| Owner | Filings | Most Recent |
|---|---|---|
| NYC Department of Design and Construction | 15 | 07/08/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Jose Alcala Architect | 1 | 02/19/2025 |
| Dose Engineering | 2 | 02/07/2025 |
| Robert W. de Bruin | 1 | 02/04/2025 |
| Severud Associates Consulting Engineering | 1 | 01/29/2025 |
| Ricardo Zurita Architecture & Plann | 1 | 01/28/2025 |
| Ivan Brice Architecture | 2 | 05/06/2024 |
| Ashraf | 2 | 02/20/2024 |
| Cameron Engineering | 3 | 12/07/2022 |
| New York & Company | 2 | 10/23/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| NYC Department of Design and Construction | 6 | 03/21/2026 |
| AC Building Consultants | 4 | 03/21/2026 |
| Rennon Construction | 2 | 03/21/2026 |
| Noel Building Consulting | 6 | 03/21/2026 |
| New York & Company | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| C. D. E. Air-Conditioning | General Contractor | 6 | 07/08/2026 |
| Sea Breeze General Construction | General Contractor | 6 | 07/08/2026 |
| Rennon Construction | Scaffold | 3 | 07/08/2026 |
| RJ Bruno | Plumbing | 2 | 07/08/2026 |
| Kevin Keaveny Electric Co | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Universal Testing and Ins | 400 | 2 | 05/06/2024 |
| Ase Engineering | 5785 | 2 | 06/06/2022 |
| New York Engineering Associates | 851 | 1 | 10/23/2020 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | Robert Michael Des & Cont | 06/25/2024 |
| DOB NOW | General Construction | Signed-off | Robert Michael Des & Cont | 03/13/2024 |
| DOB NOW | General Construction | Signed-off | Robert Michael Des & Cont | 02/21/2024 |
| DOB NOW | Construction Fence | Signed-off | Rennon Construction | 02/21/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | Rennon Construction | 02/16/2024 |
| DOB NOW | General Construction | Signed-off | Robert Michael Des & Cont | 02/05/2024 |
| DOB NOW | Structural | Signed-off | C. D. E. Air-Conditioning | 12/26/2023 |
| DOB NOW | Mechanical Systems | Signed-off | C. D. E. Air-Conditioning | 12/26/2023 |
| DOB NOW | Structural | Signed-off | C. D. E. Air-Conditioning | 01/25/2023 |
| DOB NOW | Mechanical Systems | Signed-off | C. D. E. Air-Conditioning | 01/25/2023 |
| DOB NOW | Boiler Equipment | Signed-off | RJ Bruno | 10/30/2020 |
| DOB NOW | Plumbing | Permit Issued | RJ Bruno | 10/13/2020 |
| BIS | BL | ISSUED | Varsity Plumbing & Heating | 02/09/2016 |
| BIS | PL | ISSUED | Varsity Plumbing & Heating | 02/09/2016 |
| BIS | BL | ISSUED | Varsity Plumbing & Heating | 12/23/2014 |
| BIS | PL | ISSUED | Varsity Plumbing & Heating | 12/23/2014 |
| BIS | MH | ISSUED | RP Cooling | 03/30/2012 |
| BIS | MH | ISSUED | JMK Construction Group | 04/01/2008 |
| BIS | OT | ISSUED | JMK Construction Group | 04/01/2008 |
| BIS | OT | ISSUED | JMK Construction Group | 04/01/2008 |
| BIS | PL | ISSUED | CN Plumbing | 06/28/2004 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/06/2022 | Signed-off | C. D. E. Air-Conditioning | Air Conditioning Systems | Cooling |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/19/2025 | — | — | Water/Sanitary |
| 10/23/2020 | Signed-off | Prestige Plumbing & Heating | Gas |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/19/2024 | Complete | High Quality Electric of | — |
| 01/26/2023 | Complete | Interphase Electric | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/19/2025 | — | — | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/19/2025 | — | — | 44 panels, 19.58 kw, 1,587 roof_area_sqft |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/13/2025 | Structural Stability – Alterations of existing buildings | — | special |
| 01/13/2025 | Fire-Resistant Penetrations and Joints | — | special |
| 01/13/2025 | Energy Code Compliance Inspections | — | progress |
| 01/13/2025 | Final | — | progress |
| 01/13/2025 | Air barrier - visual inspection | — | energy_progress |
| 01/10/2025 | Fire-Resistant Penetrations and Joints | — | special |
| 01/08/2025 | Lighting controls | — | energy_progress |
| 01/08/2025 | Fenestration air leakage | — | energy_progress |
| 01/08/2025 | Fenestration areas | — | energy_progress |
| 01/08/2025 | Interior lighting power | — | energy_progress |
| 01/08/2025 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 01/08/2025 | Concrete - Cast-In-Place | — | special |
| 01/08/2025 | Post-installed Anchors | — | special |
| 01/08/2025 | Structural Steel - Details | — | special |
| 01/08/2025 | Structural Steel - High Strength Bolting | — | special |
| 01/08/2025 | Final | — | progress |
| 01/08/2025 | Structural Steel - Welding | — | special |
| 01/08/2025 | Final | — | progress |
| 01/08/2025 | Fire-Resistance Rated Construction | — | progress |
| 01/08/2025 | Energy Code Compliance Inspections | — | progress |
| 01/08/2025 | Fire-Resistant Penetrations and Joints | — | special |
| 01/08/2025 | Exterior lighting power | — | energy_progress |
| 05/16/2024 | Structural Stability – Alterations of existing buildings | NELSON LOPEZ | special |
| 05/16/2024 | Masonry | NELSON LOPEZ | special |
| 05/16/2024 | Energy Code Compliance Inspections | NELSON LOPEZ | progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Queens Public Library | Government / Civic | Cellar, Floor 1, Penthouse, Roof | Project Q01164461 Project Q00713526 Project Q00713569 |
| Laurelton Branch Library | Government / Civic | — | Project Q01005496 |