| Owner | Filings | Most Recent |
|---|---|---|
| Myrtle Development | 26 | 07/08/2026 |
| Eden Group NY | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 02/24/2026 | $1.3M | — | EDEN GROUP NY LLC → Private party | $831/sf building |
| 06/24/2024 | $950K | — | Private party → EDEN GROUP NY LLC | $594/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| Pirooz Engineering | 7 | 09/25/2025 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| NCR Construction | General Contractor | 4 | 04/09/2026 |
| NCR Construction | Scaffold | 4 | 07/08/2026 |
| Anc Contracting Co in | General Contractor | 1 | 03/21/2026 |
| Somal Home Improvements.i | General Contractor | 1 | 04/09/2026 |
| Infiniti Esc Plumbing | Plumbing | 1 | 07/08/2026 |
| Branch Plumbing | Plumbing | 1 | 06/05/2013 |
| J & P Pool | General Contractor | 1 | 05/21/2013 |
| T. Adoona PLG | Plumbing | 1 | 04/05/1993 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Pirooz Engineering | 7177 | 5 | 09/25/2025 |
| Triangle Inspection & Tes | 7495 | 2 | 09/25/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| BIS | OT | ISSUED | A.N.C. Contracting | 03/22/2016 |
| BIS | PL | ISSUED | Branch Plumbing | 06/05/2013 |
| BIS | OT | ISSUED | J & P Pool | 05/21/2013 |
| BIS | PL | ISSUED | Water Works Piping | 04/05/1993 |
| BIS | — | ISSUED | Jim Young Construction | 03/09/1993 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/25/2025 | Signed-off | NCR Construction | Heating and Air Conditioning Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/25/2025 | Signed-off | Infiniti Esc Plumbing | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/25/2025 | Signed-off | NCR Construction | Concrete, Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/25/2025 | Signed-off | NCR Construction | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/22/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | PIROOZ SOLTANIZADEH | special |
| 12/22/2025 | HVAC-R and service water heating equipment | PIROOZ SOLTANIZADEH | energy_progress |
| 12/22/2025 | Maintenance information | PIROOZ SOLTANIZADEH | energy_progress |
| 12/22/2025 | HVAC-R and service water heating system controls | PIROOZ SOLTANIZADEH | energy_progress |
| 12/22/2025 | HVAC-R and service water piping design and insulation | PIROOZ SOLTANIZADEH | energy_progress |
| 12/22/2025 | Energy Code Compliance Inspections | PIROOZ SOLTANIZADEH | progress |
| 12/22/2025 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | Rajasekhar Sakhamuri | special |
| 12/22/2025 | Fire-Resistant Penetrations and Joints | PIROOZ SOLTANIZADEH | special |
| 09/24/2025 | Permanent certificate | PIROOZ SOLTANIZADEH | energy_progress |
| 09/24/2025 | Structural Stability – Alterations of existing buildings | PIROOZ SOLTANIZADEH | special |
| 09/24/2025 | Subsurface Investigations (Borings/Test Pits) | Rajasekhar Sakhamuri | special |
| 09/24/2025 | Energy Code Compliance Inspections | PIROOZ SOLTANIZADEH | progress |
| 09/24/2025 | Final | NAVEEN KUMAR | progress |
| 09/24/2025 | Fire-Resistance Rated Construction | PIROOZ SOLTANIZADEH | progress |
| 09/24/2025 | Footing and Foundation | PIROOZ SOLTANIZADEH | progress |
| 09/24/2025 | Preliminary | PIROOZ SOLTANIZADEH | progress |
| 09/24/2025 | Structural Wood Frame | PIROOZ SOLTANIZADEH | progress |
| 09/24/2025 | Ventilation and air distribution system | PIROOZ SOLTANIZADEH | energy_progress |
| 09/24/2025 | Metering | PIROOZ SOLTANIZADEH | energy_progress |
| 09/24/2025 | HVAC-R and service water piping design and insulation | PIROOZ SOLTANIZADEH | energy_progress |
| 09/24/2025 | Fenestration and door U-factor and product ratings | PIROOZ SOLTANIZADEH | energy_progress |
| 09/24/2025 | Insulation placement and R values | PIROOZ SOLTANIZADEH | energy_progress |
| 09/24/2025 | Duct leakage testing, insulation and design | PIROOZ SOLTANIZADEH | energy_progress |
| 09/24/2025 | HVAC-R and service water heating system controls | PIROOZ SOLTANIZADEH | energy_progress |
| 09/24/2025 | HVAC-R and service water heating equipment | PIROOZ SOLTANIZADEH | energy_progress |