| Owner | Filings | Most Recent |
|---|---|---|
| LEFKO CAPITAL GROUP | 3 | 09/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| BMG DESIGN BUILD LLC | 5 | 08/24/2026 |
| ELEVATED ENGINEERING NYC | 4 | 03/26/2026 |
| VASILIOS ARTEMIOU PE | 4 | 12/05/2025 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| LEAD IT BUILDERS, LLC | General Contractor | 1 | 09/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 10 | 08/24/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Permit Issued | LEAD IT BUILDERS, LLC | 09/21/2026 |
| DOB NOW | Plumbing | Permit Issued | B&B MECH PLBG & HTG LLC | 05/06/2026 |
| DOB NOW | Structural | Permit Issued | LEAD IT BUILDERS, LLC | 05/01/2026 |
| DOB NOW | Sprinklers | Permit Issued | TARGET PIPING NY LLC | 05/01/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | LEAD IT BUILDERS, LLC | 05/01/2026 |
| DOB NOW | General Construction | Permit Issued | LEAD IT BUILDERS, LLC | 02/12/2026 |
| DOB NOW | Foundation | Permit Issued | LEAD IT BUILDERS, LLC | 02/12/2026 |
| DOB NOW | Support of Excavation | Permit Issued | LEAD IT BUILDERS, LLC | 02/12/2026 |
| DOB NOW | Construction Fence | Signed-off | LEAD IT BUILDERS, LLC | 01/16/2026 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/24/2026 | Permit Issued | LEAD IT BUILDERS, LLC | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Amana PTH093J30 9,000 BTU · Ptac ×67 PTH153J30 14,400 BTU · Ptac ×38 PTH073J30 7,000 BTU · Ptac ×11 PTH123J30 11,600 BTU · Ptac ×6 PBH073G35CC 7,200 BTU ×5 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/24/2026 | Permit Issued | TARGET PIPING NY LLC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/24/2026 | Permit Issued | TARGET PIPING NY LLC | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/24/2026 | Permit Issued | POWER DIRECT ELECTRIC INC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/24/2026 | Permit Issued | LEAD IT BUILDERS, LLC | Steel, Concrete, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/24/2026 | Permit Issued | LEAD IT BUILDERS, LLC | Fence |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/24/2026 | Permit Issued | LEAD IT BUILDERS, LLC | Earthwork |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/18/2026 | Maintenance information | SHAHRIAR QUAYYUM | energy_progress |
| 08/18/2026 | Exterior lighting power | SHAHRIAR QUAYYUM | energy_progress |
| 08/18/2026 | Lighting in dwelling units | SHAHRIAR QUAYYUM | energy_progress |
| 08/18/2026 | Electrical motors and elevators | SHAHRIAR QUAYYUM | energy_progress |
| 08/18/2026 | Fenestration and door U-factor and product ratings | SHAHRIAR QUAYYUM | energy_progress |
| 08/18/2026 | Air barrier — testing | SHAHRIAR QUAYYUM | energy_progress |
| 08/18/2026 | Protection of exposed foundation insulation | SHAHRIAR QUAYYUM | energy_progress |
| 08/18/2026 | Fenestration air leakage | SHAHRIAR QUAYYUM | energy_progress |
| 08/18/2026 | Interior lighting power | SHAHRIAR QUAYYUM | energy_progress |
| 08/18/2026 | Metering | SHAHRIAR QUAYYUM | energy_progress |
| 08/18/2026 | Lighting controls | SHAHRIAR QUAYYUM | energy_progress |
| 08/18/2026 | Exterior Insulation and Finish Systems (EIFS) | SHAHRIAR QUAYYUM | special |
| 08/18/2026 | Fire-Resistant Penetrations and Joints | SHAHRIAR QUAYYUM | special |
| 08/18/2026 | Energy Code Compliance Inspections | SHAHRIAR QUAYYUM | progress |
| 08/18/2026 | Fire-Resistance Rated Construction | SHAHRIAR QUAYYUM | progress |
| 08/18/2026 | Insulation placement and R values | SHAHRIAR QUAYYUM | energy_progress |
| 08/18/2026 | Fenestration areas | SHAHRIAR QUAYYUM | energy_progress |
| 08/18/2026 | Air barrier - visual inspection | SHAHRIAR QUAYYUM | energy_progress |
| 05/26/2026 | Protection of exposed foundation insulation | SHAHRIAR QUAYYUM | energy_progress |
| 05/26/2026 | Metering | SHAHRIAR QUAYYUM | energy_progress |
| 05/26/2026 | Interior lighting power | SHAHRIAR QUAYYUM | energy_progress |
| 05/26/2026 | Insulation placement and R values | SHAHRIAR QUAYYUM | energy_progress |
| 05/26/2026 | Exterior Insulation and Finish Systems (EIFS) | SHAHRIAR QUAYYUM | special |
| 05/26/2026 | Fenestration and door U-factor and product ratings | SHAHRIAR QUAYYUM | energy_progress |
| 05/26/2026 | Exterior lighting power | SHAHRIAR QUAYYUM | energy_progress |