1935Year Built
2Stories
A5Building Class
R4-1Zoning
1,216 sfGross Floor Area
1Units
Rent Stabilized7 Open Violations ▸FDNY Report ↗
One family attached or semi-detached · 2,000 sf lot · 0.61 FAR built · Flood zone X
Locations of Work
Architecture
Cellar2p · 1 filing · 3 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
04/29/2025$780K—— → Private party$641/sf building
01/17/2019$641K—Private party → Private party$527/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
KV LAMBIRIS ARCHITECT204/30/2023
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
PASSEGGIO PLBG & HTG CORP.Plumbing107/08/2026
Building Lifecycle
All (28)Filed (2)Permit Issued (1)Signed Off (1)Violation (11)Inspection (5)Objection (8)
12/08/2025
Violation issued (ECB, closed)
Construction
11/25/2025
Violation issued (HPD, open)
I
12/05/2024
Violation issued (HPD, open)
I
03/22/2024
Signed off — Alteration
PLUMBING WORK IN CONJUNCTION WITH APPLICATION # Q00671805. TO CORRECT ECB VIOLATIONS 39083754X, 39083753Y
Q00866980-I1
02/09/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
02/08/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/12/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
01/12/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/12/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
01/08/2024
Permit issued — Plumbing
Q00866980-I1-PL
11/29/2023
Violation issued (HPD, open)
I
05/04/2023
Objection raised — Inspections
05/04/2023
Objection resolved — Addressed
05/04/2023
Objection raised — Other
05/04/2023
Objection resolved — Addressed
05/04/2023
Objection raised — Admin
05/04/2023
Objection resolved — Addressed
05/04/2023
Objection raised — Scope
05/04/2023
Objection resolved — Addressed
04/30/2023
Filed — Alteration
PLUMBING WORK IN CONJUNCTION WITH APPLICATION # Q00671805. TO CORRECT ECB VIOLATIONS 39083754X, 39083753Y
Q00866980-I1
04/30/2023
Filed — Alteration
Q00671805-I1
04/13/2023
Violation issued (ECB, closed)
Construction
04/13/2023
Violation issued (ECB, closed)
Construction
11/18/2022
Violation issued (HPD, open)
I
03/17/2022
Violation issued (HPD, open)
I
04/21/2021
Violation issued (HPD, open)
I
11/07/2019
Violation issued (HPD, open)
I
01/09/2018
Violation issued (HPD, closed)
I
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offSAFEWAY PLUMBING & HEATIN01/08/2024
1 project · most recent 03/10/2024
General Wiring
FiledStatusContractorScope
03/10/2024CompleteMAGIC ELECTRIC INCGeneral Wiring
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
02/09/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
02/08/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/12/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
01/12/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/12/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Documents — 6 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/24/2026Q00866980-I1Request digital key ↗
08/24/2026Q00671805-I1Request digital key ↗
▸Seals & Professional Certifications2
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/24/2026Q00671805-I1Open ↗
08/13/2026Q00866980-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/24/2026Q00671805-I1Open ↗