| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/20/2024 | $560K | — | — → — | $565/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| KOJO SIMPSON ARCHITECT | 1 | 09/17/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| KNIGHTVISION8555 | 2 | 03/21/2026 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/17/2025 | Complete | STRONG ISLAND ELEC. LLC | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/19/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | — | special |
| 09/16/2025 | Structural Stability – Alterations of existing buildings | — | special |
| 09/16/2025 | Energy Code Compliance Inspections | — | progress |
| 09/16/2025 | Fire-Resistance Rated Construction | — | progress |
| 09/16/2025 | Air barrier - visual inspection | — | energy_progress |
| 09/16/2025 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 09/16/2025 | Lighting in dwelling units | — | energy_progress |
| 09/16/2025 | Insulation placement and R values | — | energy_progress |
| 09/16/2025 | Fire-Resistant Penetrations and Joints | — | special |
| 09/16/2025 | Fenestration areas | — | energy_progress |