete - Cast-In-Place—special
03/11/2026Exterior Insulation and Finish Systems (EIFS)—special
03/11/2026Fire-Resistant Penetrations and Joints—special
03/11/2026Masonry—special
03/11/2026Energy Code Compliance Inspections—progress
06/18/2024Heating Systems—special
06/18/2024HVAC-R and service water heating equipment—energy_progress
06/18/2024HVAC-R and service water heating system controls—energy_progress
06/18/2024HVAC-R and service water piping design and insulation—energy_progress
Latest 25 of 33.
▾Documents — 82 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch5
09/02/2026M00648040-I1Request digital key ↗
08/17/2026M01370797-I1Request digital key ↗
08/15/2026M00516962-I1Request digital key ↗
Showing 3 of 5 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems2
08/15/2026M00449135-I1Request digital key ↗
08/14/2026M00449135-P1Request digital key ↗
▸Applications & Permits9
▸BISPLAN / WORK APPROVAL APPLICATION8
07/17/2023121208950Open ↗
01/24/2023121208950Open ↗
11/10/2022121208950Open ↗
Showing 3 of 8 on file for this type
▸BISWORK PERMIT APPLICATION1
08/08/2011120700170Open ↗
▸Zoning, Tax Lot & Property Records2
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED1
06/30/2021121208950Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/17/2026M01370797-I1Open ↗
▸Seals & Professional Certifications10
▸DOB NOWDPL-1: Design Professional Seal & Signature7
09/02/2026M00648040-I1Open ↗
09/02/2026M00648040-P2Open ↗
08/27/2026M00516962-I1Open ↗
Showing 3 of 7 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
05/25/2011120700170Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
05/25/2011120700170Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY-CERTIFICATION1
05/25/2011120700170Open ↗
▸Safety & Tenant Protection3
▸BISSTREET TREE CHECKLIST2
06/30/2021121208950Open ↗
06/30/2021121208950Open ↗
▸BISTPP1: TENANT PROTECTION PLAN1
06/30/2021121208950Open ↗
▸Environmental & Asbestos2
▸BISTHIS IS NOT AN ASBESTOS PROJECT2
05/25/2011120700170Open ↗
05/25/2011120700170Open ↗
▸Energy Compliance2
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
07/29/2021121208950Open ↗
07/28/2021121208950Open ↗
▸Inspections & Test Reports7
▸BISTECHNICAL REPORT: RESPONSIBILITY2
07/17/2023121208950Open ↗
07/28/2021121208950Open ↗
▸BISSOIL REPORT1
07/12/2023121208950Open ↗
▸BISTECHNICAL REPORT: SOIL INSPECTION1
07/12/2023121208950Open ↗
▸BISSUBSURFACE / SOILS INVESTIGATION (BORINGS/TEST PITS)1
07/12/2023121208950Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/17/2026M01370797-I1Open ↗
▸DOB NOWSOIL REPORT1
08/17/2026M01370797-I1Open ↗
▸Approvals, Objections & Sign-offs32
▸BISLETTERS - SUPPORTING DOCUMENTATION12
07/12/2023121208950Open ↗
07/28/2021121208950Open ↗
07/28/2021121208950Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter7
09/02/2026M00648040-I1Open ↗
08/15/2026M00516962-I1Open ↗
08/14/2026M00648040-P2Open ↗
Showing 3 of 7 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE6
07/17/2023121208950Open ↗
01/24/2023121208950Open ↗
11/10/2022121208950Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)5
09/02/2026M00648040-I1Open ↗
08/17/2026M01370797-I1Open ↗
08/14/2026M00648040-P2Open ↗
Showing 3 of 5 on file for this type
▸BISDESIGN COMM. APPROVAL: CITY-OWNED PROPERTY (EXTERIOR WORK)1
06/30/2021121208950Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
05/25/2011120700170Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
07/28/2021121208950Open ↗
05/25/2011120700170Open ↗
▸Filing & Intake Forms5
▸BISADDITIONAL INFORMATION3
07/28/2021121208950Open ↗
07/28/2021121208950Open ↗
07/28/2021121208950Open ↗
▸BISeFiling Job Application Cover Sheet1
05/25/2011120700170Open ↗
▸BISEFILING COVER SHEET1
07/28/2021121208950Open ↗
▸Other Documents1
▸BISPLOT DIAGRAM1
07/28/2021121208950Open ↗