| Firm | Filings | Most Recent |
|---|---|---|
| JAMES V MORRI | 4 | 05/29/2026 |
| A TECH ENGINEERING NYC, PLLC. | 1 | 06/24/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| JAMES V MORRI, RA | 3 | 03/21/2026 |
| A TECH ENGINEERING NYC | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JACOBSON CONTRACTING,INC | General Contractor | 2 | 04/09/2026 |
| FIVE BOROUGH NYC LLC | Fire Protection | 1 | 06/28/2026 |
| ALISON PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| JAMES V MORRI, RA | 1042 | 2 | 05/29/2026 |
| A TECH ENGINEERING NYC, P | 6738 | 1 | 06/24/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Signed-off | JACOBSON CONTRACTING,INC | 09/18/2025 |
| DOB NOW | Sprinklers | Permit Issued | FIVE BOROUGH NYC LLC | 07/03/2025 |
| DOB NOW | Plumbing | Permit Issued | ALISON PLBG & HTG INC | 06/12/2025 |
| DOB NOW | Structural | Permit Issued | JACOBSON CONTRACTING,INC | 03/17/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/24/2025 | Permit Issued | FIVE BOROUGH NYC LLC | 58 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/29/2026 | Permit Issued | ALISON PLBG & HTG INC | Water/Sanitary |
| 06/24/2025 | — | — | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/20/2025 | Complete | LMS ELECTRICAL CORP | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 02/10/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/31/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/29/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/29/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/31/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/24/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/15/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/10/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/10/2025 | Certified Sprinkler - SP - Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/22/2026 | Fire-Resistant Penetrations and Joints | James Morri | special |
| 05/22/2026 | Insulation placement and R values | James Morri | energy_progress |
| 05/22/2026 | Lighting controls | James Morri | energy_progress |
| 05/22/2026 | Fenestration areas | James Morri | energy_progress |
| 05/22/2026 | Fenestration air leakage | James Morri | energy_progress |
| 05/22/2026 | Air barrier - visual inspection | James Morri | energy_progress |
| 05/22/2026 | Air barrier — testing | James Morri | energy_progress |
| 05/22/2026 | Fenestration and door U-factor and product ratings | James Morri | energy_progress |
| 05/22/2026 | Structural Wood Frame | James Morri | progress |
| 05/22/2026 | Preliminary | James Morri | progress |
| 05/22/2026 | Fire-Resistance Rated Construction | James Morri | progress |
| 05/22/2026 | Final | James Morri | progress |
| 05/22/2026 | Energy Code Compliance Inspections | James Morri | progress |
| 05/22/2026 | Subgrade Inspections | James Morri | special |
| 05/22/2026 | Masonry | James Morri | special |
| 05/29/2025 | Sprinkler Systems | anthony santoro | special |
| 03/03/2025 | Masonry | James Morri | special |
| 03/03/2025 | Subgrade Inspections | James Morri | special |
| 10/21/2024 | Fenestration air leakage | James Morri | energy_progress |
| 10/21/2024 | Fenestration and door U-factor and product ratings | James Morri | energy_progress |
| 10/21/2024 | Air barrier - visual inspection | James Morri | energy_progress |
| 10/21/2024 | Fenestration areas | James Morri | energy_progress |
| 10/21/2024 | Air barrier — testing | James Morri | energy_progress |
| 10/21/2024 | Structural Wood Frame | James Morri | progress |
| 10/21/2024 | Preliminary | James Morri | progress |