← Back
One story - permanent living quarter
133-37 128 STREET
QUEENS · South Ozone Park · BIN 4256117
💬 Discuss this project
1935Year Built
1Stories
A2Building Class
R3-2Zoning
910 sfGross Floor Area
1Units
3 Open Violations 2 unresolved · 1 paperwork only ▸FDNY Report ↗
One story - permanent living quarter · Owner of record: JABR 116 LLC · 4,000 sf lot · 0.23 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralElectricalMechanical
Permit Issued — active, not yet Signed-off
Floor 2Under Construction8p · 1 filing · 15 docs
Floor 1Under Construction9p · 1 filing · 15 docs
CellarUnder Construction11p · 1 filing · 15 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
08/27/2021$650K—Private party → JABR 116 LLC$714/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ARCHITECTURAL CONCEPT605/21/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ARCHITECTUAL CONCEPT1003/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
K-LASH CONSTRUCTION CORPGeneral Contractor603/21/2026
BAY RIDGE STAR CONSTRUCTGeneral Contractor107/29/2026
NEW J.D. GEN. CONSTR. INCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ARCHITECTURAL CONCEPT3642205/21/2026
Building Lifecycle
All (85)Filed (6)Permit Issued (4)Signed Off (1)Violation (8)Objection (38)Special Inspection (28)
09/08/2026
Violation issued (ECB, open)
Unknown
09/08/2026
Violation issued (ECB, open)
Construction
07/28/2026
Permit issued — Foundation
Q01167845-I1-GC-CX
07/14/2026
Objection resolved — Resolved
06/29/2026
Objection raised — Cost
05/21/2026
Filed — Alteration
Install new plumbing fixtures, sprinkler system and related piping as per drawing.
Q01167846-S1
04/15/2026
Objection resolved — Resolved
04/15/2026
Objection resolved — Resolved
04/15/2026
Objection resolved — Resolved
04/15/2026
Objection resolved — Resolved
04/15/2026
Objection resolved — Resolved
03/23/2026
Objection raised — Cost
02/22/2026
Violation issued (ECB, open)
Construction
02/09/2026
Objection resolved — Addressed
02/05/2026
Objection resolved — Addressed
02/02/2026
Objection resolved — Addressed
02/02/2026
Objection resolved — Addressed
02/02/2026
Objection resolved — Addressed
12/19/2025
Permit issued — General Construction
Q01167845-I1-GC-CX
10/28/2025
Objection resolved — Addressed
10/24/2025
Objection raised — Admin
10/03/2025
Objection resolved — Addressed
08/25/2025
Objection resolved — Addressed
08/04/2025
Signed off — Full Demolition
Application filled to full demolition of existing one family dwelling house.
Q01164102-I1
07/22/2025
Permit issued — Full Demolition
Q01164102-I1-FD
06/05/2025
Permit issued — Construction Fence
Q01164107-I1-FN
03/27/2025
Objection raised — Fire_Protection
03/27/2025
Objection raised — Fire_Protection
03/27/2025
Objection raised — Fire_Protection
03/27/2025
Objection raised — Plumbing
03/27/2025
Objection raised — Fire_Protection
03/27/2025
Objection raised — Fire_Protection
03/27/2025
Objection raised — Plumbing
03/27/2025
Objection raised — Fire_Protection
03/27/2025
Objection raised — Fire_Protection
03/18/2025
Filed — Alteration
Install new plumbing fixtures, sprinkler system and related piping as per drawing.
Q01167846-I1
03/11/2025
Filed — Full Demolition
Application filled to full demolition of existing one family dwelling house.
Q01164102-I1
03/07/2025
Filed — Alteration
Q01167847-I1
03/07/2025
Filed — Alteration
APPLICATION FILED TO INSTALL TEMPORARY CONSTRUCTION FENCE.
Q01164107-I1
03/04/2025
Objection resolved — Addressed
03/04/2025
Objection resolved — Addressed
03/04/2025
Objection resolved — Addressed
03/04/2025
Objection resolved — Addressed
03/04/2025
Objection resolved — Addressed
02/14/2025
Objection raised — Zoning
02/14/2025
Objection raised — Zoning
02/14/2025
Objection raised — Zoning
02/14/2025
Objection raised — Structural
02/14/2025
Objection raised — Zoning
02/14/2025
Objection raised — Scope
02/14/2025
Objection raised — Energy
01/30/2025
Filed — New Building
Proposed new two family house.
Q01167845-I1
01/27/2025
Special inspection requirement — Heating Systems
MUZAFFAR JAMAL
01/27/2025
Special inspection requirement — Duct leakage testing, insulation and design
MUZAFFAR JAMAL
01/16/2025
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
MUZAFFAR JAMAL
01/16/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
MUZAFFAR JAMAL
01/16/2025
Special inspection requirement — Masonry
MUZAFFAR JAMAL
01/16/2025
Special inspection requirement — Subgrade Inspections
MUZAFFAR JAMAL
01/16/2025
Special inspection requirement — Wood – Prefabricated I-Joists
MUZAFFAR JAMAL
01/16/2025
Special inspection requirement — Final
Syed Naqvi
Latest 60 of 85 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWFoundationPermit IssuedBAY RIDGE STAR CONSTRUCT07/28/2026
DOB NOWGeneral ConstructionPermit IssuedNEW J.D. GEN. CONSTR. INC12/19/2025
DOB NOWFull DemolitionSigned-offK-LASH CONSTRUCTION CORP07/22/2025
DOB NOWConstruction FencePermit IssuedK-LASH CONSTRUCTION CORP06/05/2025
1 project · most recent 01/30/2025
Air Conditioning Systems Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
01/30/2025Permit IssuedBAY RIDGE STAR CONSTRUCTAir Conditioning Systems, Heating Systems, Ventilation Systems
Cooling
Goodman MBVC1601AA-1 4 tons · Furnace ×2
Heating
A.O. Smith UPVA 18K Water Heater ×1
Rheem PROPH80 T2 RH375-15 Water Heater ×1
Ventilation
Greenheck SP-C50-QD 50 CFM · Exhaust Fan ×5
SP-B90 100 CFM · Exhaust Fan ×2
1 project · most recent 05/21/2026
FiledStatusContractorScope
05/21/2026——25 heads
1 project · most recent 05/21/2026
Plumbing-Sprinkler Storm Water/Sanitary
FiledStatusContractorScope
05/21/2026——Plumbing-Sprinkler, Storm, Water/Sanitary
1 project · most recent 05/10/2026
General Wiring
FiledStatusContractorScope
05/10/2026Permit IssuedACCURATE ELEC'L CORP.General Wiring
1 project · most recent 01/30/2025
Wood
FiledStatusContractorScope
01/30/2025Permit IssuedBAY RIDGE STAR CONSTRUCTWood
1 project · most recent 03/07/2025
Fence
FiledStatusContractorScope
03/07/2025Permit IssuedK-LASH CONSTRUCTION CORPFence
1 project · most recent 01/30/2025
Earthwork
FiledStatusContractorScope
01/30/2025Permit IssuedBAY RIDGE STAR CONSTRUCTEarthwork
▾Special Inspection Requirements (DOB NOW) — 28
DateRequirementInspectorRole
01/27/2025Heating SystemsMUZAFFAR JAMALspecial
01/27/2025Duct leakage testing, insulation and designMUZAFFAR JAMALenergy_progress
01/16/2025Excavations - Sheeting, Shoring, and BracingMUZAFFAR JAMALspecial
01/16/2025Fire-Resistant Penetrations and JointsMUZAFFAR JAMALspecial
01/16/2025MasonryMUZAFFAR JAMALspecial
01/16/2025Subgrade InspectionsMUZAFFAR JAMALspecial
01/16/2025Wood – Prefabricated I-JoistsMUZAFFAR JAMALspecial
01/16/2025FinalSyed Naqviprogress
01/16/2025Footing and FoundationMUZAFFAR JAMALprogress
01/16/2025Energy Code Compliance InspectionsMUZAFFAR JAMALprogress
01/16/2025Fire-Resistance Rated ConstructionMUZAFFAR JAMALprogress
01/16/2025Insulation placement and R valuesMUZAFFAR JAMALenergy_progress
01/16/2025Fenestration areasMUZAFFAR JAMALenergy_progress
01/16/2025Air barrier — testing MUZAFFAR JAMALenergy_progress
01/16/2025Permanent certificateMUZAFFAR JAMALenergy_progress
01/16/2025Air barrier - visual inspectionMUZAFFAR JAMALenergy_progress
01/16/2025HVAC-R and service water heating equipmentMUZAFFAR JAMALenergy_progress
01/16/2025Ventilation and air distribution systemMUZAFFAR JAMALenergy_progress
01/16/2025Fenestration air leakageMUZAFFAR JAMALenergy_progress
01/16/2025HVAC-R and service water heating system controlsMUZAFFAR JAMALenergy_progress
01/16/2025Electric vehicle service equipment requirementsMUZAFFAR JAMALenergy_progress
01/16/2025HVAC-R and service water piping design and insulationMUZAFFAR JAMALenergy_progress
01/16/2025Interior lighting powerMUZAFFAR JAMALenergy_progress
01/16/2025Fenestration and door U-factor and product ratingsMUZAFFAR JAMALenergy_progress
01/16/2025Maintenance informationMUZAFFAR JAMALenergy_progress
Latest 25 of 28.
▾Documents — 44 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
08/21/2026Q01167845-I1Request digital key ↗
08/20/2026Q01164107-I1Request digital key ↗
08/20/2026Q01167847-I1Request digital key ↗
Showing 3 of 6 on file for this type
▸Applications & Permits1
▸BISPLAN / WORK APPROVAL APPLICATION1
07/17/2025440822987Open ↗
▸Zoning, Tax Lot & Property Records2
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026Q01167845-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026Q01167845-I1Open ↗
▸Seals & Professional Certifications12
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/20/2026Q01164107-I1Open ↗
08/20/2026Q01167847-I1Open ↗
08/16/2026Q01167846-S1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWProgress Inspector Seal & Signature3
08/22/2026Q01167845-I1Open ↗
08/22/2026Q01167845-I1Open ↗
08/22/2026Q01167845-I1Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
07/17/2025440822987Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
07/17/2025440822987Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/22/2026Q01167845-I1Open ↗
▸Trade Schedules & Equipment4
▸DOB NOWElectric Cut-Off1
08/13/2026Q01164102-I1Open ↗
▸DOB NOWWater Cut-Off1
08/13/2026Q01164102-I1Open ↗
▸DOB NOWGas Cut-Off1
08/13/2026Q01164102-I1Open ↗
▸DOB NOWSewer Cut-Off1
08/13/2026Q01164102-I1Open ↗
▸Safety & Tenant Protection3
▸BISSTREET TREE CHECKLIST1
07/17/2025440822987Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026Q01167845-I1Open ↗
▸DOB NOWStreet Tree Checklist1
08/13/2026Q01167845-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWRodent Control1
08/13/2026Q01164102-I1Open ↗
▸Inspections & Test Reports2
▸BISCONCRETE - CAST-IN-PLACE1
07/17/2025440822987Open ↗
▸DOB NOWGeotechnical Report (BC 1803.6)1
08/13/2026Q01167845-I1Open ↗
▸Filing & Intake Forms2
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
07/17/2025440822987Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
07/17/2025440822987Open ↗
▸Other Documents11
▸BISBPP - SUPPORTING DOCUMENTATION2
07/17/2025440822987Open ↗
07/17/2025440822987Open ↗
▸DOB NOWProperty Ownership Certification2
08/13/2026Q01167845-I1Open ↗
08/13/2026Q01164102-I1Open ↗
▸BISRECORDS MGMT FEE PAYMENT RECEIPT1
07/17/2025440822987Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026Q01167845-I1Open ↗
▸DOB NOWCommunity Board Notification1
08/13/2026Q01164102-I1Open ↗
▸DOB NOWFull Demo: 10-Day Notice1
08/13/2026Q01164102-I1Open ↗
▸DOB NOWStructure Photographs1
08/13/2026Q01164102-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026Q01167845-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026Q01167845-I1Open ↗