← Back
Two family converted from one family
1319 EAST 54 STREET
BROOKLYN · Flatlands · BIN 3217972
💬 Discuss this project
1940Year Built
1Stories
B3Building Class
R4Zoning
1,540 sfGross Floor Area
2Units
Two family converted from one family · 2,225 sf lot · 0.69 FAR built · Flood zone X500
Locations of Work
Electrical
Permit Issued — active, not yet Signed-off
RoofUnder Construction2 filings · 11 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR103/31/2026
SQUARE ARCH, LLC104/04/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
KAMTECH RESTORATION CORP203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
KAMTECH RESTORATION CORPGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281103/31/2026
SQ. ARCH, LLC4802104/04/2025
Building Lifecycle
All (4)Filed (2)Permit Issued (2)
04/09/2026
Permit issued — Solar
B01380778-I1-SL
03/31/2026
Filed — Alteration
installation of solar panels, rooftop, railed, grid-tied, 11 modules, 4.51 KW
B01380778-I1
04/15/2025
Permit issued — Solar
B01203104-I1-SL
04/04/2025
Filed — Alteration
ROOFTOP SOLAR INSTALLATION. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
B01203104-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedMOMENTUM SOLAR04/09/2026
DOB NOWSolarPermit IssuedKAMTECH RESTORATION CORP04/15/2025
2 projects · most recent 03/31/2026
FiledStatusContractorScope
03/31/2026Permit IssuedISLAND ELECTRIC CORP—
03/25/2025Permit IssuedBERGER QUALITY ELEC'L CON—
2 projects · most recent 03/31/2026
FiledStatusContractorScope
03/31/2026Permit IssuedMOMENTUM SOLAR11 panels, 4.51 kw, 193 roof_area_sqft
04/04/2025Permit IssuedKAMTECH RESTORATION CORP12 panels, 5.52 kw, 759.5 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 6
DateRequirementInspectorRole
03/31/2026Fire-Resistant Penetrations and JointsMina Makarspecial
03/31/2026Adhesive-Based Solar Pedestal Bonding SystemsMina Makarspecial
03/31/2026Post-installed AnchorsMina Makarspecial
03/31/2026Energy Code Compliance InspectionsMina Makarprogress
03/31/2026FinalMina Makarprogress
03/31/2026Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 11 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/22/2026B01203104-I1Request digital key ↗
08/17/2026B01380778-I1Request digital key ↗
▸Seals & Professional Certifications7
▸DOB NOWSpecial Inspector Seal & Signature3
08/27/2026B01380778-I1Open ↗
08/27/2026B01380778-I1Open ↗
08/27/2026B01380778-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/22/2026B01203104-I1Open ↗
08/17/2026B01380778-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/27/2026B01380778-I1Open ↗
08/27/2026B01380778-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/22/2026B01203104-I1Open ↗
08/17/2026B01380778-I1Open ↗