ArchitecturePlumbingStructural
Issued Permit Scope
Plumbing · Structural
Structural plans filed herewith to show tank replacement in kind; no additional loads considered. No change to use, egress, or occupancy.
On file for this project
6 documents
Baruch College, Admin. Bldg., Exterior faade repairs as per the plans filed including: Removal & replacement of crack/spall masonry units, steel lintel, window glazing & glass block, sealant and louvers.
On file for this project
6 documents · 1 drawing sheet
INSTALL NEW 6 FIRE SERVICE PIPPING, BACK-FLOW PREVENTER, FLOOR DRAIN, REPLACE BOOSTER PUMP RELATED PIPPING AT CELLAR LEVEL. INSTALL NEW 8000 GALLON FIRE/DOMESTIC WATER HOUSE TANK. CONTRACTOR TO INSTALL TEMPORARY TANKS FOR TEMPORARY DOMESTIC SUPPLY
On file for this project
19 documents
DMFire ProtectionMechanicalPlumbing
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers
INSTALL NEW 6 FIRE SERVICE AND PIPPING AND CONECT TO EXISTING FIRE DEPARTMENT CONNECTION AND FIRE CONTROL VALVE ASSEMBLY
On file for this project
21 documents · 4 drawing sheets
INSTALL NEW 6 FIRE SERVICE PIPPING, BACK-FLOW PREVENTER, FLOOR DRAIN, REPLACE BOOSTER PUMP RELATED PIPPING AT CELLAR LEVEL. INSTALL NEW 8000 GALLON FIRE/DOMESTIC WATER HOUSE TANK. CONTRACTOR TO INSTALL TEMPORARY TANKS FOR TEMPORARY DOMESTIC SUPPLY
On file for this project
19 documents · 3 drawing sheets
ArchitectureMechanicalPlumbingOther
Issued Permit Scope
General Construction · Plumbing · Sidewalk Shed
Baruch College, Admin. Bldg., Exterior faade repairs as per the plans filed including: Removal & replacement of crack/spall masonry units, steel lintel, window glazing & glass block, sealant and louvers.
On file for this project
6 documents · 4 drawing sheets
INSTALL NEW 6 FIRE SERVICE PIPPING, BACK-FLOW PREVENTER, FLOOR DRAIN, REPLACE BOOSTER PUMP RELATED PIPPING AT CELLAR LEVEL. INSTALL NEW 8000 GALLON FIRE/DOMESTIC WATER HOUSE TANK. CONTRACTOR TO INSTALL TEMPORARY TANKS FOR TEMPORARY DOMESTIC SUPPLY
On file for this project
19 documents · 12 drawing sheets
INSTALLATION OF NEW SIDEWALK SHED AT 133 EAST 22ND STREET, MANHATTAN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
3 documents · 3 drawing sheets